Godawari Power and Ispat Limited targets Q1 FY28 BESS start
Key highlights
- GPIL targets Q1 FY28 commissioning for its 20 GWh BESS project.
- GPIL had incurred Rs 609 crore on the 20 GWh project through September 30, 2026.
- GPIL received Rs 2,795 crore of sanctioned BESS facilities, including Rs 700 crore of term debt.
- GPIL acquired 112 acres in Maharashtra for the 20 GWh BESS project.
powered by IRIS

Godawari Power and Ispat Limited is targeting Q1 FY28 commissioning of its 20 gigawatt-hour (GWh) Battery Energy Storage System (BESS) project, planned at Rs 1,425 crore, after incurring Rs 609 crore through September 30, 2026 and receiving Rs 2,795 crore of sanctioned credit facilities.
Know Godawari Power & Ispat inside out
Results, valuation, peers and who's buying, in one view.
What is GPIL building through its BESS expansion?
GPIL is executing a 20 GWh BESS project as a diversification from steel into clean-energy infrastructure. The project is planned at Rs 1,425 crore and is to be funded with debt and equity in a 1:1 ratio, while the stated commissioning target is Q1 FY28.
The 20 GWh project is being executed through Godawari New Energy Private Limited, which GPIL describes as its wholly owned subsidiary. GPIL has also decided to establish a separate 3 GWh BESS capacity for commercial and industrial applications, with planned capital expenditure of Rs 135 crore and commissioning targeted for March 2028.
The proposed manufacturing capacity is much larger than GPIL's BESS installation for captive solar power. That captive project has a 45 megawatt-hour (MWh) capacity, Rs 39 crore incurred through September 30, 2026, and a December 2026 commissioning target; 20 GWh is equivalent to 20,000 MWh.
How much has GPIL spent and financed for the 20 GWh project?
GPIL had incurred Rs 609 crore on the 20 GWh BESS project up to September 30, 2026. The project-specific disclosure gives planned capital expenditure of Rs 1,425 crore, while the growth-capex pipeline also records the same Rs 609 crore incurred figure.
GPIL has received sanctions for credit facilities aggregating Rs 2,795 crore for the BESS project. The facilities comprise Rs 700 crore of term debt and Rs 2,095 crore of working-capital facilities, including Rs 100 crore of fund-based facilities and Rs 1,995 crore of non-fund-based facilities.
The growth-capex pipeline reports a Rs 1,400 crore project cost for the Godawari New Energy Private Limited BESS project, rather than the Rs 1,425 crore figure on the project page. Its Rs 791 crore balance-to-be-incurred figure reconciles with the Rs 1,400 crore pipeline cost after deducting Rs 609 crore incurred through September 2026.
What land, equipment and supply arrangements has GPIL disclosed?
GPIL has acquired 112 acres in the AURIC Industrial Area in Maharashtra for the 20 GWh project. Soil testing has been completed and compound-wall construction was under way when the presentation was issued.
Lead Intelligent Wuxi is to supply BESS assembly equipment, with its factory acceptance test expected by the end of August. GPIL does not state the year of that test or provide a separate installation or trial-production timetable beyond the Q1 FY28 commissioning target.
GPIL has finalized a long-term cell-supply agreement with EVE Power Co. Ltd. It has also signed a balance-of-system supply agreement with ROCHE Energy and executed power conversion system supply agreements with FIMER India and Hopewind.
An Indian vendor has been finalized for the energy management system, according to GPIL. Testing equipment has been finalized from REPPOWER and NEWARE in China, adding disclosed testing and control-system arrangements to the cell, assembly, balance-of-system and power-conversion supply chain.
Got a follow-up? Ask IRIS
What Maharashtra support has GPIL disclosed for the project?
GPIL says the Maharashtra government has approved multiple incentives for the BESS project, including electricity-duty and stamp-duty exemptions, a power-tariff subsidy, interest and capital subsidies, State Goods and Services Tax-linked incentives, and Employees' State Insurance and Employees' Provident Fund reimbursements. The presentation does not assign a monetary value to these incentives.
The Maharashtra project is part of a broader investment programme at AURIC. GPIL's proposed 0.7 million-tonne cold rolling mill complex was moved from Chhattisgarh to Maharashtra to access state incentives and subsidies, with proximity to the proposed BESS plant also cited as a reason; the mill is targeted for commissioning in December 2027.
GPIL is also expanding captive solar capacity from 190 megawatts (MW) to 290 MW. A 100 MW solar project had incurred Rs 240 crore through September 30, 2026 and was expected to be completed in December 2026, while a 25 MW captive solar plant was commissioned and synchronized with the grid in May 2026.
What milestones does GPIL need to meet before Q1 FY28?
GPIL needs to progress from acquired land, completed soil testing, ongoing compound-wall construction and finalized supplier arrangements to a commissioned 20 GWh facility by Q1 FY28. The only separately dated equipment milestone disclosed is the factory acceptance test for Lead Intelligent Wuxi's assembly equipment by the end of August.
The project runs alongside several other deadlines in GPIL's capex pipeline. The 100 MW solar project and 45 MWh captive BESS are expected in December 2026, the 0.7 million-tonne cold rolling mill is due in December 2027, and the 3 GWh commercial and industrial BESS project is targeted for March 2028.
GPIL's pipeline table also lists a container manufacturing line for BESS and marine containers with Rs 100 crore of capex and a March 2028 target. That line is intended to produce 10,000 20-foot containers and 11,200 small cabinets, according to the disclosed plan.
Conclusion
GPIL's 20 GWh BESS project is a planned entry into battery-storage manufacturing alongside its steel, mining, pellet and captive-power activities. The disclosed evidence includes Rs 609 crore spent through September 30, 2026, 112 acres of acquired land, identified equipment and cell suppliers, and Rs 2,795 crore of sanctioned facilities, while the presentation shows Rs 1,425 crore and Rs 1,400 crore as two project-cost figures.
The next disclosed marker is the factory acceptance test for assembly equipment by the end of August, followed by the Q1 FY28 commissioning target. Investors can also watch for progress on the December 2026 captive BESS and solar projects, and for clarification of the Rs 25 crore difference between the project-page capex and the pipeline-table cost.