Kalyani Cast-Tech Targets Early FY28 Kutch ICD Operations
Key highlights
- Kalyani Cast-Tech received permission to construct and operate its Kutch ICD on September 10, 2026.
- Warehouse construction began after the September 14, 2026 foundation ceremony, with early FY28 operations targeted by management.
- The 144-acre Kutch site has two full-length rail lines and annual container capacity of 10,000 TEUs.
- Kalyani Cast-Tech has a sanctioned Rs 100 crore HDFC Bank debt facility but said it had not used debt so far.
powered by IRIS

Kalyani Cast-Tech Limited expects its Kutch inland container depot to begin operating in early FY28 after receiving approval on September 10, 2026 and beginning warehouse construction four days later, linking a 144-acre site with rail-terminal, container-manufacturing and planned wagon-manufacturing operations.
Know Kalyani Cast-Tech inside out
Results, valuation, peers and who's buying, in one view.
What did Kalyani Cast-Tech receive for the Kutch site?
Kalyani Cast-Tech received permission on September 10, 2026, to construct and operate an Inland Container Depot, or ICD, at its Shivlakha site in Kutch. Management described an ICD as a dry port where containers can undergo customs examination, adding customs-clearance capability to a site that already includes container manufacturing and rail infrastructure.
The company laid the warehouse foundation on September 14, 2026, and management said construction had already started by the October 29 conference call. It expects the warehouse-led ICD facility to be operational at the start of the next financial year, placing the stated target in early FY28. This remains a management expectation rather than a disclosed commissioning date.
How will Kalyani Cast-Tech connect the ICD with rail and manufacturing?
Kalyani Cast-Tech intends the ICD to operate as part of an integrated platform across roughly 144 acres, with a possible expansion to 150 acres. The planned combination includes container manufacturing, wagon manufacturing, a rail terminal and customs examination, rather than treating the ICD as a standalone warehouse operation.
The rail component has two full-length railway lines and was inaugurated by the Minister for Railways on September 15, 2026. Management said the two lines can handle two trains simultaneously, with wharf areas on both lines allowing each line to independently handle cargo. Container-handling equipment is currently hired, while the company plans to purchase additional equipment.
Kalyani Cast-Tech said the Gati Shakti Cargo Terminal was commissioned before time. Management characterised the terminal as an enabler for the manufacturing and ICD businesses, and said the rail siding could need further expansion within six to nine months as cargo volumes develop. The site has rail and road links to Mundra and Kandla ports and is on the Kandla-Palanpur-Delhi highway corridor; management also said a Tuna port may come within about one year.
When does Kalyani Cast-Tech expect ICD and wagon operations to start?
Kalyani Cast-Tech expects ICD operations at the beginning of the next financial year, while its wagon-manufacturing schedule depends on a separate Railway approval process. The company has applied through the Research Designs and Standards Organisation, or RDSO, for an audit of its wagon facility under the G-105 standard, which management said is required before manufacturing can begin.
The company said RDSO had cleared stage one of its own wagon design by the October 29, 2026 call. Management expects final approval by March 31, 2027, but did not state that approval had been secured. The physical wagon facility is complete, whereas regulatory approval remains the condition for production.
Phase one of the wagon plan has capacity for 2,400 wagons annually. Management said its design reduces each wagon's weight by 1.25 tonnes, accommodates 42-foot containers rather than 40-foot containers, and could fit 49 wagons in a train compared with 45. Those are management-described design features and potential operating benefits, not reported wagon sales or production volumes.
Got a follow-up? Ask IRIS
What capacity, funding and customer activity support the Kutch site?
Kalyani Cast-Tech has already begun container production at Shivlakha, with output starting in June 2026 and 500 containers supplied to a customer by the call date. The Kutch facility has annual capacity of 10,000 twenty-foot equivalent units, or TEUs, while the Rewari facility has capacity of about 7,000 TEUs and produced about 5,400 TEUs in the previous year.
That comparison shows that Kalyani Cast-Tech entered the expansion with Rewari using roughly 75% to 80% of its 7,000-TEU capacity, while the newer Kutch plant was only several months into production. Management said the Kutch location can reduce customers' empty-container repositioning needs because cargo can be picked up in the area from the first day of container use.
Management said the company had funded development so far through equity raised via warrants, internal generation and operating surpluses, without using debt. HDFC Bank has sanctioned about Rs 100 crore of debt, which management said could be drawn when required. The company also reported an order book of about Rs 133 crore for FY27 and said it expected this could reach about Rs 170 crore, subject to ongoing order negotiations.
Customer additions provide demand context for the manufacturing side of the platform. Management said JSW Ports was a new customer and had received more than 1,000 containers, around 1,500 containers, during the financial year to date. Central Warehousing Corporation and the Indian Navy were also described as new customers, with recent Central Warehousing Corporation orders of nearly Rs 30 crore.
Conclusion
The September 10 ICD permission and September 14 warehouse foundation move Kalyani Cast-Tech's Kutch development from a rail-and-manufacturing site toward a combined logistics platform. Its two rail lines, 10,000-TEU container capacity and planned annual capacity of 2,400 wagons connect manufacturing with cargo handling and intended customs examination on about 144 acres.
The next milestones are the start of ICD operations expected in early FY28 and the wagon-facility approvals that management targets by March 31, 2027. Other disclosed matters to watch are whether the planned six-to-nine-month rail-siding expansion becomes necessary, whether the Rs 100 crore HDFC Bank sanction is drawn, and how the Rs 133 crore FY27 order book develops toward management's indicated Rs 170 crore level.