RULKA ELECTRICALS LTD has Rs 72.03 crore left to execute
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- REL’s November 2026 live portfolio was Rs 212.08 crore, with Rs 140.05 crore, or 66%, executed.
- REL had Rs 72.03 crore left to execute across 77 open work orders.
- Projects worth Rs 127 crore were between 1% and 75% complete.
- Eight REL work orders worth Rs 21.50 crore were awaiting client site clearances.
powered by IRIS

RULKA ELECTRICALS LTD had a Rs 212.08 crore live project portfolio in November 2026, with Rs 140.05 crore, or 66%, executed and Rs 72.03 crore remaining across 77 open work orders. The largest value was in projects below 76% completion, while Rs 21.50 crore of work awaited client site clearances.
Know Rulka Electricals inside out
Results, valuation, peers and who's buying, in one view.
What makes up REL’s live project portfolio?
REL’s November 2026 live portfolio comprised 103 work orders valued at Rs 212.08 crore, including 25 work orders worth Rs 53 crore that were 100% complete. The remaining Rs 72.03 crore was spread across 77 open orders, while executed value to date was Rs 140.05 crore. The portfolio measure therefore includes both completed and in-progress work orders.
REL’s November portfolio differs from its Rs 143.85 crore unexecuted order book at 31 March 2026. In FY26, the company reported Rs 137.87 crore of new order intake and Rs 110 crore of project execution. It then added 33 work orders worth Rs 35.15 crore between April 2026 and October 2026, while completing 25 work orders in H1 FY27.
The 31 March order book was equivalent to 1.3 times FY26 revenue, according to REL, and had a stated conversion window of three to four quarters. REL also identified more than Rs 60 crore of revenue visibility from projects that were at least 60% complete in Q1 FY27. These are order-book indicators rather than direct equivalents of the November live-portfolio total.
Where is REL’s portfolio value by completion stage?
REL’s portfolio value was concentrated in jobs that were between 1% and 75% complete, with Rs 70 crore in the 1% to 50% stage and Rs 57 crore in the 51% to 75% stage. Together, these bands contained Rs 127 crore of portfolio value, compared with Rs 28.30 crore in projects that were 76% to 99% complete.
REL reported 48 work orders at 76% completion or above, comprising 25 completed orders and 23 orders in the 76% to 99% band. The completion-stage rows list 102 work orders, whereas the portfolio summary states 103 work orders; the presentation does not explain the one-order difference. The stage values also describe total contract value, not the unexecuted balance within each band.
REL’s 31 March order-book mix helps show why project durations vary. Electrical work accounted for about 60% and typically had a three- to eight-month tenure across warehousing, retail and commercial assignments. Fire-fighting represented about 30% with tenures of three months to three years, while extra-high voltage, solar and other work made up about 10% with one- to two-year tenures.
Which states hold REL’s portfolio and execution exposure?
REL’s largest state exposure was Maharashtra, with 60 work orders worth Rs 111.22 crore that were 60% executed. Uttar Pradesh was second, with two work orders worth Rs 38.76 crore and 30% executed, while Gujarat had one Rs 30.41 crore order reported as 100% executed.
REL’s state table covers 101 work orders, two fewer than the 103 disclosed in the portfolio summary, but both disclosures show Rs 212.08 crore and 66% execution. The company did not provide a reconciliation. Maharashtra’s Rs 111.22 crore portfolio means its 60% execution rate has the largest influence on overall completion.
Execution rates varied across the disclosed states. Uttar Pradesh was 30% executed on Rs 38.76 crore, largely reflecting the Rs 34.24 crore Piramal NextGen programme, while Tamil Nadu was 17% executed on Rs 2.12 crore. In contrast, Gujarat and Rajasthan were shown as 100% executed on Rs 30.41 crore and Rs 1.93 crore respectively.
Got a follow-up? Ask IRIS
Which client programmes account for the largest work values?
REL’s largest disclosed programme was Piramal NextGen’s Rs 34.24 crore high-tension and low-tension electrical infrastructure contract at Lucknow Airport in Uttar Pradesh, which was 50% executed. REL described this aerospace-manufacturing-facility assignment as the largest contract in its portfolio and as its entry into airport work.
Speedex Corporation’s Rs 30.41 crore solar plant electrical and mechanical project in Jamnagar, Gujarat, was 100% executed. ILV Logistics Parks had two work orders worth Rs 16.26 crore that were 57% executed, while Dohale Ruby had six work orders worth Rs 14.75 crore at 59% execution. These programmes show that the largest contracts were at different points in their delivery cycle.
REL also reported Rs 14.22 crore across 12 Avenue Supermarts, or DMart, store work orders in Maharashtra, Karnataka and Rajasthan, with 67% execution. Runwal Group had two fire-fighting and electrical orders in the Mumbai Metropolitan Region worth Rs 14.42 crore at 69% execution. REL states that repeat clients contributed 65% of revenue and that it executed mechanical, electrical and plumbing work at DMart’s 450th store in India.
What could affect REL’s conversion of work into revenue?
REL identified eight work orders worth Rs 21.50 crore that were awaiting client site clearances in November 2026. That amount equals about 10% of the Rs 212.08 crore portfolio, and the presentation identifies client clearance as a dependency for those assignments rather than specifying a revised completion date.
REL separately reported seven work orders worth Rs 4.60 crore that were more than 90% complete but pending final bills. This is a different issue from site clearance: the former concerns final commercial closure of substantially completed work, while the latter concerns projects awaiting access or clearance to progress. The presentation does not state when either group will convert into revenue or cash collections.
REL reported revenue from operations of Rs 75.21 crore in H1 FY27, up 36.4% year on year from Rs 55.15 crore in H1 FY26. Net profit was Rs 3.03 crore, up 99.7% from Rs 1.52 crore. The portfolio data gives no allocation of that reported H1 FY27 revenue to individual programmes or completion-stage categories.
Conclusion
REL’s November 2026 data shows that a Rs 212.08 crore portfolio was 66% executed, with Rs 72.03 crore still open across 77 work orders. Maharashtra carried the largest state value at Rs 111.22 crore, while the Rs 127 crore held in projects between 1% and 75% completion represented the largest pool of work still moving through delivery stages.
The disclosed items to watch are the eight orders worth Rs 21.50 crore awaiting client site clearances, seven near-complete orders worth Rs 4.60 crore pending final bills, and progress on the Rs 34.24 crore Piramal NextGen contract, which was 50% executed. REL’s stated three- to four-quarter order-book conversion window provides its disclosed benchmark for later execution updates.