Embassy Developments faces appeal but no CIRP is pending
Key highlights
- The lender’s facilities to Sinnar Thermal Power aggregated Rs 144.40 crore.
- The NCLAT dismissed the lender’s Section 7 application against Embassy Developments on May 4, 2026.
- The Supreme Court issued notice on August 31, 2026 but did not stay the NCLAT ruling.
- Embassy Developments said no CIRP was pending against it as at September 30, 2026.
powered by IRIS

Embassy Developments Limited has no corporate insolvency resolution process pending against it despite a Supreme Court appeal over a legacy Rs 144.40 crore Sinnar Thermal Power facility, because the National Company Law Appellate Tribunal’s May 4, 2026 judgment setting aside the admission order has not been stayed.
Know Embassy Developments inside out
Results, valuation, peers and who's buying, in one view.
Why is Embassy Developments connected to Sinnar Thermal Power?
Embassy Developments is connected through a conditional corporate guarantee issued in financial year 2010-11 for equity infusion into Sinnar Thermal Power Limited, which was then its wholly owned subsidiary. Sinnar Thermal Power was demerged into a third-party entity in financial year 2011-12 and, according to Embassy Developments, was no longer under the company’s control after that transaction.
The guarantee was replaced during financial year 2011-12 under the demerger arrangement. Embassy Developments said its revised obligation was to infuse equity only if the new promoters did not do so, rather than a stated obligation to repay the borrower’s bank debt. The company identified Rattan India Power Limited and Rattan India Enterprises Limited as the new promoters and said they were not related to it.
Sinnar Thermal Power approached a consortium of banks for credit facilities during financial years 2010-11, 2013-14 and 2016-17. The lender, then known as Syndicate Bank, specifically sanctioned facilities aggregating Rs 144.40 crore. After the demerger and transfer of control, Sinnar Thermal Power defaulted in financial year 2017-18, was classified as a non-performing asset, or NPA, and is undergoing its own Corporate Insolvency Resolution Process, or CIRP.
The lender invoked the corporate guarantee against Embassy Developments and the new promoters, claiming that the guarantee required repayment of loans due to it. Embassy Developments’ disclosure therefore distinguishes between Sinnar Thermal Power, which it says is undergoing CIRP following the 2017-18 default, and Embassy Developments, against which no CIRP was pending as at September 30, 2026.
What happened in the NCLT and NCLAT proceedings?
The National Company Law Tribunal, or NCLT, Delhi Bench admitted the lender’s application against Embassy Developments on December 9, 2025. That order initiated CIRP and appointed an Interim Resolution Professional, or IRP, under the Insolvency and Bankruptcy Code, 2016, based on the lender’s interpretation of the guarantee connected to the Rs 144.40 crore facilities.
Embassy Developments appealed immediately to the National Company Law Appellate Tribunal, or NCLAT. On December 11, 2025, two days after the NCLT order, the NCLAT stayed both the CIRP and the IRP appointment pending adjudication of the appeal. The interim order meant that the NCLT process did not continue while the appellate tribunal considered the case.
The NCLAT then allowed Embassy Developments’ appeal on May 4, 2026 after detailed hearings and dismissed the lender’s application under Section 7 of the Insolvency and Bankruptcy Code. Section 7 is the provision through which a financial creditor may initiate insolvency proceedings. The May ruling set aside the NCLT’s December 9, 2025 admission order.
The December 11, 2025 stay and the May 4, 2026 decision had different effects. The first order temporarily paused CIRP and the IRP appointment; the later judgment dismissed the lender’s application altogether. Embassy Developments said the May judgment, rather than only the earlier interim stay, remains operative at the September 30, 2026 reporting date.
Got a follow-up? Ask IRIS
What is the Supreme Court appeal about?
The lender has appealed to the Supreme Court under Section 62 of the Insolvency and Bankruptcy Code, seeking restoration of the NCLT’s December 9, 2025 admission order. The appeal keeps the guarantee dispute alive, but Embassy Developments did not disclose that the Supreme Court had restored CIRP or appointed an IRP against it.
On August 31, 2026, the Supreme Court condoned the lender’s delay in re-filing the appeal, issued notice to Embassy Developments and listed the matter for further hearing. The disclosure gives no date for the next hearing. Embassy Developments said it is contesting the appeal.
Most importantly, the Supreme Court did not grant a stay of the NCLAT judgment dated May 4, 2026. Embassy Developments therefore said that the NCLAT ruling remains in effect and that the NCLT admission order continues to be set aside. The current appeal challenges that result but has not, on the disclosed facts, changed the company’s insolvency status.
The position was disclosed in unaudited consolidated results approved by the board on November 3, 2026 for the quarter and half year ended September 30, 2026. The filing does not quantify a potential liability arising from the guarantee, predict the outcome of the Supreme Court appeal, or state a timetable beyond the matter being listed for further hearing.
Does the appeal affect Embassy Developments’ operations or finances?
Embassy Developments said it continues to operate in the normal course of business and that the dispute has had no impact on its operations, governance, financial position or business activities. That statement accompanied its September 30, 2026 unaudited consolidated results, which cover the holding company and 184 subsidiaries and joint ventures.
The group reports one business segment under Indian Accounting Standard 108, or Ind AS 108: real estate development and other real estate-related services. It also said it primarily operates in India and treats its activities as a single geographical segment. Sinnar Thermal Power’s historical activity was power generation, making it different from the group’s reported real-estate segment.
The company’s account of the demerger is central to its stated position. Sinnar Thermal Power was within Embassy Developments’ control before financial year 2011-12, but the company said it was managed after the demerger by a separate promoter entity. The lender’s claim nevertheless concerns the conditional guarantee first issued in financial year 2010-11 and amended in financial year 2011-12.
The September 30, 2026 filing also records that four non-operational subsidiaries, including three step-down subsidiaries and one foreign subsidiary, were struck off during the half year. That corporate action is separate from the Sinnar Thermal Power dispute, as is the company’s statement that no CIRP is currently pending against Embassy Developments.
Conclusion
The disclosed position is that Embassy Developments remains in a live legal dispute over a legacy conditional guarantee linked to Rs 144.40 crore of facilities for Sinnar Thermal Power. However, the NCLAT’s May 4, 2026 judgment dismissing the lender’s Section 7 application continues to govern because the Supreme Court had not stayed that ruling as of the September 30, 2026 reporting date.
The next disclosed event to watch is the further Supreme Court hearing following the August 31, 2026 notice. The lender seeks restoration of the December 9, 2025 NCLT admission order, while Embassy Developments says it is contesting the appeal; any order granting a stay or restoring the admission order would alter the procedural position disclosed on November 3, 2026.