SPML Infra Limited’s new orders reach 77% of order book
Key highlights
- SPML reported a ₹5,056 crore order book on September 30, 2026, with new orders accounting for 77%.
- SPML’s 10 disclosed new wins totalled ₹5,802.81 crore, including ₹4,323 crore in water and irrigation projects.
- Management expects newly secured orders to carry 10-12% margins and execute over three to four years.
- SPML’s ₹1,128 crore NTPC BESS order is due for completion within FY28.
powered by IRIS

SPML Infra Limited reported that new orders represented 77% of its ₹5,056 crore outstanding order book on September 30, 2026, equal to ₹3,895 crore. SPML also disclosed ₹5,802.81 crore of new order wins, while management said newly secured projects are expected to carry margins of 10-12% and generally require less working capital through escrow-based execution.
Know SPML Infra inside out
Results, valuation, peers and who's buying, in one view.
What makes up SPML’s order book at September 30, 2026?
SPML’s ₹5,056 crore outstanding order book consisted of ₹3,895 crore of new orders and ₹1,161 crore of legacy orders on September 30, 2026. New orders therefore made up 77% of the book, compared with 23% for legacy orders, establishing the scale of the shift in the work portfolio.
SPML describes the ₹1,161 crore legacy portfolio as back-to-back work with no execution or cash-flow liability for the company and lower margin profiles. Management says the newer ₹3,895 crore portion consists of projects selected for higher margins, price protection and zero complexity, although the presentation does not disclose a numerical margin for legacy orders.
The order-book composition and disclosed wins should not be treated as identical measures. The presentation separately reports ₹5,802.81 crore of new wins and a ₹5,056 crore outstanding book as of September 30, 2026, without providing a reconciliation between the two figures or dates of award for each contract.
Which projects account for SPML’s ₹5,802.81 crore new wins?
SPML’s 10 disclosed new wins total ₹5,802.81 crore, led by ₹4,323 crore of listed water and irrigation projects. The largest single award is a ₹1,438 crore Jal Jeevan Mission rural water-supply project in Bharatpur, Rajasthan, with JWIL Infra in a consortium in which the presentation states a 51% share.
The second-largest water contract is the ₹1,073 crore AMRUT 2.0 urban water-supply project for Indore Municipal Corporation. Other water-related awards include the ₹618 crore Konar irrigation project in Jharkhand, ₹385 crore for the Kekri-Sarwar package in Ajmer, ₹344 crore for an AMRUT water project in Chennai, ₹258 crore for Chennai reservoirs and pumping stations, and ₹207 crore for the Nonera water-supply project in Kota.
The water projects include operations and maintenance, or O&M, terms of 10 years in most cases. The ₹344 crore Chennai AMRUT contract has 15-year O&M, while the ₹258 crore Chennai reservoir and pumping-station project has 20-year O&M. Several listed projects are consortium or joint-venture contracts with disclosed ownership shares, including a 26% share for two Chennai projects and a 10% share for the Nonera project.
SPML also listed a ₹1,128 crore battery energy storage system, or BESS, engineering, procurement and construction contract for NTPC thermal power stations at Baruni, Bihar. Its grid awards total ₹351.81 crore, comprising ₹165.4 crore for a 400 kilovolt substation and transmission project in Kota and ₹186.41 crore for POWERGRID substation and pooling-station extensions at Bhadla-III and Ramgarh in Rajasthan.
Got a follow-up? Ask IRIS
Why does management expect the new order mix to affect margins?
Management expects the growing share of new orders to improve blended margins as legacy projects taper, because it characterises legacy work as lower-margin and newly secured orders as carrying expected margins of 10-12%. The presentation does not give a forecast for blended margin or state when the full effect of the ₹3,895 crore new-order book will be reported.
SPML says projects are largely executed through an escrow mechanism, which management says produces a significantly lower working-capital requirement. Escrow-based execution is part of management’s case for the new portfolio, but the presentation gives no working-capital balance, cash-conversion period or comparison against the ₹1,161 crore legacy portfolio.
Management’s stated filters are cash-rich states, funded projects, price protection and zero complexity. It expects newly secured orders to have execution periods of three to four years. This portfolio combines long O&M commitments in water projects with the ₹1,128 crore NTPC BESS engineering, procurement and construction order, rather than relying on a single contract format.
How does the NTPC BESS order fit SPML’s execution roadmap?
The ₹1,128 crore NTPC BESS order is the largest non-water award in the disclosed ₹5,802.81 crore wins and is scheduled for completion within NTPC’s contractual timeline of FY28. SPML says it has received advance payment from NTPC, while design and drawing approvals were expected to be completed by Q3 FY27.
SPML says its Phase 1 battery assembly line at SUPA MIDC, Pune, is fully ready with 2.5 gigawatt-hours, or GWh, of capacity. Management’s plan is to scale capacity to 5 GWh by FY28 and target annual capacity of 600 container units by H1 FY28, supported by planned investment of about ₹238 crore.
At full 5 GWh capacity, management estimates annual revenue potential of ₹4,000 crore to ₹5,000 crore. This is an estimate of potential rather than booked revenue, and management says SPML will continue bidding for battery-pack and container orders as an original equipment manufacturer player.
Conclusion
The September 30, 2026 order-book data shows SPML’s portfolio weighted toward new projects, with ₹3,895 crore, or 77%, classified as new orders and ₹1,161 crore as legacy orders. The ₹5,802.81 crore disclosed wins span ₹4,323 crore of water and irrigation projects, ₹1,128 crore of BESS work and ₹351.81 crore of grid infrastructure, supporting management’s stated focus on funded and lower-complexity projects.
The next disclosed milestones are NTPC design and drawing approvals expected by Q3 FY27, completion of the ₹1,128 crore BESS project within FY28, and the planned expansion from 2.5 GWh to 5 GWh by FY28. Management also targets 600 annual container units by H1 FY28, while the pace at which legacy orders taper will determine how quickly the stated 10-12% expected margin profile influences the overall mix.