J. Kumar says China-linked TBM delay lasted one to two months
Key highlights
- J. Kumar said one GMLR TBM assembly was delayed by one to two months.
- J. Kumar said its second GMLR TBM was already operating after assembly in another country.
- J. Kumar has seven metro TBMs, with four executing projects in Delhi.
- Management said Chinese companies account for less than 10% of the hundreds of TBMs available in India.
powered by IRIS

J. Kumar said China-related restrictions delayed assembly of one GMLR tunnel-boring machine by one to two months, not its wider tunnelling execution, because a second GMLR machine was assembled in another country and was already operating. Management also cited a seven-machine metro fleet, with four machines then executing work in Delhi.
Know J Kumar Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
Did China’s TBM restriction disrupt J. Kumar’s execution?
No. J. Kumar said the China-related issue delayed one of two GMLR tunnel-boring machines, or TBMs, by only one to two months, while the other machine had already been assembled outside China and was working for the company. Management described the event as a limited delay in the assembly of one machine rather than an interruption across its metro-tunnelling operations.
The affected GMLR machine was being assembled in China when it became stuck, according to management. The second GMLR machine had already been sent to another country for assembly before entering service. This difference between the two machines was central to management’s assertion that TBM supply remained regular despite restrictions involving China.
J. Kumar said the issue did not reflect a broad dependence on Chinese-made TBMs. Management estimated that Chinese companies account for less than 10% of the hundreds of TBMs available in India. It said the core machinery and major spare parts used by suppliers such as Herrenknecht, Terratec and Robbins originate in European and United States supply chains.
Why does J. Kumar expect alternative TBM supply to continue?
J. Kumar expects alternative TBM supply to continue because management said the assembly base had moved to other locations and Herrenknecht has a large Chennai facility that manufactures and supplies machines regularly. Its conclusion was that the China disruption did not prevent India, or J. Kumar, from obtaining TBMs.
Management distinguished final fabrication from the machine’s major systems. It said China had mainly been an assembly hub for the shield, the TBM’s outer body, and the cutter head, while suppliers provided the core machine and major parts from Europe and the United States. China and India had been economical fabrication locations, management said, but the assembly work can be performed elsewhere.
J. Kumar also referred to an order placed by Afcons for the C2 high-speed project as an example of a machine getting stuck in a China-related supply route. That example was not presented as J. Kumar’s experience or as evidence of a sector-wide halt. J. Kumar’s disclosed outcome was narrower: one GMLR machine was delayed by one to two months and the second was already operating.
The company did not disclose a revised completion date, cost impact or revenue impact from the one-to-two-month GMLR delay. Management instead focused on the availability of other assembly sites and Chennai production. That leaves project-level consequences outside the information provided on the call, even as the company said machine supply itself was “absolutely” not an issue.
Got a follow-up? Ask IRIS
How much TBM capacity does J. Kumar have for metro work?
J. Kumar has seven TBMs for metro projects, four of which were in execution on Delhi work when management answered the question. The fleet provides equipment capacity beyond the two GMLR machines discussed, although the company did not give a project-by-project allocation for the other three machines.
Management said all of its TBMs had been active over the previous five years. Each machine has completed two to three projects, according to J. Kumar, and management said that operating history gives the company an advantage when bidding for underground metro work. That is management’s assessment rather than a disclosed tender award.
Tunnelling work at Surat and a Delhi project was approaching completion, which will release machines from those assignments, management said. J. Kumar expects a possible gap of six to 12 months before machines are redeployed. It linked that interval to the normal sequence of bidding for projects, winning work and refurbishing machines after a contract is completed.
The six-to-12-month redeployment interval was not attributed to the China-related disruption. Management said refurbishment is required after every project and that a bidding period is also necessary. As a result, the comparison is between four TBMs then operating in Delhi and a broader seven-machine fleet that can be prepared for new assignments as Surat and Delhi tunnelling work ends.
Where could J. Kumar redeploy released TBMs?
J. Kumar said it was about to bid for three underground metro projects in Delhi, which management identified as a potential destination for machines released from existing work. It also cited an underground Metro Line 5 project in the Thane-Bhiwandi area and unspecified jobs in Pune as further opportunities in the underground metro pipeline.
Management said underground metro projects were continuing to emerge and that there was substantial visibility in the segment. However, J. Kumar did not disclose the value of the three Delhi projects, the Mumbai Metro Line 5 opportunity or Pune jobs. It also provided no award date, bid outcome or timetable for assigning particular TBMs to those tenders.
The company’s approach is to refurbish existing machines rather than state a new TBM procurement programme. Machines completing Surat and Delhi work could therefore be used on future contracts after the stated six-to-12-month interval, subject to successful bids and project awards. The seven-machine fleet is relevant because J. Kumar said it has already supported two to three projects per machine.
J. Kumar’s management also said it is working on mechanisation and pre-casting methods to reduce labour requirements where possible. Although that comment concerned labour availability rather than TBM sourcing, it shows that the company is addressing execution through equipment and construction methods while it pursues new metro opportunities.
Conclusion
J. Kumar’s disclosed China-related TBM issue was contained to a one-to-two-month delay in assembling one GMLR machine. The company said a second GMLR machine was already operating, alternative assembly locations had become available, and Herrenknecht’s Chennai facility was supplying TBMs. Its four Delhi machines and seven-machine metro fleet provide the wider operating context for that assessment.
The next items to watch are J. Kumar’s planned bids for three Delhi underground metro projects, the Metro Line 5 opportunity in the Thane-Bhiwandi area and work in Pune. Management said TBMs released after Surat and Delhi tunnelling work could be refurbished and redeployed after a possible six-to-12-month gap, but that depends on contract wins and award timing.