Vascon’s Rs 3,400 crore EPC book exceeds FY26 by Rs 683 crore
Key highlights
- Vascon’s current EPC order book is Rs 3,400 crore, including Rs 3,215 crore of external work.
- The current Rs 3,400 crore order book is Rs 683 crore above FY26’s Rs 2,717 crore.
- Qualcomm’s Bengaluru office-facility project is Vascon’s largest listed order at Rs 560 crore.
- Management says four FY27 year-to-date key wins aggregate Rs 1,250 crore.
powered by IRIS

Vascon’s current engineering, procurement and construction (EPC) order book is Rs 3,400 crore, Rs 683 crore above FY26, with external orders rising to Rs 3,215 crore from Rs 2,387 crore. Management says four FY27 year-to-date wins aggregate Rs 1,250 crore, led by a Rs 560 crore Qualcomm facility in Bengaluru.
Know Vascon Engineers inside out
Results, valuation, peers and who's buying, in one view.
How large is Vascon’s current EPC order book?
Vascon’s current EPC order book is Rs 3,400 crore, made up of Rs 3,215 crore of external orders and Rs 185 crore of internal orders. External projects therefore account for Rs 3,215 crore of the reported pipeline, while projects classified internally account for Rs 185 crore.
The total is Rs 683 crore higher than the Rs 2,717 crore reported for FY26, calculated from Rs 2,387 crore of external orders and Rs 330 crore of internal orders. The increase reflects an Rs 828 crore rise in external orders, which more than offset a Rs 145 crore reduction in internal orders.
Vascon’s current total is also Rs 350 crore above FY25’s Rs 3,050 crore and Rs 35 crore above FY24’s Rs 3,365 crore. Across FY24 to the current period, internal orders declined by Rs 342 crore, while external orders increased by Rs 377 crore, changing the mix towards external EPC work.
Which FY27 wins are adding to Vascon’s order pipeline?
Vascon identifies four FY27 year-to-date key wins that management says aggregate Rs 1,250 crore: Qualcomm in Bengaluru, Reserve Bank of India (RBI) quarters in Guwahati, State Bank of India (SBI) facilities in Pune and a government hospital in Wardha. The four projects span a private office facility, residential redevelopment, training and residential facilities, and a 300-bedded hospital.
The largest disclosed win is a Rs 560 crore contract to develop Qualcomm’s Block K office facility in Bengaluru, described as a ground-plus-12-floor building. This project alone equals nearly half of the stated Rs 1,250 crore batch of major FY27 wins.
The other three named wins are the RBI residential-quarters redevelopment in Guwahati at Rs 294 crore, SBI’s training institute, residential flats and commercial facilities in Pune at Rs 198 crore, and the Rs 126 crore Wardha general hospital. The four project values shown on the FY27 key-wins page add to Rs 1,178 crore, rather than management’s stated Rs 1,250 crore aggregate.
Vascon’s presentation also gives two values for the RBI project. The key-wins page shows Rs 294 crore, while the external order-book table lists RBI Quarters, Guwahati at Rs 276 crore; the presentation does not explain the Rs 18 crore difference. The note on the key-wins page says values exclude applicable taxes and are rounded to the nearest crore.
Got a follow-up? Ask IRIS
How much of Vascon’s listed work is government and public-sector related?
Vascon’s presentation does not state an official government-project percentage for the Rs 3,400 crore order book, but its external-project roster contains several clearly identified government, public-sector and municipal assignments. These include Rs 276 crore of RBI quarters, Rs 272 crore for a government medical college at Sindhudurg and Rs 223 crore for medical colleges at Suphal, Bihar.
Other listed public or institutional projects include the Rs 218 crore Navi Mumbai Municipal Corporation hospital, Rs 198 crore of SBI quarters in Pune and Rs 179 crore of Pune Police staff quarters. These six projects total Rs 1,366 crore using the values in the external order-book table, before including other medical, metro and public-building assignments.
The roster additionally names a Rs 148 crore medical college and district-hospital upgrade at Koderma, a Rs 126 crore government hospital at Wardha, a Rs 39 crore MMRCIL building, and a Rs 31 crore government medical college at Kanker. It also includes Rs 30 crore of Pune Metro Region Development Authority residential quarters, Rs 16 crore of medical-college and district-hospital work at Kaushambi, and a Rs 14 crore Mumbai Metro high-rise building.
Private and corporate work remains material in the Rs 3,215 crore external book. Beyond Qualcomm’s Rs 560 crore project, Vascon lists Royal Rides Pvt Ltd in Goa at Rs 213 crore, Capgemini IT Park in Tamil Nadu at Rs 131 crore, Lotus Park in Ahmedabad at Rs 108 crore and Vedanta Barmer at Rs 14 crore.
What execution capacity does Vascon disclose for this pipeline?
Vascon says it is currently executing around 3.7 million square feet annually at 90% utilisation, supported by more than 500 personnel in its project and engineering team. The presentation positions this capacity alongside a stated focus on large, high-value civil contracts from government agencies and reputed private companies.
Vascon reports having executed more than 225 projects covering more than 45 million square feet. Its listed clients include Airports Authority of India, Bangalore Metro Rail Corporation Limited and National Buildings Construction Corporation Limited, as well as Cipla, IBM, DLF and Tata Housing.
Management attributes higher margins to turnkey capabilities, including an in-house design and engineering team, but does not disclose an EPC margin figure for the Rs 3,400 crore book. It says the EPC business aims to generate positive cash flows from all projects and reinvest them to support growth.
The Rs 185 crore internal book contains five projects, led by The Prakash CHS Limited redevelopment in Santacruz West, Mumbai, at Rs 90 crore. The remaining projects include Rs 30 crore for OHM Sainath CHS Limited, Rs 27 crore for Tulip Gold Phase III, Rs 25 crore for Tower of Ascend and Rs 13 crore for Good Life Katvi.
Conclusion
Vascon’s Rs 3,400 crore EPC order book has moved above its FY24, FY25 and FY26 levels, driven by an Rs 828 crore increase in external orders from FY26. The listed portfolio combines a Rs 560 crore private-sector Qualcomm project with substantial medical, housing, police, metro and institutional assignments, while internal orders have declined to Rs 185 crore.
The next disclosed items to watch are Vascon’s pursuit of large government-agency and reputed-private-company civil contracts, and execution of the four FY27 wins management says total Rs 1,250 crore. Clarification of the RBI Guwahati value is also relevant because the presentation shows Rs 276 crore in the order-book table and Rs 294 crore on the key-wins page.