VAS Infrastructure Limited CIRP extended 90 days to February 2027
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- NCLT extended VAS Infrastructure’s re-initiated CIRP by 90 days until February 3, 2027.
- VAS Infrastructure received 19 expressions of interest as of October 27, 2026.
- Three of the 19 EOI applicants had not paid the Rs 50 lakh refundable deposit.
- The prior 120-day re-initiated CIRP period expired on November 5, 2026.
powered by IRIS

VAS Infrastructure Limited received a 90-day extension of its re-initiated Corporate Insolvency Resolution Process, or CIRP, taking the deadline to February 3, 2027, after the National Company Law Tribunal recorded 19 expressions of interest as of October 27, 2026. The order gives the process time for resolution-plan submission and consideration.
Know Vas Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
Why did VAS Infrastructure receive 90 more CIRP days?
VAS Infrastructure received the additional 90 days because the National Company Law Tribunal, Mumbai Special Bench Court II, accepted the Resolution Professional’s request to continue the re-initiated CIRP beyond its prior 120-day period. The tribunal’s November 20, 2026 order in IA 4916/2026 extended the process until February 3, 2027, and the order was uploaded on the Mumbai Bench portal on November 27, 2026.
The extension applies to the insolvency proceeding in C.P. (IB) No. 314/MB/2023, which began pursuant to a March 11, 2024 tribunal order. The application was made under Sections 7 and 12(2) of the Insolvency and Bankruptcy Code, or IBC. VAS Infrastructure’s disclosure says the 90 days were granted beyond the prescribed 120 days of the re-initiated process, rather than being a fresh insolvency admission.
The tribunal recorded that the earlier 120-day window had been granted in an order dated July 7, 2026 in I.A. (I.B.C.) (Plan) No. 41/MB/2025. That period expired on November 5, 2026. The new order therefore preserves the re-initiated process after its initial timetable ended, with February 3, 2027 set as the revised end date.
What bidder interest did VAS Infrastructure’s process attract?
VAS Infrastructure’s re-initiated CIRP had received 19 expressions of interest, or EOIs, as of October 27, 2026, according to the application considered by the tribunal. The order described this response as substantial interest and said it created a concrete opportunity to pursue a resolution rather than a merely speculative prospect of revival.
Of the 19 EOI applicants, three had not remitted the refundable deposit required under the detailed invitation for EOI. The stated deposit was Rs 50 lakh for each applicant. The filing does not identify the applicants, specify whether the other EOI applicants were qualified participants, or disclose proposed values, terms or funding arrangements for any potential resolution plan.
The Resolution Professional sought the extension so that the competitive process could move through plan submission, examination and consideration by the Committee of Creditors, or CoC. The tribunal accepted that rationale and allowed the application. The order does not say that the CoC had approved a plan, selected a bidder or fixed a recovery amount by November 20, 2026.
Got a follow-up? Ask IRIS
How does the February 2027 deadline change the process timetable?
VAS Infrastructure now has a CIRP deadline of February 3, 2027, replacing the November 5, 2026 expiry of the earlier 120-day re-initiated window. This is a 90-day extension sought from the expiry of that prior period, as set out in the prayer before the tribunal. The company’s November 27, 2026 disclosure confirms that the tribunal allowed the requested extension.
The sequence shows that the request for more time was linked to the planned next stage of the process. The application said the request for resolution plans, or RFRP, was proposed to be issued on November 7, 2026, after the November 5 expiry of the existing period. It also proposed allowing at least 30 days for submission of plans, which could not be completed within the expired 120-day timeframe.
The tribunal’s order did not amend or disclose the terms of the RFRP, the eligibility conditions for prospective applicants, or any revised milestone before February 3, 2027. It only extended the CIRP period as requested. The disclosed change is therefore procedural: VAS Infrastructure has time to take the renewed process to plan consideration, but the outcome remains undisclosed.
What must happen before VAS Infrastructure’s new CIRP deadline?
VAS Infrastructure’s renewed process is intended to proceed from the proposed November 7, 2026 RFRP to the submission, examination and CoC consideration of resolution plans before February 3, 2027. The Resolution Professional told the tribunal that at least 30 days should be provided for plan submission, and that the added 90 days would enable the competitive process to reach a meaningful conclusion.
The relevant decision-making body identified in the order is the CoC, which is to consider plans after their submission and examination. The November 20 order does not state a scheduled CoC voting date, a deadline for approval of a plan, or a hearing date following February 3, 2027. It also provides no information on the amount of admitted claims, VAS Infrastructure’s assets, or expected payments to creditors.
For disclosure purposes, VAS Infrastructure reported the extension under Regulation 30 read with Part A of Schedule III of the Securities and Exchange Board of India Listing Obligations and Disclosure Requirements Regulations, 2015. Resolution Professional Bimal Kumar Agarwal signed the November 27, 2026 intimation. His authorisation for assignment is valid until June 30, 2027, which is later than the revised CIRP deadline.
Conclusion
VAS Infrastructure’s February 3, 2027 deadline keeps its re-initiated CIRP open for 90 days beyond the November 5, 2026 end of the previous 120-day period. The tribunal’s decision followed 19 EOIs received by October 27, 2026, although three applicants had not paid the Rs 50 lakh refundable deposit, and the stated need to allow a competitive plan process to proceed.
What to watch next is whether resolution plans are submitted, examined and placed before the CoC before February 3, 2027. The source does not disclose whether the proposed November 7, 2026 RFRP was issued, whether any plans were received, or whether the CoC has considered a plan, leaving those stages unresolved within the extended period.