SPML Infra turns H1 operating cash flow positive at Rs 82.4 crore
Key highlights
- SPML Infra generated Rs 82.4 crore of operating cash flow in H1 FY27 versus a Rs 44.1 crore outflow in H1 FY26.
- Cash and cash equivalents rose 88% to Rs 119 crore at September 30, 2026, from Rs 63 crore at the end of March.
- H1 FY27 revenue was Rs 505 crore, up 45% year on year, while PAT was Rs 45 crore, up 64%.
- SPML Infra's order book was about Rs 5,056 crore at September 2026, including about Rs 1,161 crore of legacy projects.
powered by IRIS

SPML Infra Limited generated Rs 82.4 crore of operating cash flow in H1 FY27, reversing a Rs 44.1 crore outflow in H1 FY26, as management said it selected fully funded projects in cash-rich states and advanced design approvals before execution. Cash and cash equivalents rose 88% to Rs 119 crore at September 30, 2026.
Know SPML Infra inside out
Results, valuation, peers and who's buying, in one view.
Why did SPML Infra's operating cash flow turn positive?
SPML Infra said the H1 FY27 turnaround reflected a structural change in project selection rather than a one-time cash event. Management said it prioritised projects with assured funding, particularly in financially strong states, and sought adequate visibility of payment timing before bidding. It reported Rs 82.4 crore of operating cash flow for H1 FY27, against an outflow of Rs 44.1 crore a year earlier.
The company also linked cash generation to project readiness. Management said cash flow remains healthy through execution when a project is fully funded and major design and drawing approvals are in place. That approach matters for engineering, procurement and construction, or EPC, contracts because approval cycles can delay physical execution; management said new design-and-drawing projects typically take six to nine months for approvals before execution starts.
SPML Infra's bidding rules extend beyond customer funding. Management said it does not bid for contracts lacking price-variation clauses, which are intended to cover movements in commodity prices, component costs and foreign exchange rates during multiyear projects. It said this rule applies across water, power and battery energy storage system, or BESS, contracts, reducing the risk that an approved project generates cash while its economics deteriorate.
How did SPML Infra's H1 FY27 cash conversion compare with last year?
SPML Infra's operating cash flow changed by Rs 126.5 crore year on year, moving from negative Rs 44.1 crore in H1 FY26 to positive Rs 82.4 crore in H1 FY27. The change occurred alongside higher first-half revenue, earnings before interest, tax, depreciation and amortisation, or EBITDA, and profit after tax, or PAT, although the call did not provide a detailed working-capital bridge.
Cash and cash equivalents reached Rs 119 crore as of September 30, 2026, compared with Rs 63 crore at the end of March, an 88% increase. Net worth stood at Rs 1,185 crore at September 2026, supported by profit accretion and warrant conversion, according to management. These balance-sheet figures are separate from operating cash flow but show that the first-half cash result coincided with a larger reported cash balance.
The reported profit trend was also positive. In Q2 FY27, SPML Infra recorded revenue of Rs 238.7 crore, up 20% year on year, EBITDA of Rs 26.3 crore, up 33%, and PAT of Rs 22.2 crore, up 46%. EBITDA margin rose to 11% from 10%, while PAT margin was 9.3%, giving context to the Rs 505 crore H1 revenue base that produced positive operating cash flow.
Got a follow-up? Ask IRIS
Which orders and business segments support SPML Infra's cash plan?
SPML Infra's Rs 5,056 crore order book at September 2026 is increasingly composed of projects management considers better funded and higher margin. Only about Rs 1,161 crore related to legacy projects, while the balance predominantly carried expected operating margins of 10% or more, management said. It added that roughly 30% to 35% of the order book was power, including the BESS order, with the rest in water.
The Rs 1,128 crore National Thermal Power Corporation, or NTPC, BESS order is a central near-term execution item. SPML Infra said it had received design and drawing approvals and expected project revenue to begin in H2 FY27, with about Rs 300 crore of revenue expected from the contract in FY27. The company described the approval as an important milestone because it enables the transition from engineering to revenue-generating execution.
In transmission, SPML Infra received a Rs 186 crore contract from Power Grid Corporation of India for extensions of the Bhadla-III and Ramgarh substations in Rajasthan. Management said the award marks entry into the 765 kilovolt extra-high-voltage segment. In water, it said it was targeting selected projects under Jal Jeevan Mission 2.0 where funding clarity is available, while confirming it has no direct exposure to earlier Jal Jeevan Mission projects with pending payments.
Can SPML Infra sustain positive operating cash flow?
SPML Infra expects positive operating cash flow to continue as its order book increasingly consists of fully funded projects, but this is management's expectation rather than a formal quantified cash-flow forecast. The company retained guidance for at least 25% growth in revenue and profit for FY27, while saying H2 should contribute more than H1 because monsoon conditions constrained site activity in the first half.
Its order-selection discipline is the mechanism management cited for sustainability. SPML Infra said it avoids fixed-price contracts without protection against input-cost escalation and does not pursue projects without clear fund flows or expected margins of at least 10%. Management said the BESS contract includes price-variation provisions and that recent commodity-price movements had not materially affected the profitability of that project.
There are still execution and collection matters outside recurring operating cash generation. SPML Infra said it had repaid Rs 330 crore of a legacy obligation of about Rs 700 crore, with the remaining Rs 370 crore fully backed by an arbitration award of about Rs 655 crore plus accumulating interest. It also reported arbitration claims of about Rs 3,827 crore, while two matters totalling around Rs 100 crore were at an advanced stage; these are potential balance-sheet events, not reported operating cash flow.
Conclusion
SPML Infra's H1 FY27 result shows a cash-flow reversal: Rs 82.4 crore of operating cash inflow replaced a Rs 44.1 crore outflow a year earlier, while cash and cash equivalents rose to Rs 119 crore. The company attributes the shift to funded-project selection, price-variation protection and project approvals, alongside 45% H1 revenue growth to Rs 505 crore and 64% growth in PAT to Rs 45 crore.
Next, investors should watch H2 FY27 execution of the Rs 1,128 crore NTPC BESS order, from which management expects about Rs 300 crore of FY27 revenue, and whether further selected water, power and BESS orders support its Rs 5,000 crore order-inflow guidance. Management also expects progress on two arbitration matters worth around Rs 100 crore, which it said could improve liquidity and reduce debt.