GE Vernova T&D India’s Rs 3,100 crore approval lapses
Key highlights
- GE Vernova T&D India’s Rs 3,100 crore Middle East-France export approval lapsed at the 2026 AGM.
- GE Vernova T&D India booked Rs 1,040 crore of export orders in H1 FY26-27, versus Rs 1,180 crore in full-year FY25-26.
- A US$151 million US data-centre transformer order remained under discussion, with approval valid until May 15, 2027.
- GE Vernova T&D India had a Rs 21,440 crore order backlog at September 2026.
powered by IRIS

GE Vernova T&D India Limited’s Rs 3,100 crore approval for Middle East and France exports lapsed at the 2026 annual general meeting after the end customer delayed operational planning, while management hopes to conclude a separate US$151 million US data-centre transformer order in H2 FY26-27. The US approval remains valid until May 15, 2027.
Know GE Vernova T&D India inside out
Results, valuation, peers and who's buying, in one view.
Why did GE Vernova T&D India’s Rs 3,100 crore export approval lapse?
GE Vernova T&D India’s Rs 3,100 crore export approval lapsed because the underlying customer order was on hold due to the customer’s operational-planning delays. The company had obtained shareholder approval at its 2025 annual general meeting, or AGM, for exports of high-voltage switchgear components to two related parties in the Middle East and France. Management said a related-party approval is valid for one year, so the authority expired at the 2026 AGM.
The approval covered a potential transaction rather than a booked order. Managing Director and Chief Executive Officer Sandeep Zanzaria said the wider project was of a much bigger size, but the customer had imposed the hold. He said it was too early to say whether the hold would be lifted in six months, eight months or a year, leaving the timing of any renewed approval or order unresolved.
The held-up approval contrasts with the company’s current order intake. GE Vernova T&D India reported Q2 FY26-27 order intake of Rs 2,440 crore, up 52% year on year from Rs 1,610 crore in the quarter ended September 2025. Cumulative H1 FY26-27 intake was about Rs 3,580 crore, a year-on-year increase of 11%.
How is GE Vernova T&D India’s regular export order flow performing?
GE Vernova T&D India’s regular export order flow accelerated in H1 FY26-27 despite the large Middle East-France approval lapse. The company booked Rs 1,040 crore of export orders in the first half, compared with Rs 1,180 crore in the whole of FY25-26. Chief Financial Officer Sushil Kumar said a significant part of the H1 export bookings came from related parties, but represented normal product orders rather than the large material related-party opportunity.
The H1 total was about 88% of the preceding full-year amount, showing that smaller export orders continued to arrive while the larger project remained on hold. Management described the smaller-order pipeline as broad-based across geographies. Zanzaria cited investment in several markets, stretched supply chains and factory certifications developed during the previous year as factors supporting opportunities.
Exports represented 29% of H1 FY26-27 order intake and 31% of H1 revenue. In Q2 FY26-27, exports accounted for 21% of orders but 32% of revenue, indicating that quarterly export execution included work ordered before the quarter. The company cited equipment orders for gas-insulated switchgear, or GIS, and air-insulated switchgear, or AIS, across North America, Europe, the Middle East and Africa, alongside grid-automation packages.
Will GE Vernova T&D India secure the US data-centre transformer order?
GE Vernova T&D India has not secured the US order, but management hopes to conclude the US$151 million opportunity in H2 FY26-27. The company has a related-party approval for goods exported from India to a US entity, valid through May 15, 2027. Kumar said the order was still at the discussion stage with customers on the October 30, 2026 earnings call.
Management identified the proposed supply as transformers for US data centres. This differentiates the US opportunity from the Middle East-France approval, which concerned high-voltage switchgear components and had lapsed after the customer-side hold. GE Vernova T&D India did not provide a signing date, expected order-book contribution or assurance that the US discussions would result in an order.
The company also said it had approval for Rs 1,300 crore of potential orders that could flow from the global organisation’s order pipeline, with finalisation still under way. Zanzaria said GE Vernova has two transformer factories in Asia: Indonesia produces transformers up to 245 kilovolts, while higher-rated transformers are manufactured in Vadodara. That manufacturing position was discussed in connection with potential global-factory orders.
Got a follow-up? Ask IRIS
What supports GE Vernova T&D India while the large export opportunity is delayed?
GE Vernova T&D India said domestic orders and smaller exports are supporting activity while the large export opportunity has no timetable. Management described Q2 FY26-27 domestic bookings as regular orders rather than one-off wins. These included a package for a 1,500-megawatt pumped-storage hydro project in Maharashtra, GIS packages for transmission projects in Andhra Pradesh, and reactor and GIS supplies for a tariff-based competitive bidding transmission project in Himachal Pradesh.
Management also expects domestic transmission opportunities to remain active over the next four to five months. Zanzaria said GE Vernova T&D India had been declared the lowest bidder for the Barmer project and that Power Grid had acquired the project. He said management expected the order to be significant for booking in the current quarter, which was an expectation rather than a reported award.
The order backlog was Rs 21,440 crore at September 2026, nearly unchanged from Rs 21,460 crore at March 2026. Management said the September backlog represented more than three years of FY25-26 revenue. Q2 FY26-27 revenue rose 32% year on year to Rs 2,030 crore, while H1 revenue increased 35% to about Rs 3,860 crore.
Operating performance also reflected the pace of execution. Q2 earnings before interest, tax, depreciation and amortisation, or EBITDA, were Rs 550 crore, equal to 27.1% of revenue, while profit before tax and exceptional items was Rs 580 crore. Management said H1 EBITDA margin was about 26.2% and reiterated its guidance for a mid-20% EBITDA margin over the full year.
How is GE Vernova T&D India funding capacity and localisation?
GE Vernova T&D India generated Rs 1,010 crore of cash in H1 FY26-27 and had about Rs 3,250 crore of cash and cash equivalents at September 2026, including funds lent to the cash pool. The company said finance costs remained negligible because it maintained a net zero debt position. These figures accompanied a disclosed capacity-expansion programme of about Rs 1,000 crore.
Management said roughly 20% of the Rs 1,000 crore programme had already been incurred by the Q2 FY26-27 call. Zanzaria said the company had localised transformer, valve and control production for high-voltage direct current, or HVDC, systems in India, although some components supplied by subcontractors and vendors still come from outside India.
Management said the next phase of localisation would involve developing Indian supply sources for such components, including testing products to company requirements before use. It also said it would continue evaluating market conditions and would consider additional capital expenditure if required. The company expects a minimum of two to three HVDC projects to emerge next year, according to Zanzaria.
Conclusion
The lapse of the Rs 3,100 crore Middle East-France approval means a sizeable potential export transaction has no confirmed timing, because the end customer’s planning delay remains unresolved. However, GE Vernova T&D India reported Rs 1,040 crore of H1 export orders, Q2 revenue of Rs 2,030 crore and a Rs 21,440 crore September 2026 backlog, showing that routine exports and domestic execution continued alongside the delay.
The next disclosed event to watch is management’s H2 FY26-27 target to conclude the US$151 million data-centre transformer opportunity before its approval expires on May 15, 2027. Management also expects the Barmer project to be booked in the current quarter and sees a domestic transmission pipeline for the next four to five months, while it has given no schedule for the Middle East-France customer hold to end.