PNC BESS order lapses after NHPC agreements stay unsigned
Key highlights
- PNC’s NHPC BESS LOA lapsed after agreements remained unsigned through the September 30 extension deadline.
- PNC said its bid security was refunded and BESS was never included in its Rs. 18,000 crore unexecuted order book.
- PNC had Rs. 913 crore of remaining equity requirement across 14 HAM projects as of September 2026.
- PNC has submitted 17 bids worth Rs. 16,600 crore, with price bids yet to be opened.
powered by IRIS

PNC Infratech’s battery energy storage system award from NHPC lapsed after the required agreements remained unsigned through the extended September 30 deadline, and PNC received a refund of its bid security. Management said the project had never been included in its Rs. 18,000 crore unexecuted order book.
Know PNC Infratech inside out
Results, valuation, peers and who's buying, in one view.
Why did PNC’s NHPC BESS order lapse?
PNC’s letter of award, or LOA, lapsed because NHPC did not sign power-sale agreements, or PSAs, with prospective distribution companies before the contractual deadline. Management said those PSAs were a precondition to NHPC signing a power-purchase agreement, or PPA, with PNC, so the PPA could not be completed within one year of the award.
PNC sought a one-month extension from August 31 to September 30, but neither the PSAs nor the PPA was signed during that period. Management said the request for proposal, or RFP, stipulated that the LOA stood cancelled if the agreements were not completed, and NHPC refunded the bid security submitted by PNC.
The disclosed sequence points to an unmet contracting condition rather than the termination of an operating project. The call did not disclose the award date, the bid-security amount, any construction activity, or a revised NHPC timetable for the battery energy storage system, or BESS, project.
What does the BESS lapse change in PNC’s order book?
PNC said the BESS lapse does not reduce its stated Rs. 18,000 crore unexecuted order book because the company had not included the project in that figure from the beginning. The backlog includes two newly secured National Highways Authority of India, or NHAI, hybrid annuity model, or HAM, projects, with highways accounting for 63% of the total.
Management said PNC could still enter the next financial year with Rs. 15,000 crore of unexecuted work even without new orders. This is lower than the current Rs. 18,000 crore order book because projects are expected to be executed during the year, but it excludes the cancelled BESS opportunity in both periods.
The project’s lapse also leaves PNC’s disclosed equity plans centred on road assets. Its 14 HAM projects have a total equity requirement of Rs. 2,125 crore, of which Rs. 1,212 crore had been infused through September 2026, leaving Rs. 913 crore to be invested over the next two to three years.
Was PNC’s BESS exit linked to higher battery costs?
Management said it viewed the exit favourably because prices of input materials, including batteries, and logistics costs had increased amid the West Asia conflict. This was management’s assessment of the outcome after the LOA lapsed, rather than a disclosed calculation of the costs, capital expenditure or margin that the BESS project would have required.
The stated contractual cause nevertheless remained the absence of signed PSAs and a PPA by September 30. Management did not provide a battery-price index, a revised project estimate or an estimate of potential losses avoided, so the call does not quantify the financial effect of higher batteries or logistics costs.
PNC’s non-road portfolio continues to include water, canal, railway and airport contracts, which account for about 21% of the Rs. 18,000 crore order book, and coal mining, which accounts for 16%. During the quarter ended September 30, management said the government released Rs. 267 crore of pending water payments and the Government of Andhra Pradesh paid Rs. 183 crore for irrigation work.
Got a follow-up? Ask IRIS
How is PNC planning growth after the BESS project ended?
PNC said highways will remain its core growth sector across HAM, engineering, procurement and construction, or EPC, and build-operate-transfer toll, or BOT Toll, models. Its 17 fund-based projects comprise one BOT-Toll project, two BOT annuity projects and 14 HAM projects; six HAM projects had achieved provisional commercial operation date, or PCOD, and commercial operation date, or COD, while five were under construction.
Management maintained its guidance of Rs. 6,000 crore of revenue for the current financial year, Rs. 7,500 crore for the following year and an earnings before interest, tax, depreciation and amortisation, or EBITDA, margin of 12%. Standalone revenue reached Rs. 2,664 crore in the first half of FY27, up 26% from Rs. 2,119 crore in the first half of FY26, while standalone EBITDA increased 85% to Rs. 513 crore from Rs. 277 crore.
PNC said it had submitted 17 bids with an estimated value of Rs. 16,600 crore, with price bids yet to open. These comprise 13 EPC bids, three HAM bids and one tariff-based competitive bidding, or TBCB, power-transmission bid, while management identified about 80 projects worth Rs. 1.80 lakh crore for bidding over the next two to three months through the end of January.
The company is also pursuing non-fund-based overseas EPC road projects rather than overseas assets requiring project investment. PNC incorporated a Kazakhstan subsidiary, submitted a road-project bid in Georgia in September 2026, and said it was pursuing opportunities in Uzbekistan and the United Arab Emirates; management said such projects would need working capital rather than significant investment.
Conclusion
The NHPC BESS opportunity ended because the PSAs and PPA were not executed by the extended September 30 deadline, resulting in cancellation of the LOA under the RFP terms and a bid-security refund. PNC said the reported Rs. 18,000 crore order book is unchanged because BESS had never been counted, leaving highways and selected adjacent infrastructure segments as its disclosed operating base.
Next, investors can watch whether PNC meets management’s Rs. 6,000 crore revenue guidance and 12% EBITDA-margin target for the current financial year. Other disclosed milestones are the opening of price bids for Rs. 16,600 crore of submitted bids, planned FY28 HAM equity investment of Rs. 460 crore, and bidding on identified opportunities through the end of January.