SPML targets 5 GWh as Pune battery assembly line becomes ready
Key highlights
- SPML says its 2.5 GWh battery assembly line at SUPA MIDC, Pune, is fully ready.
- SPML plans to scale battery capacity to 5 GWh by FY28 with about Rs. 238 crore of planned investment.
- SPML has received an advance payment on its Rs. 1,128 crore NTPC BESS order in Baruni, Bihar.
- SPML estimates Rs. 4,000 crore to Rs. 5,000 crore of annual revenue potential at full 5 GWh capacity.
powered by IRIS

SPML Engineering Ltd says its 2.5 gigawatt-hour (GWh) battery assembly line at SUPA MIDC, Pune, is fully ready and planned to reach 5 GWh by FY28, while its Rs. 1,128 crore battery energy storage system (BESS) contract for NTPC has received an advance payment. The company expects design and drawing approvals by Q3 FY27.
Know SPML Infra inside out
Results, valuation, peers and who's buying, in one view.
Is SPML's Pune battery assembly line ready?
Yes. SPML says Phase 1, a 2.5 GWh battery assembly line at SUPA MIDC in Pune, is fully ready. The presentation identifies the facility as the first stage of an execution roadmap associated with its technology collaboration with Energy Vault.
SPML states that Phase 1 will deliver 2.5 GWh of capacity by Q1 FY27. The presentation does not provide production volumes, customer deliveries, utilisation levels or commissioning dates beyond that capacity timeline, so the stated readiness of the line is separate from disclosed commercial output.
SPML also says its battery pack has completed international safety, performance and transportation testing requirements. The presentation does not name the testing standards, laboratories or certification agencies, but says all global certifications have been received for the battery-pack and container-order bidding plan.
How will SPML expand battery capacity to 5 GWh?
SPML plans to double battery capacity from 2.5 GWh in Phase 1 to 5 GWh by FY28. The scale-up includes a target of 600 container units of annual capacity by the first half of FY28 and total planned investment of about Rs. 238 crore.
The move from 2.5 GWh to 5 GWh represents an additional 2.5 GWh of capacity under SPML's stated roadmap. The 600-container-unit target is tied to H1 FY28, while the 5 GWh target is stated for FY28; the presentation does not provide a quarterly construction schedule or split the planned Rs. 238 crore between equipment, facilities and working capital.
SPML says it will continue bidding for battery-pack and container orders as an original equipment manufacturer (OEM). The presentation lists no separate battery-pack or container order apart from the Rs. 1,128 crore NTPC BESS engineering, procurement and construction (EPC) contract.
What is the status of SPML's NTPC BESS order?
SPML says it has already received an advance payment on its Rs. 1,128 crore BESS order from NTPC. The new-order-wins schedule identifies the client as NTPC Ltd., the location as Baruni, Bihar, and the order type as BESS implementation on an EPC basis.
The next disclosed milestone is completion of design and drawing approvals by Q3 FY27. SPML says the contract is to be completed within NTPC's contractual timeline of FY28, making the approvals the stated near-term dependency before completion.
The NTPC contract is the only BESS project in SPML's Rs. 5,802.81 crore of listed new order wins. Water and irrigation projects account for several larger listed contracts, including a Rs. 1,438 crore Bharatpur Jal Jeevan Mission project and a Rs. 1,073 crore Indore AMRUT 2.0 water-supply project, showing the BESS order alongside SPML's established water work.
Got a follow-up? Ask IRIS
What revenue does SPML expect from 5 GWh capacity?
SPML estimates annual revenue potential of Rs. 4,000 crore to Rs. 5,000 crore at full 5 GWh capacity. This is management's capacity-linked potential estimate rather than reported revenue, and the presentation does not specify assumed selling prices, utilisation rates, project mix or the financial year in which full-capacity revenue could occur.
The difference between the Rs. 4,000 crore and Rs. 5,000 crore ends of management's range is Rs. 1,000 crore annually. The estimate is explicitly attached to full 5 GWh capacity, whereas Phase 1 is 2.5 GWh, so the presentation does not support treating the full range as an estimate for the initial phase alone.
SPML cites Rs. 1,000 crore of viability-gap funding for BESS in the 2026-27 budget and Rs. 1,775 crore for grid-connected solar projects. It also cites customs-duty exemptions on BESS capital goods and solar inputs as policy measures relevant to storage tender activity and project economics.
What supports SPML's battery-storage execution plan?
SPML identifies its technology collaboration with Energy Vault and its 45-plus-year power and grid execution history as support for the plan. The presentation says the partnership provides access to Energy Vault's global storage technology, but does not disclose commercial terms, technology-transfer arrangements, revenue sharing or geographic scope.
SPML also links the battery plan to recent power-project activity. Its new-order list includes a Rs. 165.4 crore 400-kilovolt grid-substation and transmission order in Kota and a Rs. 186.41 crore POWERGRID substation and pooling-station order in Rajasthan, alongside the Rs. 1,128 crore NTPC BESS contract.
As of 30 September 2026, SPML reported an outstanding order book of Rs. 5,056 crore, comprising Rs. 3,895 crore of new orders and Rs. 1,161 crore of legacy orders. Management says newly secured orders meet criteria including higher margins, price protection and zero complexity, and identifies expected margins of 10% to 12% with execution periods of three to four years; these are management expectations, not reported outcomes for the NTPC contract.
Conclusion
SPML has disclosed a defined storage expansion sequence: a fully ready 2.5 GWh Pune assembly line, planned doubling to 5 GWh by FY28, and a Rs. 1,128 crore NTPC EPC contract in Baruni with an advance payment received. Its Rs. 4,000 crore to Rs. 5,000 crore annual revenue-potential estimate depends on reaching full capacity and remains separate from reported revenue.
The next disclosed markers are design and drawing approvals for the NTPC project by Q3 FY27, the 600-container-unit annual-capacity target by H1 FY28, and NTPC completion within FY28. SPML has also identified about Rs. 238 crore of planned investment for the scale-up, while commercial output from the Pune line and further battery-pack or container orders remain undisclosed.