Vascon Engineers receives Rs 195 crore Borivali contract
Key highlights
- Vascon Engineers received a Rs 195 crore Letter of Intent excluding taxes for Borivali shell-and-core construction.
- The Borivali redevelopment work covers T1, T2 and T3 at Mohan Society Redevelopment Project.
- Vascon Engineers must complete the domestic BOQ-based order within 24 months.
- Kanakia Transparent Developers Pvt. Ltd awarded the Rs 195 crore contract.
powered by IRIS

Vascon Engineers Limited received a Rs 195 crore, tax-exclusive domestic Letter of Intent from Kanakia Transparent Developers Pvt. Ltd for shell-and-core work at Borivali’s Mohan Society Redevelopment Project, with T1, T2 and T3 to be completed within 24 months on mutually agreed terms.
Know Vascon Engineers inside out
Results, valuation, peers and who's buying, in one view.
What order has Vascon Engineers received for Borivali?
Vascon Engineers has received a Letter of Intent for construction of shell-and-core works at the Mohan Society Redevelopment Project in Borivali, Mumbai. Kanakia Transparent Developers Pvt. Ltd awarded the Rs 195 crore contract, which the disclosure classifies as a domestic order.
The filing’s subject line specifies that the scope covers T1, T2 and T3. In Annexure-A, the project is called the Kanakia Mohan Society Redevelopment Project at Borivali, Mumbai, while the main letter uses Mohan Society Redevelopment Project; both parts describe the same Rs 195 crore shell-and-core assignment.
Vascon Engineers disclosed the contract under Regulation 30 of the Securities and Exchange Board of India Listing Obligations and Disclosure Requirements Regulations, 2015. The annexure also cites the Securities and Exchange Board of India circular CIR/CFD/CMD/4/2015 dated September 9, 2015, as part of the disclosure framework for the 24-month order.
How much is the Borivali shell-and-core contract worth?
The Borivali contract has a broad consideration of Rs 195 crore excluding taxes. Vascon Engineers gives that numeric value in both the main announcement and Annexure-A, with no separate value assigned to T1, T2 or T3.
The two parts of the disclosure show no change in the Rs 195 crore consideration or the 24-month delivery requirement. Annexure-A describes the order as being on a BOQ basis, while the main announcement states the shell-and-core construction scope for the Borivali project.
The filing contains an inconsistency in the amount written in words in Annexure-A, which says “One Hundred and Ninety Crores only,” although the numeric figure there is Rs 195 crore. The main announcement gives both Rs 195 crore and “One Hundred & Ninety Five Crore,” so the numeric Rs 195 crore figure is the consistent disclosed consideration.
The Rs 195 crore amount excludes taxes, and Vascon Engineers has not disclosed a tax-inclusive value for the Borivali work. The announcement also does not provide a comparison with earlier orders, an order-book figure, revenue contribution, margin estimate or tower-wise consideration for the three-tower scope.
When does Vascon Engineers have to complete the work?
Vascon Engineers must complete the Borivali shell-and-core work within 24 months on mutually agreed terms. The 24-month period appears in the main Letter of Intent announcement and is repeated in Annexure-A for the Rs 195 crore domestic contract.
The disclosure does not state the Letter of Intent date, mobilisation date, calendar completion date or interim milestones within the 24-month period. Therefore, the announcement establishes the duration for T1, T2 and T3 but does not support calculation of a quarterly execution run rate or a precise completion date.
Vascon Engineers has also not disclosed payment milestones, advances, retention, escalation provisions, damages or certification terms for the Rs 195 crore work. Apart from the BOQ basis and the mutually agreed 24-month terms, the filing provides no further commercial mechanism for the shell-and-core assignment.
Got a follow-up? Ask IRIS
Who awarded the contract and is it related to Vascon Engineers?
Kanakia Transparent Developers Pvt. Ltd awarded the Rs 195 crore Letter of Intent to Vascon Engineers. The company identifies the awarding entity in Annexure-A and classifies both the counterparty and the Borivali contract as domestic.
Vascon Engineers marked promoter, promoter-group and group-company interest in Kanakia Transparent Developers Pvt. Ltd as “Not Applicable.” It also marked the related-party transaction field as “Not Applicable,” so the disclosure does not identify the 24-month order as a related-party transaction.
The contract’s stated scope is construction of shell-and-core works, rather than project development, finishing work, maintenance or sales activity. The filing does not disclose built-up area, construction quantities, schedules of rates or any split of the Rs 195 crore value among the T1, T2 and T3 towers.
What does the BOQ basis disclose about this contract?
Vascon Engineers identifies the nature of the Rs 195 crore Borivali order as BOQ basis in Annexure-A. The filing does not expand the term or publish the underlying BOQ, while the announced work remains shell-and-core construction for T1, T2 and T3.
No item-level quantities or rates are provided for concrete, steel, structural elements or other components of the 24-month construction scope. The company also does not state whether the Rs 195 crore consideration may change for quantity variations, leaving the disclosed order mechanism limited to its BOQ description.
The filing similarly does not set out billing intervals or a division of work between the three towers. As a result, the available information supports the contract value, location, scope, domestic classification and 24-month execution requirement, but not a tower-level or period-level financial contribution.
Conclusion
The Letter of Intent adds a domestic shell-and-core construction assignment at Mohan Society Redevelopment Project in Borivali to Vascon Engineers’ disclosed contracts. Its key stated terms are Rs 195 crore excluding taxes, coverage of T1, T2 and T3, a BOQ basis and Kanakia Transparent Developers Pvt. Ltd as the awarding entity.
The disclosed point to watch next is delivery within the 24-month requirement. Vascon Engineers has not provided a mobilisation date, milestone schedule, calendar completion date or itemised BOQ terms, so any later company disclosure on progress, consideration or completion would add detail to the announced execution plan.