Tera Software Limited’s Rs 3,502.78 crore share spans 10 years
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Tera Software’s BharatNet Phase III work share is Rs 3,502.78 crore, equal to 50% of the Rs 7,005.55 crore consortium value.
- The project covers about 50,515 km of optical-fibre network across three packages.
- The 10-year term includes a three-year build phase and seven years of operations and maintenance.
- The three packages cover 12,929 Gram Panchayats and 691 blocks.
powered by IRIS

Tera Software has disclosed a Rs 3,502.78 crore, 50% work share in BharatNet Phase III, covering about 50,515 km of optical-fibre network over 10 years. The project combines a three-year build phase with seven years of operations and maintenance across three packages, which are being executed with consortium partner ITI Limited.
Know Tera Software inside out
Results, valuation, peers and who's buying, in one view.
What does Tera Software’s BharatNet Phase III share include?
Tera Software’s BharatNet Phase III work share is Rs 3,502.78 crore, representing 50% of the Rs 7,005.55 crore consortium contract value. Tera Software is participating as a consortium partner of ITI Limited to develop and maintain middle-mile optical-fibre network infrastructure.
The stated project term is 10 years, split between a three-year buildout and seven years of operations and maintenance, or O&M. The disclosed scope covers design and deployment of underground and aerial optical fibre cable, or OFC, networks; supply and installation of network infrastructure and equipment; system integration; testing; commissioning; and long-term network O&M.
The contract structure extends beyond the initial construction period because the seven-year O&M phase follows the three-year build phase. Tera Software’s operating framework identifies technical support, system monitoring, software and network maintenance, facility management, and troubleshooting as activities within its O&M model.
How is Tera Software’s BharatNet network divided by package?
Tera Software’s 50,515 km BharatNet network scope is divided among Package 8 in Himachal Pradesh, Package 9 in West Bengal and the Andaman and Nicobar Islands, and Package 15 in Arunachal Pradesh, Nagaland and Manipur. The three packages collectively cover 12,929 Gram Panchayats, or GPs, and 691 blocks.
Package 8 has the greatest route length at 20,100 km, which is 7,910 km more than Package 15’s 12,190 km. Package 15 has the highest GP count at 5,902, compared with 3,615 in Package 8 and 3,412 in Package 9, showing that fibre length and GP coverage differ across the packages.
Package 9 has 353 blocks, exceeding Package 15’s 258 and Package 8’s 80. The presentation says package values are approximate, include goods and services tax, or GST, and are not Tera Software’s individual work-share values; it therefore does not provide a basis for allocating the Rs 3,502.78 crore share among the three packages.
Got a follow-up? Ask IRIS
What will Tera Software do during the 10-year BharatNet term?
Tera Software will execute the stated network lifecycle from fibre design and deployment through commissioning and seven years of O&M. The first three years cover underground and aerial OFC deployment, network infrastructure and equipment supply, system integration, testing, and commissioning.
The O&M period accounts for seven of the project’s 10 years. The presentation describes long-term network operations and maintenance as part of the BharatNet scope, while Tera Software’s wider O&M framework includes network monitoring, technical support, software and network maintenance, facility management, and troubleshooting.
The work spans six named geographical areas: Himachal Pradesh; West Bengal; the Andaman and Nicobar Islands; Arunachal Pradesh; Nagaland; and Manipur. The project’s use of both underground and aerial fibre deployment methods applies across a stated route scope of about 50,515 km.
Tera Software lists BharatNet Phase III with the status of implementation. The presentation does not disclose package-level construction milestones, the contract award date, annual revenue recognition, completion dates inside the three-year build window, or the division of the Rs 3,502.78 crore work share between construction and O&M.
How does BharatNet Phase III compare with Tera Software’s other disclosed projects?
BharatNet Phase III is the largest project in Tera Software’s disclosed portfolio, with a Rs 7,005.55 crore consortium value and a Rs 3,502.78 crore Tera Software share. Its 50,515 km OFC scope and 12,929 GPs exceed the stated physical scope of Odisha BharatNet Phase II, which covered about 20,427 km and 3,065 GPs.
Odisha BharatNet Phase II has a stated value of Rs 497.32 crore and is described as implementation completed, with a five-year annual maintenance contract, or AMC. BharatNet Phase III remains in implementation and has a stated seven-year O&M period, two years longer than Odisha BharatNet Phase II’s disclosed five-year AMC period.
Tera Software also lists Uttar Pradesh electricity-distribution spot-billing projects worth Rs 273.11 crore in total, including Rs 107.65 crore for PUVVNL, Rs 75.40 crore for DVVNL, and Rs 90.06 crore for MVVNL. Those projects cover meter reading, bill generation, and bill distribution, while BharatNet Phase III centres on fibre deployment, network integration, and middle-mile network maintenance.
Other disclosed assignments include a Rs 74.84 crore Davanagere Smart City information and communication technology project in O&M or AMC and a Rs 58.12 crore West Bengal State Electricity Distribution Company Limited spot-billing assignment across five zones. Tera Software also states that it has completed around 20 projects across e-governance, utility systems, digital connectivity, smart city and information and communication technology, public services, and IT infrastructure.
Conclusion
Tera Software’s BharatNet Phase III disclosure describes a Rs 3,502.78 crore share in a Rs 7,005.55 crore consortium contract, spanning 50,515 km across three packages. The scope combines a three-year network buildout with seven years of O&M, differentiating it from the company’s shorter-term deployment-only activities and linking construction with long-term support obligations.
The next disclosed point to watch is progress from implementation through the three-year build plan, including deployment, integration, testing, and commissioning. The presentation does not disclose package-wise Tera Software values, construction milestones, or the allocation of contract value between build and O&M, leaving those execution details unresolved.