Tembo solar project has 10 sites handed over, four billing
Key highlights
- Tembo handed over 10 solar SPV sites, with billing started at four sites by H1FY27.
- Tembo’s Maharashtra solar PPA covers 120 MW and has stated capital expenditure of Rs 640 crore.
- The stated funding mix includes Rs 120 crore of equity, Rs 100 crore of post-commissioning subsidy and Rs 420 crore of debt.
- Financial institutions sanctioned approximately Rs 471 crore, and Tembo expects remaining-site handovers by end-Q3FY27.
powered by IRIS

Tembo Global Industries Limited had handed over 10 special-purpose vehicle sites for its 120 megawatt Maharashtra solar project by H1FY27, but billing had started at only four sites. Tembo has set out Rs 640 crore of required capital expenditure and revenue potential of about Rs 80 crore in FY27, subject to further execution and commissioning.
Know Tembo Global Industries inside out
Results, valuation, peers and who's buying, in one view.
What is Tembo’s solar project rollout status?
Tembo had handed over 10 solar special-purpose vehicle, or SPV, project sites, while billing had commenced at four sites as disclosed in its November 2026 Q2 and H1FY27 investor presentation. The update relates to Tembo’s 120 megawatt, or MW, power purchase agreement, or PPA, signed with the Maharashtra Government.
The reported difference means six handed-over sites had not yet begun billing at the time of the presentation. Tembo does not disclose the capacity allocated to each site, the tariff under the PPA, the commissioning status of individual sites, generation from the four billing sites or billing value received from them.
Management expects handover of all remaining sites by the end of Q3FY27. This is a timetable for physical handover, rather than a stated deadline for billing commencement, full commissioning or receipt of the Rs 100 crore government subsidy.
How is Tembo funding the 120 MW Maharashtra solar project?
Tembo’s stated Rs 640 crore project funding requirement comprises Rs 120 crore of equity, Rs 100 crore of government subsidy receivable after commissioning and Rs 420 crore of debt. These three components total the stated capital expenditure requirement for the 120 MW project.
Financial institutions had sanctioned approximately Rs 471 crore, and Tembo said the first loan disbursement had been made by November 2026. The sanctioned amount is Rs 51 crore higher than the Rs 420 crore debt component in the presented funding mix, but the presentation does not explain that difference or disclose the amount drawn after the first disbursement.
Tembo also reported that land had been finalised. The project subsidy is specifically described as receivable post commissioning, so the presentation does not identify it as money already received or as a source available before that commissioning condition is met.
The solar financing is distinct from Tembo’s Vasai manufacturing expansion. That facility, commissioned in January 2026 at 1,00,000 metric tonnes per annum, involved Rs 75 crore of capital expenditure, including Rs 50 crore of debt, whereas the solar project carries its own Rs 640 crore funding structure.
What revenue does Tembo expect from the solar project in FY27?
Tembo estimates revenue potential of about Rs 80 crore from the solar project in FY27. The company also presents Power as an expected 5% contributor to FY27 revenue, alongside expected contributions of 75% from Engineering Products, 10% from Textiles and 10% from Defence.
Actual solar revenue was not separately reported for H1FY27, even though four solar sites had started billing. In the reported H1FY27 segment mix, Engineering Products accounted for 96% of revenue and Textiles accounted for 4%, with no separate Power revenue figure provided.
At the consolidated level, Tembo reported H1FY27 revenue of Rs 533.9 crore, compared with Rs 493.5 crore in H1FY26, an increase of 8.2%. Tembo attributed the half-year revenue growth to its Engineering division, while earnings before interest, tax, depreciation and amortisation, or EBITDA, rose 40.4% to Rs 86.1 crore.
Profit after tax, or PAT, increased 36.2% to Rs 57.2 crore in H1FY27 from Rs 42 crore a year earlier. The solar project’s Rs 80 crore FY27 revenue potential is therefore a management projection, and Tembo has not disclosed project-level operating profit, cash collection, generation output or tariff realisation from the four billing sites.
Got a follow-up? Ask IRIS
How does Tembo’s solar plan compare with its core businesses?
Tembo positions solar power as a diversification initiative intended to add recurring revenue over the long term, but Engineering and EPC remained its larger disclosed operating base in H1FY27. Engineering Products represented 96% of the half-year revenue mix, compared with the expected 5% FY27 contribution from Power.
Engineering and EPC had an order book of more than Rs 1,600 crore, while the order-bidding pipeline, including L1, was more than Rs 2,550 crore as disclosed for Q2FY27. L1 denotes the lowest bidder position, although Tembo does not state how much of this pipeline will convert into orders or on what timetable.
The solar build-out is occurring alongside other expansion programmes. Tembo’s defence manufacturing facility at Amravati, Maharashtra, has a production target of March 2027, while JR UAV drone production at the Vasai facility is expected to commence by the end of December 2026.
Tembo reported total debt of Rs 444 crore as of 30 September 2026, against Rs 377 crore as of 31 March 2026. Working-capital days rose to 105 in H1FY27 from 94 in FY26; Tembo attributed the higher level to extended credit periods in EPC projects and longer conversion timelines in engineering projects.
What are the next solar milestones for Tembo?
Tembo’s next disclosed solar milestone is completion of handover for all remaining sites by the end of Q3FY27. Because billing had begun at four of 10 handed-over sites, subsequent disclosures would be needed to establish whether handover, billing and commissioning progress together across the remaining sites.
Commissioning is also material to the stated Rs 100 crore government subsidy, which Tembo says is receivable after commissioning. The presentation does not give a target date for full project commissioning, a site count for the entire project, an annual generation forecast or the date by which the Rs 420 crore debt component will be fully drawn.
The FY27 revenue expectation of about Rs 80 crore and the planned 5% Power contribution provide management’s stated commercial benchmarks. Actual delivery against those benchmarks will depend on progress beyond the four sites where billing had commenced by H1FY27.
Conclusion
Tembo’s presentation establishes that the 120 MW Maharashtra solar project had moved into an early revenue stage by H1FY27, with 10 SPV sites handed over and four billing. The six-site gap between those measures is important because Tembo has disclosed a Rs 640 crore funding requirement and about Rs 80 crore FY27 revenue potential without reporting actual solar revenue, generation or cash collections.
The next point to watch is management’s end-Q3FY27 target to hand over the remaining sites. Later updates will also need to show commissioning progress, further debt drawdowns from the approximately Rs 471 crore sanctioned amount, receipt of the Rs 100 crore post-commissioning subsidy and whether Power approaches Tembo’s expected 5% share of FY27 revenue.