Lumino EPC order book rises to Rs 1,963 crore in H1 FY27
Key highlights
- Lumino’s EPC order book was Rs 1,963 crore in H1 FY27, up from Rs 738 crore in FY24.
- EPC accounted for about 68% of Lumino’s combined Rs 2,885 crore H1 FY27 order book.
- Lumino secured orders worth Rs 386 crore between 30 September and 1 November 2026.
- Lumino was L1 in tenders worth Rs 555 crore as of 1 November 2026.
powered by IRIS

Lumino reported an EPC order book of Rs 1,963 crore in H1 FY27, Rs 1,225 crore above its Rs 738 crore FY24 balance and about 68% of its combined Rs 2,885 crore EPC and manufacturing backlog. The EPC balance was Rs 29 crore below FY26, while manufacturing orders declined to Rs 922 crore.
Know Lumino Industries inside out
Results, valuation, peers and who's buying, in one view.
How has Lumino’s EPC order book changed since FY24?
Lumino’s EPC order book increased from Rs 738 crore in FY24 to Rs 1,963 crore in H1 FY27, equivalent to growth of about 166% over the period. The balance rose by Rs 608 crore in FY25 and by a further Rs 646 crore in FY26, before declining by Rs 29 crore in H1 FY27 from the FY26 level.
Lumino’s EPC order-book coverage increased from 1,015 days in FY24 to 1,176 days in FY26, then moderated to 1,019 days in H1 FY27. Manufacturing coverage moved in the other direction, falling from 476 days in FY24 to 202 days in H1 FY27; Lumino states that its H1 FY27 day ratios are annualised.
Why is EPC Lumino’s largest order-book segment?
EPC was Lumino’s largest reported order-book segment in H1 FY27 because its Rs 1,963 crore balance was more than twice the Rs 922 crore manufacturing order book. The two segments totalled Rs 2,885 crore, with EPC accounting for about 68% based on the reported segment balances.
The mix changed from FY24, when manufacturing orders of Rs 1,203 crore exceeded the Rs 738 crore EPC order book. By H1 FY27, EPC was Rs 1,225 crore above its FY24 level, while manufacturing was Rs 281 crore below its FY24 balance. The combined order book of Rs 2,885 crore was also Rs 265 crore below the Rs 3,150 crore reported in FY26.
Which projects support Lumino’s EPC order book?
Lumino identifies three ongoing EPC projects with a combined stated value of Rs 431 crore: a Rs 209 crore Revamped Distribution Sector Scheme, or RDSS, project in Baramulla, Jammu and Kashmir; a Rs 128 crore 400/220 kilovolt substation in Udaipur, Rajasthan; and a Rs 94 crore 11 kilovolt Medium Voltage Covered Conductor project in Jamnagar, Gujarat. Lumino does not present these projects as a complete breakdown of the Rs 1,963 crore EPC order book.
Lumino’s completed-project examples include a Rs 694 crore RDSS project in Kanpur, a Rs 91 crore underground-cable project in Patan and a Rs 24 crore 220 kilovolt substation in Agra. Its engineering, procurement and construction, or EPC, work spans substations, power transmission and distribution, and High Temperature Low Sag, or HTLS, re-conductoring. Lumino says it has completed 55 distribution projects covering about 80,000 circuit kilometres, including a 64 circuit-kilometre, 220 kilovolt HTLS project at Sirhind, Punjab.
Got a follow-up? Ask IRIS
What demand backdrop does Lumino identify for EPC?
Lumino identifies electricity-demand growth and network investment as the market backdrop for its EPC activity. CRISIL figures in the presentation estimate Indian power demand at 1,815 billion to 1,825 billion units in FY27P and 2,189 billion to 2,405 billion units in FY31P, implying projected compound annual growth of 5% to 7%. India’s per-capita electricity consumption is shown at 1,460 kilowatt-hours, against a world average of 3,558 kilowatt-hours.
The presentation also cites a Rs 3.04 lakh crore RDSS programme for state distribution companies over five years and a proposal to add 63,502 circuit kilometres of intrastate transmission lines by 2027. Green Energy Corridor phases I and II aim to connect 44 gigawatts of renewable capacity across 10 states, of which around 26 gigawatts has been integrated. These disclosed programmes form an infrastructure context for distribution, substation and conductor work rather than a forecast of Lumino’s future order intake.
What could change Lumino’s order book after H1 FY27?
Lumino disclosed that it secured Rs 386 crore of orders after 30 September 2026 and up to 1 November 2026. It also said it was L1, meaning lowest bidder, in tenders worth Rs 555 crore. The Rs 386 crore refers to secured orders, whereas the presentation does not describe the Rs 555 crore of L1 tenders as awarded work or as part of the reported H1 FY27 order book.
On the manufacturing side, Lumino plans to begin commercial production at Unit III in Ranihati from Q4 FY27 under a Rs 180 crore expansion plan. The facility is planned to add 10,000 metric tonnes in Q4 FY27, 10,000 metric tonnes in Q3 FY28 and 15,000 metric tonnes in Q1 FY29, taking the phased addition to 35,000 metric tonnes. The unit is intended to manufacture low-tension and high-tension cables for industrial and infrastructure applications.
Conclusion
Lumino’s H1 FY27 backlog shows EPC has become the larger reported order-book segment, at Rs 1,963 crore compared with Rs 922 crore in manufacturing. Although the Rs 2,885 crore combined balance was below the Rs 3,150 crore FY26 level, the EPC order book remained close to its Rs 1,992 crore FY26 balance and was Rs 1,225 crore higher than in FY24.
The next disclosed items to watch are the Rs 386 crore of orders secured through 1 November 2026, the outcome of Rs 555 crore of L1 tenders, and Unit III’s planned Q4 FY27 commercial-production start. Lumino also reported 1,019 days of annualised EPC order-book coverage in H1 FY27, which can be tracked alongside project execution and subsequent order additions.