Hindustan Zinc approves Rs 80,000 crore growth capacity plan
Key highlights
- Hindustan Zinc approved approximately Rs 80,000 crore for HZL 2.0 on November 16, 2026.
- Hindustan Zinc targets metal-production capacity of 2.0 MTPA, up from 1.1 MTPA.
- HZL 2.0 implies a 0.9 MTPA capacity increase over the next three to five years.
- Hindustan Zinc scheduled an investor call at 14:15 IST on November 16, 2026.
powered by IRIS

Hindustan Zinc Limited approved on November 16, 2026, an approximately Rs 80,000 crore HZL 2.0 Growth Program to increase metal-production capacity from 1.1 million tonnes per annum (MTPA) to 2.0 MTPA over the next three to five years. The board approval was followed by an investor call scheduled for 14:15 Indian Standard Time (IST) that day.
Know Hindustan Zinc inside out
Results, valuation, peers and who's buying, in one view.
What did Hindustan Zinc's board approve?
Hindustan Zinc's board approved the HZL 2.0 Growth Program on November 16, 2026, to expand the company's metal-production capacity from 1.1 MTPA to 2.0 MTPA. The company disclosed the decision under Regulation 30 of the Securities and Exchange Board of India (SEBI) Listing Obligations and Disclosure Requirements Regulations, 2015, and referred to the initiative as the 2X Growth Project elsewhere in the filing.
The November 16 filing sets out an aggregate capacity target and an approximate Rs 80,000 crore capital-expenditure framework, rather than individual project details. Hindustan Zinc did not identify mines, smelters, plants or other assets within HZL 2.0, and it did not split the spending estimate by project, metal or location.
How much capacity will Hindustan Zinc add?
Hindustan Zinc plans to add 0.9 MTPA of metal-production capacity, taking its stated capacity from 1.1 MTPA to 2.0 MTPA. This is a capacity objective, not a forecast for actual metal output, sales volume or revenue, and the filing does not separate the target across zinc, lead, silver or other metals.
The comparison shows a planned increase of 0.9 MTPA from the current 1.1 MTPA base. Hindustan Zinc did not disclose annual capacity additions during the three-to-five-year period, the date on which it expects to reach 2.0 MTPA, or how much of the increase would come from new facilities versus expansions of existing operations.
Got a follow-up? Ask IRIS
What are Hindustan Zinc's spending and timing commitments?
Hindustan Zinc envisages approximately Rs 80,000 crore of capital expenditure for HZL 2.0 over the next three to five years from the November 16, 2026 board approval. The company used the term “approximately” for the expenditure estimate and did not provide financial-year allocations or a narrower completion date within the three-to-five-year range.
The Rs 80,000 crore estimate is linked in the filing to the move from 1.1 MTPA to 2.0 MTPA. Hindustan Zinc did not disclose a funding mix, expected project returns, commodity-price assumptions, permitting requirements, construction milestones or interim commissioning targets in its November 16 announcement.
Why did Hindustan Zinc hold an investor call at short notice?
Hindustan Zinc scheduled an investor call for 14:15 IST on November 16, 2026, following the board's approval and public disclosure of HZL 2.0. The company said the call would provide further insights into the plan and facilitate direct engagement with investors after the decision.
The company said the short-notice call was necessary because the 2X Growth Project had been Unpublished Price Sensitive Information before the board approval and disclosure on November 16, 2026. Hindustan Zinc cited a SEBI circular dated February 25, 2025, and Point 19.1 of the Industry Standards Note under Regulation 30; it also made playback available from November 16 through November 23 using code 09007#.
Conclusion
Hindustan Zinc has committed to a board-approved expansion from 1.1 MTPA to 2.0 MTPA, implying 0.9 MTPA of additional metal-production capacity, with approximately Rs 80,000 crore envisaged over three to five years. The filing establishes the scale and timing range of HZL 2.0 but does not provide asset-level execution details or annual spending targets.
The next disclosures to watch are any plan details emerging from the November 16 investor call or later updates, particularly project locations, phased capacity additions, commissioning dates and funding arrangements. The company made the call replay available until November 23, 2026, but its November 16 filing did not set a date for achieving the 2.0 MTPA target.