VL Infra's Rs 200 crore backlog targets 12-18 month execution
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- VL Infra expects to execute its Rs 200 crore September 30, 2026 order book over 12 to 18 months.
- Water-pipeline projects represent 80% of VL Infra's order book and 67.33% of H1 FY27 revenue.
- Government clients account for 80.76% of VL Infra's order book, while Gujarat contributes 71.77%.
- VL Infra received Rs 67.05 crore of new orders in H1 FY27 and reported an active bid pipeline of around Rs 63 crore.
powered by IRIS

V.L.Infraprojects Limited, referred to here as VL Infra, expects to execute its Rs 200 crore order book recorded on September 30, 2026 over 12 to 18 months. Water-pipeline projects account for 80% of the backlog, while government clients represent 80.76%, according to management’s November 25, 2026 H1 FY27 conference call.
Know V.L.Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
What is VL Infra's order book and execution timeline?
VL Infra reported a Rs 200 crore order book as of September 30, 2026 and expects to execute it over the following 12 to 18 months. Management disclosed the timeframe during its H1 FY27 results call on November 25, 2026, providing its stated horizon for converting the contracted backlog into project execution and revenue.
Government clients account for 80.76% of the Rs 200 crore order book. VL Infra said its clients are mainly government and semi-government bodies, including water supply and sewerage boards and municipal corporations, while its work includes water supply, sewerage networks, pipeline procurement and laying, irrigation, civil works, electromechanical installation, and operation and maintenance, or O&M.
The 12-to-18-month period is management’s execution expectation, not a quarterly revenue forecast. Management did not provide a split of the Rs 200 crore backlog by quarter, nor did it specify how much would be recognised in H2 FY27, which follows the half year ended September 30, 2026.
How concentrated is VL Infra's backlog in water pipelines?
VL Infra's order book is concentrated in water pipelines, which comprise 80% of the Rs 200 crore backlog, compared with 67.33% of H1 FY27 revenue. The comparison shows that pipeline projects carry a larger share of work yet to be executed than they contributed to revenue in the first half.
Civil works accounted for 20.31% of H1 FY27 revenue but form around 15% of the order book. Irrigation and sewerage contributed 12.36% of H1 FY27 revenue and make up 5% of the backlog, leaving the future work mix more weighted to pipelines than the revenue mix reported for the half year.
Management said supply portions had been almost completed on many projects and that current work mainly involved civil construction, including civil buildings and pumping stations. In response to a margin question, management said new orders could have a greater supply component, but it did not give a margin forecast for the Rs 200 crore backlog.
Which projects and markets could support VL Infra's execution?
VL Infra said Gujarat is its core market, contributing 71.77% of the order book, while Madhya Pradesh, Telangana and Andhra Pradesh make up a growing share. This means the reported backlog remains centred on Gujarat despite management’s plan to build its presence in other states.
Management named Telav water supply, Jalundra water supply, Shela, Adas and Abdasa water supply, and Balasinor water supply and sewerage projects as works progressing towards completion between December 2026 and August 2027. That project-completion schedule falls within the company’s stated 12-to-18-month order-book execution period.
VL Infra said it holds licences across Gujarat, Telangana, Madhya Pradesh, Andhra Pradesh and Karnataka and has a presence in eight states. Management said it plans to deepen its presence in Telangana, Hyderabad and Andhra Pradesh and enter Bihar and Odisha, although it did not disclose any current order-book amount for those proposed new markets.
The company said it has completed more than 30 projects and executed more than Rs 150 crore of orders in FY26. That historical execution level provides context for the Rs 200 crore backlog, but management did not state the value of each named project or provide a project-by-project execution schedule.
Got a follow-up? Ask IRIS
What order inflows and tender activity has VL Infra disclosed?
VL Infra received new orders worth Rs 67.05 crore in H1 FY27 and reported an active bid pipeline of around Rs 63 crore. The new-order figure was disclosed alongside the Rs 200 crore order book, though management did not state how much of the H1 FY27 inflow was included in the September 30 backlog balance.
During the call, management said it was participating in tenders worth around Rs 200 crore to Rs 250 crore and expected at least Rs 100 crore in the coming quarter. Management also said it was targeting around Rs 200 crore of new orders for FY27, which is a target rather than an order inflow already secured.
An analyst said the order book had moved from Rs 218 crore in March to Rs 200 crore in June despite H1 order inflows of about Rs 67 crore. Management said some tenders had been won and some had not, but did not provide a reconciliation of the order-book movement or clarify the June reference in the analyst’s question.
Management said its bid-to-win ratio was around 20%, compared with around 40% two years earlier, citing greater competition. It added that tender activity was continuing in Gujarat, while activity in Madhya Pradesh was not substantial, differentiating conditions in its core market from one of its other operating states.
How does the order book compare with VL Infra's H1 FY27 performance?
VL Infra reported total income of Rs 71.79 crore in H1 FY27, up 14.14% from Rs 62.90 crore in the previous-year period. Revenue from operations was Rs 71.70 crore, while earnings before interest, tax, depreciation and amortisation, or EBITDA, were Rs 6.70 crore at a 9.36% margin, and profit after tax was Rs 3.18 crore.
Management said H1 FY27 included investments in expanding execution across more sites and new geographies. It said operating leverage could support margins as projects mature and activity increases, but this was management’s expectation and the company did not quantify a prospective EBITDA or profit effect.
Management maintained a target of 20% year-on-year revenue growth for FY27 and said the final quarter is usually crucial for engineering, procurement and construction, or EPC, companies. The call also recorded other expenses of Rs 5.18 crore in H1 FY27, compared with Rs 3.55 crore in the previous-year period, with management citing professional, initial public offering, site, and bank and working-capital-limit renewal costs.
Conclusion
VL Infra has provided a defined 12-to-18-month execution expectation for its Rs 200 crore backlog, but the work is concentrated in water pipelines, government clients and Gujarat. Water pipelines account for 80% of pending work versus 67.33% of H1 FY27 revenue, indicating a more pipeline-weighted backlog than the revenue mix reported in the first half.
The next disclosed milestones are completion of the named water and sewerage projects between December 2026 and August 2027, management’s expectation of at least Rs 100 crore of orders in the coming quarter, and its FY27 new-order target of around Rs 200 crore. Execution against the 20% FY27 revenue-growth target will also be relevant after H1 total income increased 14.14% to Rs 71.79 crore.