Websol targets March 2027 TOPCon conversion, 1.35 GW capacity
Key highlights
- Websol targets March 2027 commercialisation of a 750 MW TOPCon cell line.
- The conversion would raise Websol cell capacity by 150 MW, from 1,200 MW to 1,350 MW.
- Websol reported 91% cell utilisation and production of more than 255 MW in Q2 FY27.
- Websol estimates the MonoPERC-to-TOPCon conversion will cost about Rs 270 crore.
powered by IRIS

Websol Energy System Limited is targeting March 2027 commercialisation of a converted 750 MW TOPCon cell line, which would lift its cell capacity by 150 MW to 1.35 GW. The project converts an existing 600 MW MonoPERC line and would leave Websol with 750 MW of TOPCon and 600 MW of MonoPERC capacity.
Know Websol Energy System inside out
Results, valuation, peers and who's buying, in one view.
When will Websol complete the TOPCon conversion?
Websol expects to commercialise the 750 MW TOPCon line by March 2027, the final quarter of FY27. Management said on the November 5, 2026 earnings call that the plan remained on track, describing the conversion as its immediate investment priority.
The equipment list has been finalised, advances have been paid and most equipment had been shipped to the Falta facility. Work at the plant was centred on completing civil work and preparing utility infrastructure, while management estimated the brownfield TOPCon upgrade at about Rs 270 crore.
Websol said it was prepared to finance the Rs 270 crore conversion through internal accruals, though it may use some borrowing. This is separate from the proposed 2 GW greenfield project, where management expects debt to be the principal funding source after Websol repaid its IREDA debt in August 2026.
How will Websol's capacity and technology mix change?
Websol's cell capacity would rise from 1,200 MW to 1,350 MW after the conversion, with 750 MW of TOPCon and 600 MW of MonoPERC capacity. Its module capacity remains 550 MW under the disclosed plan, meaning the upgrade changes the cell technology mix rather than module capacity.
The 150 MW addition results from converting a 600 MW MonoPERC line into a 750 MW TOPCon line, rather than from a like-for-like technology replacement. Websol would therefore retain 600 MW of MonoPERC capacity while shifting more than half of its 1,350 MW cell base to TOPCon.
In Q2 FY27, ended September 30, 2026, Websol operated its cell line at 91% utilisation and produced a little over 255 MW of cells. Module utilisation was 68% in the same quarter, placing cell utilisation 23 percentage points above module utilisation as the company prepared the conversion.
What does the TOPCon upgrade mean for prices and operations?
Websol expects TOPCon cells to achieve higher realisations than MonoPERC cells, although management did not provide a forecast for its own selling-price premium. Management also said TOPCon technology offers an efficiency improvement of almost 7% over MonoPERC, while cautioning that realised pricing will depend on market conditions.
The technology comparison does not establish a committed increase in Websol's output efficiency or revenue per unit. The commercial outcome will depend on equipment installation, production ramp-up and customer demand after the 750 MW line is commercialised in March 2027.
Websol is undertaking the upgrade during a period of higher reported operations. Q2 FY27 revenue increased 114.6% year on year to Rs 361 crore, while earnings before interest, tax, depreciation and amortisation, or EBITDA, rose 77.3% to Rs 128 crore and net profit grew 73.2% to Rs 80 crore.
For H1 FY27, Websol reported revenue of Rs 734 crore and EBITDA of Rs 254 crore. Cash from operations increased to Rs 244 crore from Rs 137 crore in H1 FY26, while net operating cash flow after taxes rose to Rs 212 crore from Rs 132 crore, providing the cash-generation context for management's internal-accrual funding plan.
Got a follow-up? Ask IRIS
How does this conversion support Websol's larger Falta expansion?
Websol intends to use the MonoPERC-to-TOPCon conversion as an operating learning platform for the first 2 GW phase of its proposed integrated TOPCon facility at Falta. Management targets trial runs for that 2 GW facility in Q3 FY27-28 and said it aims to start it by December 2027.
Websol has received 54.20 acres at Falta Industrial Park for a proposed 4 GW integrated project, structured in two 2 GW phases. Land development was under way in November 2026, with civil work expected to begin around January 2027; the allotted land is for the integrated TOPCon facility, not the proposed ingot and wafer operation.
Management estimated the first 2 GW phase would cost about Rs 1,350 crore and outlined a funding plan of roughly 30% equity and 70% debt. Websol also said it expects to use about Rs 400 crore to Rs 500 crore of internal accruals, with the remaining funding raised as debt, while retaining flexibility for a second 2 GW phase and planned backward integration.
Websol's chief technology officer said the current conversion would provide the learning curve for the 2 GW plant. Management expects the nearby locations to allow employee training on the converted line before workers move to the new facility, and said the conversion equipment supplier was outside China, limiting the stated impact of Chinese restrictions on certain equipment.
What remains unresolved in Websol's expansion plan?
Websol has announced its intention to add ingot and wafer manufacturing, but has not committed capital or given a final project cost. Management said a different facility would be required for ingot and wafer operations and that it was awaiting clarity on the deadline for ALMM List III before confirming the project's timeline.
Management said it was working to a June 2028 timeline for the ALMM List III mandate as of November 2026. It expected to provide more clarity on ingot and wafer capital expenditure by the following quarter, while its planned 4 GW Falta project and Rs 270 crore conversion remained the disclosed manufacturing priorities.
Conclusion
Websol's March 2027 target combines a 150 MW cell-capacity addition with a substantial technology shift: its planned base changes from 1,200 MW of MonoPERC to 1,350 MW comprising 750 MW of TOPCon and 600 MW of MonoPERC. Equipment shipments, paid advances and Falta utility preparation indicate that the conversion is in execution, while Q2 FY27 cell utilisation of 91% provides operating context.
The next disclosed milestones are March 2027 commercialisation of the 750 MW TOPCon line, civil work around January 2027 for the first 2 GW Falta phase, and targeted trial runs in Q3 FY27-28. Websol's eventual decision on ingot and wafer spending remains dependent on clarity around the ALMM List III timeline, which management was then treating as June 2028.