Bondada Executes India’s First Two Utility-Scale VRFB Projects
Key highlights
- Bondada said it is executing India’s first two utility-scale VRFB projects for two agencies.
- Management said the next 18 months could establish confidence in VRFB for long-duration energy storage.
- Bondada reported an approximately 1,250 MWh BESS order book, including approximately 850 MWh of annuity-based orders.
- Management cited a 14% to 14.5% IRR over 12 years for 850 MWh of annuity BESS orders.
powered by IRIS

In the earnings call, Bondada Engineering Limited said it is executing India’s first two utility-scale vanadium redox flow battery, or VRFB, projects for two agencies. Management said the next 18 months could establish confidence in VRFB as a long-duration energy-storage technology, but it did not disclose the projects’ capacities, values, sites or completion dates.
Know Bondada Engineering inside out
Results, valuation, peers and who's buying, in one view.
Which VRFB projects is Bondada executing?
Bondada said it is executing two utility-scale VRFB projects for two different agencies, which management described as the nation’s first two largest projects of their kind. In closing remarks, management also called them India’s first two grid-scale VRFB orders. The transcript does not identify either agency, the technology partner, or the projects’ megawatt and megawatt-hour capacities.
The projects extend Bondada’s battery energy storage system, or BESS, activity, which management said it entered less than 18 months earlier. Management said Bondada had won significant profitable BESS orders and was on schedule to execute them despite force majeure conditions notified by the Ministry of New and Renewable Energy, or MNRE. No revenue, cost, margin or funding estimate was disclosed for the two VRFB contracts.
Management presented the two installations as an early demonstration of a technology rather than evidence of completed operating performance. Chief Executive Officer R. Sreenivas said execution of the two projects would set the tone for India’s approach to energy storage, especially longer-duration applications. That remains management’s view because the call provided no commissioning, operational or performance data from either project.
How does Bondada compare VRFB with lithium-ion storage?
Bondada said VRFB can address life and duration constraints that management associated with lithium-ion storage. Sreenivas said lithium-ion systems had a life limit of nearly 12 years and two-hour or four-hour cycle duration, whereas a VRFB plant’s life could be comparable to that of a solar plant and its operating duration could be configured around peak-hour demand.
The comparison positions VRFB as a long-duration storage option rather than simply another BESS equipment category. Bondada said the technology could support electricity supply during peak periods, but it did not give an hourly duration for either utility-scale project. The transcript also contains no installed-cost comparison, performance guarantee, degradation assumption or warranty term for VRFB versus lithium-ion systems.
Bondada said it is working with a technology partner that had already demonstrated a pilot-scale VRFB project with NTPC. The company is also examining follow-on VRFB supply-chain opportunities, including vanadium electrolytes. This suggests an interest beyond engineering, procurement and construction, or EPC, work, although management gave no investment amount, commercial arrangement or timetable for supply-chain activity.
Got a follow-up? Ask IRIS
Why does Bondada expect VRFB sourcing to affect margins?
Bondada said diverse VRFB raw-material sources could support better margins than lithium-ion technology, whose supply management described as dependent on a single source. Asked directly about margin differences, Sreenivas did not provide a VRFB margin range, internal rate of return, or IRR, or earnings before interest, taxes, depreciation and amortisation, or EBITDA, figure. He instead cited reduced dependence on one country as the reason for the view.
That assessment follows management’s disclosure of battery-cell and imported-battery price volatility in its broader BESS business. Bondada said it slowed BESS order intake over the preceding six to seven months, or roughly two quarters, because of volatility in cell availability and imported battery prices. Management said it expected intake to recover from the current quarter as cell availability stabilised.
Bondada disclosed an approximately 1,250 megawatt-hour, or MWh, BESS order book. Of that amount, management said about 850 MWh was annuity-based and about 350 MWh was EPC work, leaving approximately 50 MWh not categorised in the call. The company said bank finance had closed for the 850 MWh annuity portfolio, which was under execution and expected to generate a 14% to 14.5% IRR over 12 years.
Bondada did not say whether either VRFB project sits in the 850 MWh annuity portfolio, the 350 MWh EPC portfolio, or the uncategorised balance. The stated VRFB margin advantage is therefore a management assessment based on sourcing, not a disclosed project-level return. By comparison, management provided a 12% to 13% EBITDA margin range for conventional BESS EPC work.
How does VRFB fit Bondada’s planned business mix?
Bondada said annuity revenue and new technologies could contribute 30% to 35% of its business over the next three years, compared with EPC’s current contribution of about 90% to 92%. Management described the intended revenue mix as 70:30 and said it expected to maintain or improve EBITDA margins as annuity activity increased. The company did not assign a specific share of that shift to VRFB.
VRFB is one of several diversification areas identified by Bondada, alongside BESS, defence and data-centre activity. The company said that within about nine months of announcing its data-centre entry, it had concluded a definitive agreement to develop primary infrastructure for a 50-megawatt hyperscale data centre that could scale to 300 megawatts. The wider strategy means VRFB is part of a move beyond a predominantly EPC-led model rather than a separately disclosed earnings segment.
Management also cited a revenue target of Rs 10,000 crore by 2030, saying that this represented roughly three to four times growth from the current level. It did not allocate that target among VRFB, lithium-ion BESS, solar EPC, data centres or defence. For VRFB, the specific disclosed milestone is confidence-building through execution over the next 18 months rather than an order-book, capacity or revenue target.
Conclusion
Bondada’s central disclosure is that it is executing two utility-scale VRFB projects that management calls India’s first two largest installations of their kind. The company argues that VRFB can provide longer operating life and more adaptable duration than the lithium-ion model it described, while a diversified raw-material base could reduce single-country supply dependence. Those technology and margin comparisons are management’s views, not reported project results.
The next development to watch is execution during the 18 months management identified as important for establishing confidence in VRFB. Investors will need further disclosure on capacity, counterparties, contract structure, warranties and project economics to assess the importance of the two orders. Separately, management plans for annuity revenue and new technologies to represent 30% to 35% of business over the next three years.