Narayana Health targets 7,800-plus beds by FY30 through six projects
Key highlights
- Narayana Health reported 5,879 beds on 30 September 2026 and is targeting more than 7,800 beds by FY30.
- Six disclosed projects will add 1,555 beds at a stated cost of Rs 2,990 crore.
- Bangalore accounts for 785 of the six projects’ 1,555 beds, while Kolkata accounts for 470 beds and Raipur for 300 beds.
- A further 400-bed pipeline is included in the FY30 capacity path, but NH has not disclosed its location, cost, timing or status.
powered by IRIS

Narayana Health targets more than 7,800 beds by FY30, up from 5,879 beds on 30 September 2026. Its six named projects add 1,555 beds at a stated cost of Rs 2,990 crore, while a further 400-bed pipeline brings the indicated capacity path to 7,834 beds.
Know Narayana Hrudayalaya inside out
Results, valuation, peers and who's buying, in one view.
How will NH reach more than 7,800 beds by FY30?
NH plans to reach its FY30 capacity target through 1,555 beds in six identified developments and 400 beds classified as pipeline. Adding the six projects to the 5,879 beds reported on 30 September 2026 gives 7,434 beds, while the pipeline takes the total to 7,834 beds.
The named additions are concentrated in flagship regions. Bangalore accounts for 785 of the 1,555 beds through HSR, central and south Bangalore; Kolkata accounts for 470 beds through Rajarhat and Park Street; and Raipur accounts for 300 beds.
The 400-bed pipeline is necessary to reach the stated 7,800-plus target because the six named projects alone total 7,434 beds including current capacity. NH did not provide the pipeline's location, type, cost, completion date or project status on the expansion page.
Which NH projects add beds and when will they open?
NH has scheduled 635 beds for FY28 through the HSR Bangalore, Raipur and Park Street Kolkata projects. The 215-bed HSR greenfield project and 300-bed Raipur expansion have main contractors onboarded, while the 120-bed Park Street lease project has an operations and management agreement executed.
FY29 is scheduled to add 570 beds through Rajarhat Kolkata and central Bangalore. The 350-bed Rajarhat greenfield project has sanctions in place and is progressing as per schedule, while the 220-bed central Bangalore lease project has executed its lease and construction agreement and is in design and approvals.
The final named development is the 350-bed south Bangalore greenfield project, scheduled for FY30 and in design and approvals. Separately, NH said the South-West Bangalore Banashankari Hospital commenced operations in the last week of September 2026, but the expansion page did not state its bed count or project cost.
Got a follow-up? Ask IRIS
What will NH spend on the expansion programme?
NH has assigned Rs 2,990 crore of project costs to the six named developments. Rajarhat Kolkata is the largest individual commitment at Rs 900 crore, followed by south Bangalore at Rs 800 crore, Raipur at Rs 540 crore and HSR Bangalore at Rs 490 crore.
The four greenfield or expansion projects account for Rs 2,730 crore of the disclosed total. The two lease projects account for the remaining Rs 260 crore, comprising Rs 160 crore for central Bangalore and Rs 100 crore for Park Street Kolkata.
NH's FY27 capital-expenditure table separately lists Rs 460 crore for greenfield or inorganic expenditure in its first FY27 column and Rs 95.5 crore in its second FY27 column. Replacement and maintenance expenditure is listed at Rs 270 crore and Rs 68.1 crore, respectively; the presentation does not state whether these figures use the same recognition basis as the project-cost totals.
How does the expansion fit NH's current operating position?
NH India reported operating revenue of Rs 1,440.2 crore in Q2 FY27, up 8.7% from Rs 1,324.7 crore in Q1 FY27 and 16.6% from Rs 1,234.7 crore in Q2 FY26. Earnings before interest, tax, depreciation and amortisation were Rs 354.8 crore, up 22.3% quarter on quarter and 30.8% year on year.
At group level, NH reported operating income of Rs 2,844 crore in Q2 FY27, compared with Rs 2,683.6 crore in Q1 FY27 and Rs 1,643.8 crore in Q2 FY26. Group earnings before interest, tax, depreciation and amortisation rose 19.8% quarter on quarter to Rs 605.4 crore, while profit after tax increased 45.3% to Rs 301.2 crore.
NH reported consolidated net debt of Rs 1,883 crore as of 30 September 2026. India had net debt of Rs 850.1 crore, the Cayman Islands entity had net cash of Rs 678.1 crore, and the United Kingdom had net debt of Rs 1,711.1 crore; the presentation did not specify funding for individual expansion projects.
What does NH's project status say about execution?
NH describes the HSR Bangalore and Raipur projects as progressing as per schedule after main-contractor appointments. These two FY28 projects represent 515 beds and have combined stated costs of Rs 1,030 crore.
Rajarhat Kolkata, the Rs 900 crore and 350-bed project, also has sanctions in place and is described as progressing as per schedule. The remaining 690 named beds are at stages involving executed agreements, an operations and management agreement, or design and approvals, showing that the six projects are at different disclosed stages of development.
Conclusion
NH has set out a numerical route from 5,879 beds in September 2026 to more than 7,800 by FY30. The route comprises 1,555 beds from six identified projects and 400 beds in pipeline, with Bangalore representing the largest named regional addition and Rajarhat Kolkata the highest-cost single development.
The next disclosed milestones are the FY28 completions for HSR Bangalore, Raipur and Park Street Kolkata, followed by FY29 completion targets for Rajarhat and central Bangalore and the FY30 target for south Bangalore. NH's 400-bed pipeline remains a key item to watch because the presentation provides no location, cost, timing or status for it.