Capacit’e plans Rs 140 crore FY '27 formwork spend as costs rise
Key highlights
- Capacit’e plans Rs 135 crore to Rs 140 crore of FY '27 formwork procurement after spending Rs 64.2 crore in H1 FY '27.
- Aluminium formwork rose 40% to Rs 14,500 per square metre from Rs 10,500 per square metre.
- Capacit’e reported Q2 FY '27 revenue of Rs 771 crore, up 19% year on year, and EBITDA of Rs 119 crore.
- Management has factored Rs 45 crore to Rs 50 crore of FY '27 revenue loss from potential NGT restrictions.
powered by IRIS

Capacit’e plans Rs 135 crore to Rs 140 crore of FY '27 formwork procurement despite a 40% increase in aluminium-formwork prices to Rs 14,500 per square metre, after purchasing Rs 64.2 crore in H1 FY '27, because management expects the higher upfront outlay to affect cash deployment rather than reported profitability.
Know Capacite Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
How much will Capacit’e spend on formwork in FY '27?
Capacit’e expects to complete its Rs 135 crore to Rs 140 crore budgeted formwork procurement during FY '27 because its order pipeline is strong. Management corrected an earlier response on the call and said H1 FY '27 formwork purchases were Rs 64.2 crore, while plant and machinery purchases were Rs 10.57 crore.
The planned formwork spend is tied to the number and scale of projects that Capacit’e begins each quarter. Management said capital-expenditure requirements are directly proportional to order intake and the quantum of project starts, making the FY '27 procurement budget part of the equipment requirement for execution rather than a stand-alone spending target.
The H1 FY '27 formwork purchase of Rs 64.2 crore represents less than half of the Rs 135 crore to Rs 140 crore full-year procurement budget. Management therefore indicated that the balance of procurement would be required in H2 FY '27 as projects progress and the order pipeline translates into site activity.
Why have Capacit’e's aluminium-formwork costs increased?
Capacit’e said aluminium-formwork prices increased 40% to Rs 14,500 per square metre from Rs 10,500 per square metre. Management said aluminium prices had declined but remained above pre-war levels, while dollar appreciation had also added to the cost of procurement.
Management expects future aluminium-formwork purchases to correct to about Rs 12,000 to Rs 12,500 per square metre, but did not predict a return to pre-war pricing. It also cited steel prices of about Rs 62,000 per metric tonne, compared with Rs 47,000 per metric tonne three months earlier, as evidence of continuing input-cost volatility.
The gap between cost inflation and contractual escalation also narrowed during FY '27, according to management. It said the difference was 5% to 6% in Q1 FY '27 and had reduced to about 2% in Q2 FY '27, while government wholesale-price indices can take six to nine months to reflect changes in international markets.
Will higher formwork prices reduce Capacit’e's profitability?
Management said higher aluminium-formwork prices should not materially affect Capacit’e's reported profitability because formwork is capital expenditure depreciated over five to six years. It illustrated the cash effect by saying a formwork purchase that previously cost Rs 1 crore would now require Rs 1.4 crore of upfront cash.
Management said it was too early to quantify the full-year cash-flow effect of the additional Rs 2,000 per square metre aluminium cost. It described the likely effect on full-year cash flow from operations as slight or negligible, but said it needed to observe prices for a further period before assessing the outcome.
Capacit’e maintained FY '27 earnings before interest, tax, depreciation and amortisation, or EBITDA, margin guidance of 15.5% to 16.5%. It also retained cash profit after tax, or cash PAT, guidance of about 10.5% to 11.25%, after reporting Q2 FY '27 revenue of Rs 771 crore and EBITDA of Rs 119 crore.
The Q2 FY '27 comparison shows revenue rising faster than EBITDA. Revenue increased 19% year on year to Rs 771 crore, while EBITDA rose 10% to Rs 119 crore and the EBITDA margin was 15.5%; management linked margin pressure to commodity costs, although contractual escalation reduced part of the effect.
Got a follow-up? Ask IRIS
How does Capacit’e's formwork plan support revenue growth?
Capacit’e links additional equipment deployment to its plan to reach Rs 4,000 crore of revenue in FY '28. Management said the business had exceeded a Rs 260 crore monthly run rate in the preceding month and was positioned to exceed Rs 300 crore by Q4 FY '27.
Capacit’e reported H1 FY '27 revenue of Rs 1,400 crore, up 13% year on year, and EBITDA of Rs 218 crore, up 4%. PAT was Rs 87 crore in H1 FY '27, compared with Rs 98 crore in H1 FY '26, a decline that occurred while management cited commodity-price and escalation timing pressures.
Management said Capacit’e's consolidated fixed-asset revenue-turnover ratio was 4.7% at September 30, 2026, and expects it to be above 5 at Rs 4,000 crore of revenue. That is management's projection and depends on future order intake, project starts and the use of assets across construction sites.
The available order base supports the planned capacity additions. Capacit’e's order book stood at Rs 13,013 crore on September 30, 2026, with 54% from public-sector projects and 46% from private-sector projects, while management said active bid negotiations totalled Rs 3,270 crore.
What could affect Capacit’e's procurement and execution plan?
National Green Tribunal, or NGT, restrictions in the National Capital Region could affect Capacit’e's FY '27 execution schedule. Management has factored in Rs 45 crore to Rs 50 crore of possible revenue loss from NGT-related disruption during winter, while stating that it did not then anticipate water-supply issues for its urban construction sites.
Labour availability around elections is another variable for the FY '27 plan. Management said Q1 FY '27 revenue was affected by the Bengal elections, but labour availability was currently strong and Capacit’e was taking steps to retain workers ahead of Q4 FY '27.
Project ramp-ups could increase both revenue and formwork needs. Capacit’e said CIDCO generated Rs 177 crore in the first six months, or nearly Rs 30 crore per month, and management expects that run rate to increase by 35% to 40% in Q3 and Q4 before reaching at least Rs 50 crore per month in the next financial year.
Conclusion
Capacit’e's Rs 135 crore to Rs 140 crore FY '27 formwork procurement plan indicates that management is preparing for higher project execution despite aluminium formwork costing Rs 14,500 per square metre versus Rs 10,500 previously. Management's stated distinction is that the 40% price increase raises immediate cash deployment because the equipment is depreciated over five to six years, rather than directly reducing reported profitability.
The next disclosures to watch are H2 FY '27 procurement against the Rs 135 crore to Rs 140 crore budget, movement in aluminium prices toward management's Rs 12,000 to Rs 12,500 per square metre expectation, and any NGT disruption within the Rs 45 crore to Rs 50 crore revenue contingency. Management also said it would be better placed to assess any provision reversal when it next reports Q3 FY '27 results.