Ratnaveer plans five CCL lines, nearly 50% capacity covered
Max Plan at ₹4,999/yr₹8,999
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Ratnaveer plans five CCL lines with combined annual installed capacity of 79.2 lakh sheets.
- Ratnaveer expects the first CCL line to commence operations in February 2027 and the fifth in June 2028.
- Ratnaveer says commitments and orders cover nearly 50% of planned CCL capacity.
- Ratnaveer projects CCL revenue of Rs 2,004.75 crore and EBITDA of Rs 519.10 crore in FY29.
powered by IRIS

Ratnaveer Precision Engineering Limited plans a five-line Copper Clad Laminate (CCL) facility with annual installed capacity of 79.2 lakh sheets, and says customer commitments and orders cover nearly 50% of that planned capacity before the first line is expected to commence operations in February 2027. The full five-line rollout is scheduled through June 2028.
Know Ratnaveer Precision Engineering inside out
Results, valuation, peers and who's buying, in one view.
What capacity will Ratnaveer’s CCL plant have?
Ratnaveer’s proposed CCL facility will have annual installed capacity of approximately 79.2 lakh sheets across five production lines. Each line is planned to provide approximately 15.84 lakh sheets a year, so annual capacity is intended to rise in equal increments as the company installs and commissions additional lines.
CCL is an electronic-grade material used in the Printed Circuit Board, or PCB, value chain. Ratnaveer has planned investment of approximately Rs 338 crore over three years for the project and describes the facility as one of India’s first integrated CCL manufacturing projects. The company links the expansion to limited domestic CCL availability and demand from Indian PCB manufacturers.
The facility remains a proposed project rather than a source of current production. Ratnaveer said its 26 November 2026 disclosure contains forward-looking statements on planned capacity, trial runs and commercial-production timing, which are subject to market conditions, customer qualification, supply-chain factors and execution timelines.
When will Ratnaveer commission its CCL production lines?
Ratnaveer expects the first CCL line to commence operations in February 2027 and the fifth line in June 2028. The plan schedules the second and third lines for September 2027 and December 2027, followed by the fourth line in March 2028.
If the timetable proceeds as planned, three lines with combined annual capacity of 47.52 lakh sheets will have commenced operations by December 2027. The remaining 31.68 lakh sheets of annual capacity are scheduled to be added through the March and June 2028 lines, creating a phased ramp-up rather than a single commissioning event.
Ratnaveer said actual results could differ materially from its plans. Its stated risks include execution timelines, market conditions, supply-chain matters and customer qualification, all of which may affect the February 2027 to June 2028 schedule.
How much CCL demand has Ratnaveer secured?
Ratnaveer says customer commitments and orders cover nearly 50% of its planned 79.2 lakh-sheet annual CCL capacity before commercial operations begin. The company also said further orders and long-term supply agreements are at an advanced stage of discussion.
The company is seeking long-term supply agreements to support the progressive use of capacity as the five lines are added between February 2027 and June 2028. Ratnaveer attributes the early customer response to a shortage of CCL availability in India and increasing demand from the domestic PCB manufacturing industry.
The filing does not name the customers, state contract values, disclose agreement durations or specify whether every commitment is binding. Ratnaveer separately identified customer qualification as a risk to its forward-looking statements, so the nearly 50% figure represents stated support for planned capacity rather than reported CCL sales or output from the not-yet-operational plant.
Got a follow-up? Ask IRIS
What financial contribution does Ratnaveer project from CCL?
Ratnaveer projects CCL revenue of Rs 49.50 crore in FY27, Rs 653.40 crore in FY28 and Rs 2,004.75 crore in FY29. The projected increase coincides with the planned move from one line commencing operations in February 2027 to all five lines scheduled to be in place by June 2028.
The CCL revenue projection of Rs 2,004.75 crore exceeds the Rs 1,909.09 crore forecast for the Stainless Steel business in FY29. This is a reversal from FY27, when CCL is projected at Rs 49.50 crore against Rs 1,364.47 crore for Stainless Steel, reflecting the planned installation of additional CCL lines while the existing segment grows at a smaller projected rate.
Ratnaveer projects CCL earnings before interest, tax, depreciation and amortisation, or EBITDA, of Rs 12.82 crore in FY27, Rs 169.19 crore in FY28 and Rs 519.10 crore in FY29. The company projects a 25.89% CCL EBITDA margin in each of the three years, while consolidated EBITDA is projected to rise from Rs 179.96 crore in FY27 to Rs 775.31 crore in FY29.
The company’s financial model projects consolidated EBITDA margin increasing from 12.73% in FY27 to 19.81% in FY29. Ratnaveer says these projections depend on execution, capacity utilisation, input costs, market conditions and other business factors and should not be construed as guaranteed future performance.
How could ECMS approval affect Ratnaveer’s CCL project?
Ratnaveer’s CCL project has received approval under the Government of India’s Electronics Component Manufacturing Scheme, or ECMS. Management said the project is eligible for a capital-expenditure subsidy on eligible project costs, subject to scheme conditions and disbursement.
Management expects the subsidy, if received, to reduce the effective capital investment burden within the planned Rs 338 crore three-year project outlay. The company also said lower funding requirements could reduce associated interest expenses and finance costs, potentially affecting project profitability and return on investment.
Ratnaveer has also onboarded a technical team with CCL manufacturing and quality-production expertise ahead of commercialisation. The filing does not quantify the ECMS subsidy, specify its disbursement schedule or state a revised project cost after any incentive, leaving those matters dependent on applicable scheme conditions.
Conclusion
Ratnaveer’s announcement combines a defined capacity plan with stated early demand coverage: five CCL lines are planned to reach 79.2 lakh sheets of annual capacity by June 2028, while customer commitments and orders cover nearly half of that capacity. Management’s model consequently projects CCL revenue of Rs 2,004.75 crore and EBITDA of Rs 519.10 crore in FY29.
The next disclosed milestones are the expected February 2027 start of the first line, the September and December 2027 additions, and the March and June 2028 installations. Progress in customer qualification, long-term supply agreements and ECMS subsidy disbursement under applicable conditions will determine how the planned capacity and projected financial contribution develop.