AVP Infracon says half of H2 revenue relies on new orders
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- AVP Infracon reported Rs 240 crore of revenue in H1 FY 2027 against its Rs 600 crore FY 2027 target.
- AVP Infracon needs Rs 360 crore of revenue in H2 FY 2027 to meet its full-year target.
- Management said 50% of H2 revenue, or about Rs 180 crore, should come from new projects and back-to-back work.
- AVP Infracon cited a Rs 400 crore unexecuted order book expected to be completed within six to eight months.
powered by IRIS

AVP Infracon Limited needs Rs 360 crore of H2 FY 2027 revenue to reach its reiterated Rs 600 crore full-year target, and management said 50% of that second-half revenue would come from new projects and back-to-back orders. AVP Infracon reported Rs 240 crore in H1 FY 2027 and expects Q4 to be its highest-revenue quarter.
Know AVP Infracon inside out
Results, valuation, peers and who's buying, in one view.
How much revenue does AVP Infracon need in H2 FY 2027?
AVP Infracon needs Rs 360 crore of revenue in H2 FY 2027 because its stated FY 2027 target is Rs 600 crore and it reported Rs 240 crore in H1 FY 2027. This means the second half would need to contribute 60% of the full-year target, compared with the 40% delivered in the first half.
Management reiterated the Rs 600 crore target during the November 5, 2026 earnings call, rather than reducing it after H1. The target therefore requires a substantial sequential increase in activity in H2, especially in the January-to-March Q4 period that management described as the highest-revenue quarter of its four-quarter cycle.
How much of AVP Infracon's H2 target comes from existing projects?
AVP Infracon said at least 50% of its Rs 360 crore H2 requirement, or about Rs 180 crore, should come from existing projects. Management also said its Rs 400 crore unexecuted order book would be completed within six to eight months, indicating that the current portfolio supplies a significant part, but not all, of the revenue needed in the remaining half-year.
The balance 50% of the H2 requirement, or about Rs 180 crore, is expected from new projects and back-to-back work. That split is central to the FY 2027 target because AVP Infracon is not relying only on the Rs 400 crore unexecuted order book but also on converting additional opportunities during H2.
Why does AVP Infracon expect orders to rise in H2?
AVP Infracon expects its order book to increase in H2 because management said tender processes generally occur after budgeting processes are completed. The company said it had bid for several projects and that its order-book additions have historically occurred in the second half rather than in H1.
Management specifically identified Q4, covering January, February and March, as the period when revenue rises most sharply. It said that in the prior year, Q4 revenue was almost equal to the combined revenue of Q1, Q2 and Q3, although it did not provide quarterly amounts on the November 5, 2026 call. This historical pattern is the basis for management's confidence that the FY 2027 run rate can accelerate.
The Rs 400 crore order book also includes work beyond Tamil Nadu state-government projects. Management described around Rs 125 crore as state-government work and around Rs 225 crore as National Highways Authority of India, or NHAI, work, with the remainder linked to private and back-to-back work. AVP Infracon said it bids for NHAI and Ministry of Road Transport and Highways projects outside Tamil Nadu while not pursuing other states' government projects.
Got a follow-up? Ask IRIS
What new business must AVP Infracon finalise to meet its target?
AVP Infracon must convert negotiations for new and back-to-back projects into executable orders to supply about Rs 180 crore of its H2 FY 2027 requirement. Management said it was close to finalising some back-to-back projects with leading contractors but could not disclose them because contracts had not been finalised.
The outstanding issue on those potential projects was commercial pricing, rather than primary financial or technical evaluation, according to management. It also said it was pursuing two or three quotation-based orders, including repeat business from an earlier customer. These are prospects rather than disclosed secured orders, so their timing and value remained unresolved on the November 5, 2026 call.
This distinction matters because AVP Infracon described Rs 400 crore as its unexecuted order book, while the additional H2 contribution is linked to bids, negotiations and repeat-order quotations. Management said back-to-back projects could be finalised “any moment” but provided neither contract values nor specified award dates.
What execution and cash-conversion factors could affect H2 revenue?
AVP Infracon said it had no administrative-approval delays as of the November 5, 2026 call. Management said receivables had returned to a free flow after delays during the first three or four months following formation of the new government, and that earlier receivables of around Rs 140 crore in March had declined after collections.
The company also said an increase in other current assets reflected an accounting classification rather than a new operating asset. Unbilled revenue that had earlier been included in inventory was reclassified into other current assets as AVP Infracon prepares to adopt Indian Accounting Standards, or Ind AS, next year. Management said unbilled revenue is usually billed within three to four months in infrastructure companies.
For contracts, management said all work other than state-government contracts has price-variation or price-escalation provisions. Tamil Nadu state-government contracts also have escalation provisions, but management said there is a 5% cap of total project cost before a revised administrative sanction is required. The company said contractors had applied for such sanctions and that the government had accepted the process.
Conclusion
AVP Infracon's reiterated Rs 600 crore FY 2027 revenue target requires a clear H2 acceleration from Rs 240 crore reported in H1. Existing projects are expected to provide at least Rs 180 crore of the Rs 360 crore H2 requirement, while the balance depends on new projects and back-to-back orders that were still under commercial negotiation on November 5, 2026.
The next markers are the finalisation of undisclosed back-to-back projects, conversion of two or three repeat-order quotations, and execution in the January-to-March Q4 period that management said has historically generated revenue almost equal to the preceding three quarters combined. Management also said it would try to keep FY 2028 revenue at Rs 750 crore to Rs 800 crore, describing those figures as conservative.