Lumino targets 75,000 MT capacity with phased Ranihati ramp
Key highlights
- Lumino schedules 35,000 MT of Ranihati capacity in Q4 FY27, Q3 FY28 and Q1 FY29.
- The Ranihati plan would lift stated manufacturing capacity from 40,000 MT to 75,000 MT.
- Ranihati has 15 acres of land and 2.5 lakh square feet of constructed area.
- Lumino discloses Rs 180 crore and Rs 200 crore as differing capital-expenditure figures for the expansion.
powered by IRIS

Lumino Industries Limited plans to raise manufacturing capacity to 75,000 metric tonnes (MT) from 40,000 MT through a 35,000-MT Ranihati cable unit, with 10,000 MT scheduled for Q4 FY27, another 10,000 MT for Q3 FY28 and 15,000 MT for Q1 FY29.
Know Lumino Industries inside out
Results, valuation, peers and who's buying, in one view.
Why is Lumino building the Ranihati cable facility?
Lumino is building Unit III at Ranihati to add 35,000 MT of cable capacity and manufacture high-temperature (HT) power cables rated up to 66 kilovolts (kV). The presentation describes the project as serving industrial and infrastructure applications, while its proposed range includes concentric, quad, control, HT, medium-voltage covered conductor (MVCC), solar, instrumentation and railway signalling cables.
The project occupies 15 acres and has 2.5 lakh square feet of constructed area, with surplus land identified for future manufacturing expansion. Lumino acquired land at Ganesh Complex, Ranihati in 2025, and its November 2026 presentation positions the new unit as its third manufacturing facility after two existing Jangalpur units in West Bengal.
How is Lumino scheduling the 35,000-MT Ranihati ramp-up?
Lumino schedules the 35,000-MT addition in three stages: 10,000 MT in Q4 FY27, 10,000 MT in Q3 FY28 and the remaining 15,000 MT in Q1 FY29. This timetable means the facility’s stated full capacity is not scheduled until Q1 FY29, rather than becoming available in a single commissioning event.
Lumino states that commercial production is expected to commence from Q4 FY27, matching the first 10,000-MT tranche. However, an earlier expansion-plan slide says operations are to commence in phases from H2 FY28. The presentation does not explain whether Q4 FY27 refers to an initial production line, trial output or commercial output, or why the H2 FY28 wording differs.
How does Ranihati change Lumino's manufacturing footprint?
Lumino’s capacity table shows 40,000 MT across its operating Jangalpur units and 35,000 MT at the Ranihati unit under construction, for a stated total of 75,000 MT. Unit I at Jangalpur has 31,000 MT of capacity and makes overhead aluminium conductors, high-temperature low-sag (HTLS) conductors, low-tension cables and power cables; Unit II has 9,000 MT of capacity for power cables and electrical wires.
The new facility is larger by area than the existing sites combined: Ranihati is listed at 6.5 lakh square feet, versus 2.64 lakh square feet for Units I and II together. The presentation also contains a labelling inconsistency, as the heading above the same table calls this “Total FY27 Capacity of 50,000 MT across 3 Units,” while its capacity rows add to 75,000 MT and separately identify Ranihati as under construction.
The existing plants’ utilisation figures show different operating patterns before the new capacity enters service. Unit I moved from 78.9% in FY24 to 81.3% in FY25 before declining to 79.1% in FY26, while Unit II rose from 41.6% to 84.6% and then eased to 78.2%. These figures concern the 40,000-MT existing base, not the phased Ranihati capacity.
Got a follow-up? Ask IRIS
What new products and voltage capability would Ranihati provide?
Lumino says Ranihati will manufacture HT power cables up to 66 kV, extending the facility into products aimed at industrial and infrastructure uses. The company also identifies potential expansion into extra-high-voltage (EHV) cables up to 132 kV, but presents that 132-kV capability as a potential future portfolio extension rather than committed initial Ranihati output.
The planned range adds to Lumino’s existing cable portfolio, which includes low-voltage cross-linked polyethylene and polyvinyl chloride insulated power and control cables, aerial bunch cables, solar cables, railway signalling cables and an 11-kV HT cable example. Its current power-cable business also manufactures low-tension cables up to 1.1 kV, making the stated 66-kV capability a higher-voltage manufacturing plan.
Lumino links the new facility with an ability to serve export markets, although the presentation does not quantify prospective Ranihati exports or contracts. Lumino says it exports to the United States and Africa, has Underwriter Laboratories certification supporting United States and European market expansion, and completed its first cable export shipment to the United States in FY26.
What does Lumino say the Ranihati project will cost?
Lumino gives two capital-expenditure figures for the 35,000-MT project: Rs 180 crore on the dedicated Ranihati expansion slide and Rs 200 crore on the manufacturing-business expansion slide. Both figures are presented as project or planned capital expenditure, but the presentation does not reconcile the Rs 20 crore difference or specify whether either amount includes later phases, working capital or contingencies.
The scale of the stated investment can be read alongside Lumino’s H1 FY27 reported revenue of Rs 1,183 crore and cash flow from operations of Rs 56 crore. The presentation notes that cash flow from operations would have been Rs 131 crore excluding a Rs 74 crore trade-acceptance repayment, but it does not state a funding mix, debt plan or internal-accrual allocation for Ranihati.
The capacity plan also sits beside manufacturing and engineering, procurement and construction (EPC) order books reported as of September 30, 2026. Lumino reported a Rs 922 crore manufacturing order book and a Rs 1,963 crore EPC order book, but it does not identify how much of the manufacturing order book is for products planned at Ranihati or contingent on its commissioning.
Conclusion
Lumino’s disclosed plan is a phased 35,000-MT move into a larger Ranihati cable platform, taking stated capacity from 40,000 MT to 75,000 MT while adding planned HT cable capability up to 66 kV. The project would also provide 6.5 lakh square feet of facility area, compared with 2.64 lakh square feet across the two operating Jangalpur units.
The next disclosed milestones are the first 10,000 MT in Q4 FY27, the second tranche in Q3 FY28 and the final 15,000 MT in Q1 FY29. Readers should watch for management clarification of the differing Rs 180 crore and Rs 200 crore capital-expenditure figures, the Q4 FY27 versus H2 FY28 commissioning language, and the table heading that describes FY27 capacity as 50,000 MT despite rows totalling 75,000 MT.