POWER MECH MDO backlog accounts for 69% of FY27 order book
Key highlights
- POWER MECH reported Rs 39,243 crore of MDO backlog within total FY27 YTD order backlog of Rs 56,729 crore.
- MDO represented about 69.18% of POWER MECH's FY27 YTD order backlog based on disclosed segment values.
- MDO generated Rs 85 crore, or 5.28%, of POWER MECH's Rs 1,609 crore Q2 FY27 revenue.
- POWER MECH reported FY27 YTD order inflow of Rs 4,801 crore, equal to 40% of its target.
powered by IRIS

POWER MECH's Rs 39,243 crore mining development and operations (MDO) backlog accounted for about 69% of its Rs 56,729 crore FY27 year-to-date (YTD) order backlog. MDO was therefore the largest source of contracted future work, although it generated Rs 85 crore, or 5.28%, of Rs 1,609 crore revenue in Q2 FY27.
Know Power Mech Projects inside out
Results, valuation, peers and who's buying, in one view.
Why does MDO dominate POWER MECH's order backlog?
MDO dominates POWER MECH's FY27 YTD order backlog because its Rs 39,243 crore balance exceeds the combined Rs 17,486 crore held in Industrial Construction, Infrastructure Construction and Industrial Services. Calculated from the segment figures disclosed in the presentation, MDO made up 69.18% of the Rs 56,729 crore total backlog.
Infrastructure Construction was the next-largest backlog segment at Rs 7,903 crore, followed by Industrial Services at Rs 5,689 crore and Industrial Construction at Rs 3,894 crore. MDO's backlog was Rs 31,340 crore higher than Infrastructure Construction's, showing that mining contracts now account for most of POWER MECH's contracted work pipeline.
The backlog composition differs sharply from the Q2 FY27 revenue mix. MDO's Rs 39,243 crore backlog was substantially larger than every other segment's balance, but MDO generated only Rs 85 crore in quarterly revenue, compared with Rs 582 crore from Infrastructure Construction, Rs 570 crore from Industrial Services and Rs 372 crore from Industrial Construction.
How much MDO revenue did POWER MECH report in Q2 FY27?
POWER MECH reported MDO revenue of Rs 85 crore in Q2 FY27, equal to 5.28% of its Rs 1,609 crore quarterly revenue. That was Rs 1 crore above Rs 84 crore in Q1 FY27 and Rs 54 crore above Rs 31 crore in Q2 FY26.
Management attributed the rise in MDO's revenue share to production ramp-up at the KBP mine. The presentation does not disclose KBP's production volume, a revenue target for MDO, or the timetable for converting the Rs 39,243 crore MDO backlog into revenue.
Infrastructure Construction was the largest reported Q2 FY27 revenue contributor at Rs 582 crore and 36.17% of revenue. Industrial Services followed with Rs 570 crore and 35.43%, while Industrial Construction contributed Rs 372 crore and 23.12%; together, these three segments supplied Rs 1,524 crore of quarterly revenue.
The sequential trend varied across the operating segments. Infrastructure Construction revenue declined by Rs 214 crore from Rs 796 crore in Q1 FY27, while Industrial Services rose by Rs 139 crore from Rs 431 crore and Industrial Construction increased by Rs 59 crore from Rs 313 crore; MDO increased by Rs 1 crore.
How has POWER MECH's overall order position changed?
POWER MECH's total FY27 YTD order backlog was Rs 56,729 crore, up Rs 1,578 crore from Rs 55,151 crore in FY26. The presentation describes the increase as approximately 3% year-on-year.
The FY27 YTD balance was also above the Rs 53,994 crore reported in FY25, but below the Rs 57,053 crore reported in FY24. This means the reported backlog had recovered from FY25 and moved above FY26, without surpassing the FY24 level.
POWER MECH reported FY27 YTD order inflow of Rs 4,801 crore, which management said represented 40% of its target. Industrial Services accounted for Rs 3,718 crore of the disclosed inflow split and Infrastructure Construction accounted for Rs 1,083 crore, while the Industrial Construction and MDO cells were left blank in the presentation.
Management said the company won Rs 1,890 crore of orders during Q2 FY27 and a further Rs 1,046 crore in Q3 to date. Listed awards included five-year comprehensive operations and maintenance (O&M) contracts for Vedanta's 2 x 600 megawatt Athena plant and Adani's 2 x 600 megawatt Moxie Power Thermal Plant at Tuticorin, as well as a three-year Yadadri Thermal Power Station O&M contract.
Got a follow-up? Ask IRIS
What does MDO scale-up mean for POWER MECH's margins?
Management expects an uptrend in earnings before interest, tax, depreciation and amortisation (EBITDA) margin in coming quarters as MDO revenue scales, but it did not provide a target margin or a target date. POWER MECH reported Q2 FY27 EBITDA of Rs 187 crore and an EBITDA margin of 11.55%.
Q2 FY27 EBITDA was Rs 11 crore higher than Rs 176 crore in Q1 FY27, while the margin rose from 10.78%. The presentation attributed the sequential EBITDA increase to better operating costs, and management also cited sustained execution in core segments and the ramp-up of newly secured orders.
Year on year, EBITDA increased by Rs 29 crore from Rs 158 crore in Q2 FY26, even as the margin declined from 12.65% to 11.55%. Revenue increased 30% from Rs 1,238 crore in Q2 FY26 to Rs 1,609 crore in Q2 FY27, with the presentation linking the EBITDA increase to higher revenue.
Profit after tax (PAT) was Rs 88 crore in Q2 FY27, compared with Rs 89 crore in Q1 FY27 and Rs 78 crore in Q2 FY26. The PAT margin was 5.46%, down from 5.50% sequentially and 6.31% year on year; management attributed the Rs 2 crore sequential PAT decline to higher finance and depreciation costs.
What MDO capabilities and contracts has POWER MECH disclosed?
POWER MECH describes MDO as mine-infrastructure development, mineral-processing operations and full contract mining supported by its execution and O&M capabilities. The company reported peak rated mining capacity of 9 million metric tonnes a year, long-term contract value above Rs 39,500 crore and contract tenures above 25 years.
The presentation identifies MDO work at Tasra mines in Jharkhand among projects under execution. It does not state whether the reported long-term contract value above Rs 39,500 crore is identical to the Rs 39,243 crore FY27 YTD MDO backlog, so the two disclosed measures should not be treated as interchangeable.
POWER MECH also reported more than 42 gigawatts of capacity under O&M care globally and more than 24,000 dedicated O&M personnel. Its timeline identifies mining entry, backward and forward integration, and order-book expansion as elements of its 2020-2026 strategic pivot.
Conclusion
POWER MECH's FY27 YTD figures show that MDO has become the central component of future contracted work, accounting for about 69% of its Rs 56,729 crore order backlog. Yet the Q2 FY27 revenue base remained led by Infrastructure Construction and Industrial Services, which together generated Rs 1,152 crore against MDO's Rs 85 crore.
The next measure to watch is whether the KBP mine production ramp-up increases MDO's share of revenue and contributes to the EBITDA-margin uptrend management expects in coming quarters. Investors can also track FY27 order inflow against management's target, as Rs 4,801 crore represented 40% of that target and the presentation did not disclose the target's absolute value.