Websol targets December 2027 trials for 2 GW Falta plant
Key highlights
- Websol targets December 2027 trial runs for the first 2 GW of its planned 4 GW Falta TOPCon project.
- Websol estimates Rs 1,350 crore of spending for the first 2 GW Falta phase, with about 70% planned debt funding.
- Websol reported Rs 212 crore of net operating cash flow after taxes in H1 FY27, compared with Rs 132 crore in H1 FY26.
- Websol targets March 2027 commercialisation of its 750 MW TOPCon upgrade at the existing Falta plant.
powered by IRIS

Websol Energy System Limited is targeting December 2027 trial runs for the first 2 gigawatts of its planned 4-gigawatt integrated TOPCon facility at Falta, West Bengal, with the first phase estimated to cost Rs 1,350 crore. Management said land development had begun, civil work was expected around January, and the project would be financed largely with debt.
Know Websol Energy System inside out
Results, valuation, peers and who's buying, in one view.
When will Websol start trials at the Falta plant?
Websol is targeting trial runs for the first 2 gigawatts of its Falta project by December 2027, which management identified as the third quarter of FY28. The company plans the 4-gigawatt integrated TOPCon project in two phases of 2 gigawatts each, following the allotment of 54.20 acres at Falta Industrial Park in September.
The December 2027 date applies only to the first phase, not the full 4-gigawatt build-out. Websol did not disclose a construction, commissioning or trial-run date for the second 2-gigawatt phase. Management said the new plant would be near its current Falta operations, allowing it to train people at the existing facility before transferring them to the larger site.
Land development was under way during the Q2 FY27 call. Management expected that work to finish by early next year, after which construction would commence. It later said site civil work was expected around January, while the pre-engineered building, or PEB, would be produced at the vendor's location.
How much will Websol spend and borrow for phase one?
Websol estimates that the first 2-gigawatt Falta phase will cost Rs 1,350 crore and is targeting funding of about 30% equity and 70% debt. Management said it expected to provide roughly Rs 400 crore to Rs 500 crore from internal accruals, with the remainder raised through borrowings.
Management said the 70:30 debt-equity structure was intended to retain capital for later investment requirements. These include the second 2-gigawatt Falta phase and a separate proposed ingot-and-wafer project. It said the 54.20-acre allotment was for the integrated TOPCon project only and that ingot-and-wafer manufacturing would be located elsewhere.
Websol had repaid its Indian Renewable Energy Development Agency debt in August and described itself as debt-free. It reported Rs 212 crore of net operating cash flow after taxes in H1 FY27, compared with Rs 132 crore in H1 FY26, while management cited net worth of Rs 780 crore at the September results date. Management had not decided to raise equity or issue warrants at the time of the call.
What capacity will Websol have before the new plant starts?
Websol expects its existing cell capacity to reach 1.35 gigawatts by the end of FY27 after converting a 600-megawatt Mono PERC line into a 750-megawatt TOPCon line. The conversion adds 150 megawatts of capacity and is separate from the 4-gigawatt greenfield development.
Before the conversion, Websol said it had 1.2 gigawatts of Mono PERC cell capacity and 550 megawatts of module capacity. After conversion, management expects 600 megawatts of Mono PERC cell capacity and 750 megawatts of TOPCon cell capacity, while module capacity remains 550 megawatts.
Management said most equipment for the existing upgrade had been shipped and was on its way to the current Falta plant. Civil work and utility readiness were continuing. Websol maintained its target to commercialise the upgraded line by March 2027, about nine months before the planned trial runs at the first greenfield phase.
Got a follow-up? Ask IRIS
What supports Websol's expansion plan?
Websol reported 91% cell-capacity utilisation and 68% module-capacity utilisation in Q2 FY27, while producing more than 255 megawatts of cells. Management said the current TOPCon conversion would provide operational learning for the 2-gigawatt project, and the nearby site could support employee training before the larger facility begins operations.
Q2 FY27 revenue rose 114.6% year on year to Rs 361 crore, while earnings before interest, tax, depreciation and amortisation, or EBITDA, increased 77.3% to Rs 128 crore. Net profit rose 73.2% to Rs 80 crore. In H1 FY27, revenue was Rs 734 crore and EBITDA was Rs 254 crore, both described by management as half-year highs.
The outstanding order book stood at Rs 1,280 crore at the end of Q2 FY27. Management also cited about 30.8 gigawatts of solar-capacity additions in India during the first six months of the financial year. It said the gap between domestic cell and module capacity remained substantial, but added that the eventual supply balance would depend on how quickly announced cell plants are actually completed.
What could affect Websol's Falta timetable?
Websol's December 2027 target depends on completing land development, beginning civil construction, finalising technical arrangements and raising project debt. Management said teams were assessing technical details and engaging vendors for equipment, utilities and electrical supplies, but did not say that greenfield equipment orders or debt facilities had been finalised.
Management addressed potential technology-sourcing constraints after an analyst asked about Chinese restrictions on certain equipment. It said furnaces affected by the restrictions could be sourced outside China and that other Chinese-sourced equipment was not on the restricted list. Websol also said it had not placed a turnkey order with a Chinese company and that its existing upgrade technology provider was German.
The separate ingot-and-wafer plan remains at an earlier stage than the Falta TOPCon project. Websol said it was evaluating technology providers and working to a June 2028 timeline for the Approved List of Models and Manufacturers List III, or ALMM List III. Management had not disclosed the location, cost or financing structure for that project, though it expected to clarify the capex requirement by the next quarter.
Conclusion
Websol has progressed from a 4-gigawatt expansion announcement to a defined first-phase plan: 54.20 acres at Falta, Rs 1,350 crore of estimated investment, a roughly 30% equity and 70% debt funding target, and December 2027 trial runs for the first 2 gigawatts. The plan follows Q2 FY27 cell utilisation of 91% and H1 FY27 net operating cash flow after taxes of Rs 212 crore.
The next items to watch are completion of land development, the expected January start of civil work, debt-raising progress and the March 2027 commercialisation target for the 750-megawatt TOPCon conversion. Management also expects to provide further clarity by the next quarter on proposed ingot-and-wafer capex while monitoring the June 2028 ALMM List III timeline.