WEBSOL expects Q3 FY28 COD for first 2 GW Falta expansion
Key highlights
- WEBSOL expects Q3 FY28 COD for Phase 1 of its Falta cell project.
- WEBSOL has been allotted 54.20 acres at Falta Industrial Park and paid Rs 27.13 crore for the land.
- The Falta facility is planned as 4 GW of integrated cell capacity in two 2 GW phases.
- WEBSOL closed Q2 FY27 with a Rs 1,280 crore order book, including Rs 701 crore of solar-cell orders.
powered by IRIS

WEBSOL expects Phase 1 of its planned 4 GW integrated cell facility at Falta, West Bengal, to achieve commercial operation date, or COD, in Q3 FY28, following the allotment of 54.20 acres and payment of Rs 27.13 crore for the land. The project is planned in two 2 GW phases next to its existing special economic zone, or SEZ, plant.
Know Websol Energy System inside out
Results, valuation, peers and who's buying, in one view.
What is WEBSOL building at Falta?
WEBSOL is planning a 4 GW integrated cell facility at Falta Industrial Park, West Bengal, to be developed in two phases of 2 GW each. The company describes the project as a greenfield expansion and says the 54.20-acre site is next to its existing SEZ plant. The presentation does not disclose total project cost, funding arrangements, equipment suppliers or the intended technology for the Falta cell lines.
The phased 2 GW-plus-2 GW structure is intended to reduce the risk of technology changes, according to WEBSOL. Management also cites the location’s proximity to existing operations, an established supplier base and a skilled workforce as factors that could shorten the lead time to production. The company says a larger, multi-gigawatt manufacturing scale can lower per-unit production cost through higher throughput, but it does not quantify the expected saving.
When does WEBSOL expect the first Falta phase to start?
WEBSOL expects COD of Phase 1 at Falta in Q3 FY28. This is an expected COD rather than a reported commissioning event. The presentation supplies no month within Q3 FY28, no construction timetable for the 2 GW first phase and no stated date for the second 2 GW phase.
The Q3 FY28 target extends beyond the schedule disclosed for WEBSOL’s separate brownfield technology upgrade. For that project, civil work on an existing 600 MW Mono PERC, or passivated emitter and rear cell, line runs from March 2026 to November 2026; equipment ordering and installation run from June 2026 to February 2027; and trial runs and validations are scheduled for February to March 2027. That upgrade is marked for Q4 FY27 trial runs and validations, earlier than the Falta Phase 1 COD expectation.
How does the Falta project change WEBSOL's cell capacity plan?
WEBSOL’s disclosed plan combines the 4 GW Falta cell project with a 600 MW-to-750 MW conversion of an existing Mono PERC line to TOPCon, or tunnel oxide passivated contact, technology. The brownfield conversion would lift total cell capacity to 1.35 GW, according to the presentation. The 4 GW Falta facility is separately described as integrated cell capacity, so the materials do not provide a combined future capacity figure after both initiatives are completed.
The two projects differ in scale, location and execution approach. The TOPCon conversion adds 150 MW to one existing line, while the Falta plan consists of two new 2 GW phases. WEBSOL targets TOPCon cell efficiency of about 25%, compared with 23.35% on Mono PERC, and indicates an approximately three-year payback for that conversion. No efficiency target, payback period or capacity-utilisation assumption is provided for the Falta project.
The current operating data show the backdrop for the capacity plan. Cell production rose from 116 MW in Q2 FY26 to 255 MW in Q2 FY27, while cell capacity utilisation increased from 83% to 91%. Over the same comparison, module production increased from 38 MW to 88 MW and module utilisation rose from 30% to 68%, although both module measures were lower than their Q1 FY27 levels of 103 MW and 81%, respectively.
Got a follow-up? Ask IRIS
What demand and operating data accompany WEBSOL's expansion plan?
WEBSOL reported a closing order book of Rs 1,280 crore at the end of Q2 FY27, up Rs 2 crore from Rs 1,278 crore at the close of Q1 FY27. During Q2 FY27, it executed orders worth Rs 361 crore and recorded new orders worth Rs 363 crore. Solar cells represented Rs 701 crore, or 55%, of the closing order book, while solar modules accounted for Rs 579 crore, or 45%.
Quarterly revenue from operations was Rs 361 crore in Q2 FY27, compared with Rs 373 crore in Q1 FY27 and Rs 168 crore in Q2 FY26. Earnings before interest, tax, depreciation and amortisation, or EBITDA, excluding other income, were Rs 128 crore in Q2 FY27, versus Rs 126 crore in Q1 FY27 and Rs 72 crore a year earlier. Profit after tax was Rs 80 crore, up from Rs 78 crore in Q1 FY27 and Rs 46 crore in Q2 FY26.
The quarterly comparison also shows that Q2 FY27 revenue was below the Rs 401 crore reported in Q4 FY26, while EBITDA of Rs 128 crore was below Rs 146 crore in that quarter. Q4 FY26 profit after tax of Rs 125 crore included a tax effect from an appellate order that allowed set-off of brought-forward losses against current taxable income, reducing tax expense. That disclosed tax item makes the Q4 FY26 profit figure not directly comparable with the later quarters without adjustment information.
What else is in WEBSOL's manufacturing pipeline?
WEBSOL lists three projects in sequence: the TOPCon brownfield upgrade, the phased Falta greenfield cell expansion and a greenfield ingot and wafer facility. For the upstream project, the company identifies Linton Crystal as its equipment and technology support partner. It says in-house ingot and wafer production is intended to add upstream control and improve margins, while reducing reliance on imported wafers.
The company also links the ingot and wafer facility to Approved List of Models and Manufacturers, or ALMM, List-III compliance. The presentation does not provide a site, capacity, capital expenditure, commissioning date or construction status for this facility. In contrast, the Falta disclosure supplies a 54.20-acre land allotment, a Rs 27.13 crore land payment and a Q3 FY28 expected COD for its first 2 GW phase, giving that project the clearest disclosed milestones among the greenfield plans.
Conclusion
WEBSOL has set out a phased route from its current cell operations toward a 4 GW integrated cell facility at Falta: 54.20 acres have been allotted, Rs 27.13 crore has been paid for land, and Phase 1 is expected in Q3 FY28. The plan sits alongside a 150 MW TOPCon capacity increase and an upstream ingot-and-wafer initiative, while Q2 FY27 closed with a Rs 1,280 crore order book.
The next disclosed milestones are the TOPCon upgrade’s equipment installation through February 2027 and trial runs and validations in February to March 2027, followed by the expected Q3 FY28 Phase 1 COD at Falta. Matters still not disclosed include the Falta project’s cost, financing, detailed construction schedule, technology configuration and COD target for Phase 2.