Hindustan Zinc approves 2 MTPA capacity plan worth Rs 80,000 crore
Key highlights
- Hindustan Zinc approved about Rs 80,000 crore to target 2.0 MTPA of refined-metal capacity within three to five years.
- Total ore-production capacity is planned to increase by 15.7 MTPA, from 19.3 MTPA to 35.0 MTPA.
- Total smelting capacity is listed to rise from 1,144 KTPA to 2,021 KTPA.
- The 265-KTPA Debari integrated zinc smelter is expected to be commissioned by the second quarter of FY29.
powered by IRIS

Hindustan Zinc has approved an approximately Rs 80,000 crore programme to raise refined-metal capacity from 1.1 million tonnes per annum to 2.0 million tonnes per annum within three to five years, supported by 15.7 million tonnes per annum of mine-and-milling additions and 965 thousand tonnes per annum of smelting expansion.
Know Hindustan Zinc inside out
Results, valuation, peers and who's buying, in one view.
What has Hindustan Zinc’s board approved?
Hindustan Zinc’s board has approved 2.0 projects with overall investment of about Rs 80,000 crore over three to five years. The investment includes earlier approved phase-1 work, new zinc and lead smelters, a silver refinery, and the associated mine and milling expansion required to support refined-metal capacity of 2.0 million tonnes per annum (MTPA).
The starting refined-metal capacity is 1.1 MTPA, comprising 0.9 MTPA of zinc and 0.2 MTPA of lead. The stated three-to-five-year outcome is 1.6 MTPA of zinc and 0.4 MTPA of lead, taking the refined-metal total to 2.0 MTPA. This compares with the 1.1 MTPA current base shown in the presentation.
The plan is integrated across ore production, smelting and refining rather than limited to new furnaces. Total ore-production capacity is set to increase from 19.3 MTPA to 35.0 MTPA, while total smelting capacity is listed to rise from 1,144 thousand tonnes per annum (KTPA) to 2,021 KTPA. Silver-refining capacity is planned to increase from 800 tonnes per annum (TPA) to 1,500 TPA.
How will Hindustan Zinc reach 2.0 MTPA of refined metals?
Hindustan Zinc plans to add a 265-KTPA integrated zinc smelter at Debari, expected to be commissioned by the second quarter of FY29. The presentation says this project moves the company towards 1.4 MTPA of refined-metal capacity by FY29, compared with its current 1.1 MTPA capacity.
A further 700 KTPA of capacity is expected within three to five years, comprising a 500-KTPA zinc smelter and a 200-KTPA lead smelter. Combined with the Debari project, the planned smelting additions total 965 KTPA. The post-expansion smelting table lists 1,611 KTPA of zinc capacity and 410 KTPA of lead capacity, or 2,021 KTPA in total.
The zinc capacity figure includes an operating change at Debari. Hindustan Zinc says an existing 88-KTPA cell house at the Debari zinc smelter will be discontinued, a note attached to the 1,611-KTPA post-expansion zinc figure. Separately, a new 700-TPA silver refinery would lift silver-refining capacity by 87.5%, from 800 TPA to 1,500 TPA.
Got a follow-up? Ask IRIS
Which mines will support Hindustan Zinc’s smelter additions?
Hindustan Zinc plans to lift ore-production capacity by 15.7 MTPA, from 19.3 MTPA to 35.0 MTPA. Rajpura Dariba has the largest planned absolute increase of 5.4 MTPA, from 1.1 MTPA to 6.5 MTPA, followed by Zawar’s 4.3-MTPA addition, from 5.2 MTPA to 9.5 MTPA.
Bamnia Kalan is shown with no existing capacity and a planned 3.5-MTPA addition. Sindesar Khurd is planned to rise by 1.0 MTPA to 7.5 MTPA, while Rampura Agucha and Kayad are grouped for a 1.5-MTPA increase to 8.0 MTPA. Together, the five disclosed changes equal the 15.7-MTPA total expansion.
Rampura Agucha also has a separate tailings-reprocessing plant requiring an additional Rs 3,823 crore of investment. Hindustan Zinc says the plant’s output will be input for the smelters. The presentation identifies a 10-MTPA tailings-reprocessing plant in its growth vision, while noting that ore-production capacities are conceptual estimates that may change after further project detailing.
What is Hindustan Zinc’s timetable and what remains unresolved?
Hindustan Zinc provides a specific expected commissioning point of the second quarter of FY29 for the 265-KTPA Debari zinc smelter. The larger 700-KTPA package, consisting of 500 KTPA of zinc and 200 KTPA of lead capacity, has an expected commissioning range of three to five years rather than a stated financial-year target.
Mine capacity remains subject to further design work. Hindustan Zinc says the 35.0-MTPA ore-production capacity is an estimate based on a conceptual plan and that final capacities may change with further detailing. Management was scheduled to discuss the board-approved growth plan on an investor call at 14:15 Indian Standard Time on November 16, 2026, but the presentation does not provide annual spending phasing for the about Rs 80,000 crore programme.
Conclusion
Hindustan Zinc’s programme combines a 0.9-MTPA increase in refined-metal capacity with a 15.7-MTPA increase in ore-production capacity and a 700-TPA increase in silver refining. The proposed zinc and lead smelters, mining and milling additions, silver refinery, and tailings-reprocessing feed link show that the stated 2.0-MTPA target depends on coordinated expansion across the production chain.
The next stated operating milestone is the expected second-quarter FY29 commissioning of the 265-KTPA Debari zinc smelter. Progress on the remaining 700 KTPA of smelting additions and further detailing of the 35.0-MTPA ore plan will matter because Hindustan Zinc has said final mine capacities may change from the conceptual estimates.