- Diamond Power Infrastructure received a Rs 707.80 crore purchase order, including GST, from Adani Energy Solutions.
- The order covers 9,059.33 km of AL-59 conductors for the ±800 kV Bhadla-Fatehpur HVDC project.
- The basic order value is Rs 599.83 crore excluding GST.
- Month-wise deliveries must be completed by December 31, 2027.
powered by IRIS

Diamond Power Infrastructure has received a Rs 707.80 crore purchase order, including GST, from Adani Energy Solutions to supply 9,059.33 km of AL-59 conductors for the ±800 kV Bhadla-Fatehpur HVDC transmission project. The order adds a large transmission-equipment supply contract to Diamond Power Infrastructure's disclosed order wins.
Know Diamond Power Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
What order has Diamond Power Infrastructure received from Adani Energy Solutions?
Diamond Power Infrastructure has received a purchase order from Adani Energy Solutions for AL-59 overhead transmission conductors for the Bhadla-Fatehpur high-voltage direct current, or HVDC, project. The order is valued at Rs 707.80 crore, including Goods and Services Tax.
The company will supply 9,059.33 km of conductors for the ±800 kV transmission project. The disclosed scope includes design, engineering, manufacturing, testing, packing and supply of the conductors. This makes the contract a supply assignment that covers multiple stages before delivery.
Adani Energy Solutions is the customer named in the purchase order. The filing identifies the Bhadla-Fatehpur project as the end-use project but does not disclose separate payment milestones or a break-up of the contract value by activity.
What are the order value and delivery terms?
The purchase order's basic value is Rs 599.83 crore excluding GST, while its total value including GST is Rs 707.80 crore. Deliveries are scheduled to be made month-wise in line with the project schedule and must be completed by December 31, 2027.
The long delivery period means the announced order is linked to execution over more than one year rather than a single immediate shipment. The filing does not state how much of the order will be supplied in any particular financial year.
Why are AL-59 conductors required for the Bhadla-Fatehpur project?
AL-59 conductors are the specified transmission conductors under the order for the ±800 kV Bhadla-Fatehpur HVDC project. HVDC systems are used for high-voltage direct-current electricity transmission, and the project requires conductors across a substantial route length.
The supplied context describes the corridor as being developed to transmit renewable energy from Rajasthan to demand centres in northern India. Within that project, Diamond Power Infrastructure's stated role is limited to the conductor supply scope set out in the purchase order.
The company has also disclosed other Adani Energy Solutions work during 2026. In July, it received a letter of award valued at Rs 185 crore excluding GST for AL59 aluminium alloy conductors for transmission projects in Tuticorin and Pune. That assignment covered 1,050 km of Moose conductor and 3,770 km of Zebra conductor.
Got a follow-up? Ask IRIS
How does the Adani order affect Diamond Power Infrastructure's disclosed business?
The Rs 707.80 crore purchase order represents a sizeable disclosed contract for Diamond Power Infrastructure and provides a scheduled supply programme through December 2027. Its financial recognition, however, will depend on the timing of manufacturing, supply and other applicable accounting conditions, none of which are detailed in the filing.
For investors, the key disclosed measures are the order's value, the 9,059.33 km quantity and the execution deadline. The filing does not provide an order-book total after the award, expected profit margin, financing details or a revised revenue outlook.
The announcement also places the company within ongoing transmission-equipment procurement for a major HVDC corridor. For Adani Energy Solutions, the order identifies a conductor supplier for the Bhadla-Fatehpur project, with month-wise deliveries aligned to the underlying project schedule.
What has Diamond Power Infrastructure disclosed about its recent order activity?
Diamond Power Infrastructure has reported several power-sector and cable supply orders during 2026. Besides the earlier Rs 185 crore Adani Energy Solutions conductor award, it disclosed a Rs 435.71 crore order in July for high-tension and low-tension power cables for 310 MW data-centre projects in Hyderabad.
These announcements involve different products and customers or projects, so their values should not be treated as interchangeable revenue figures. The current purchase order specifically concerns AL-59 conductors for the Bhadla-Fatehpur HVDC project and is valued at Rs 707.80 crore including GST.
The company was reported trading at Rs 368.50 on the BSE following the order announcement, up Rs 2.65 or 0.72% from the previous close of Rs 365.85. That price movement is a reported market snapshot and does not establish the longer-term market effect of the contract.
Conclusion
Diamond Power Infrastructure's Rs 707.80 crore purchase order from Adani Energy Solutions covers the supply of 9,059.33 km of AL-59 conductors for the ±800 kV Bhadla-Fatehpur HVDC project. The contract's basic value is Rs 599.83 crore excluding GST, and its scope extends from engineering and manufacturing to testing, packing and supply.
The next disclosed execution point is the month-wise delivery programme, with completion required by December 31, 2027. Investors will need to track future company disclosures for supply progress, order-book updates and any financial impact attributed to this contract.