Premier Energies targets 10 GW ingot-wafer capacity by 2028
Key highlights
- Premier Energies targets 5 GW of ingot-wafer commissioning in December 2027 and another 5 GW in December 2028.
- Premier Energies' 7 GW N-type TOPCon G12R cell plant has an average target efficiency of 25.8%.
- Premier Energies reported 99% cell utilisation and 916 MW of cell production in Q2 FY 2027.
- Premier Energies' order book was 10,729 MW, valued at Rs 16,600 crore, as of 30 September 2026.
powered by IRIS

Premier Energies targets 10 GW of ingot-wafer capacity through 5 GW commissioning milestones in December 2027 and December 2028, while its 7 GW N-type TOPCon G12R cell plant is due to begin commercial production shortly. The plan is disclosed alongside 99% cell utilisation in Q2 FY 2027 and a Rs 16,600 crore order book at 30 September 2026.
Know Premier Energies inside out
Results, valuation, peers and who's buying, in one view.
What will Premier Energies' 7 GW cell plant manufacture?
Premier Energies' 7 GW cell plant will manufacture N-type TOPCon G12R solar cells, with an average target efficiency of 25.8%. The presentation says commercial production is to commence shortly, but does not disclose a specific start date or a phased commissioning timetable for this facility.
The stated production capacity is 88,000 solar cells per hour. Premier Energies says the plant uses artificial intelligence-enabled predictive analysis, precision process control and automated material handling to enhance manufacturing efficiency. These operating features sit alongside the 25.8% average cell-efficiency target disclosed for the G12R product.
The facility also includes a Zero Liquid Discharge system intended to maximise water recycling and reuse. Premier Energies has provided the 7 GW capacity and 88,000-cells-per-hour output rate, but it has not stated the capital cost, location, ramp-up volume or expected revenue contribution of the plant in the supplied presentation.
How have Premier Energies' production and utilisation changed?
Premier Energies increased quarterly cell production by 409 MW from Q2 FY 2026 to Q2 FY 2027, while cell utilisation rose from 79% to 99%. Module production increased by 238 MW over the same five-quarter comparison, but module utilisation declined by 24 percentage points to 55%.
Cell output rose in every reported quarter, from 507 MW in Q2 FY 2026 to 916 MW in Q2 FY 2027. Module output moved differently: it fell from 961 MW in Q2 FY 2026 to 918 MW in Q4 FY 2026 before reaching 1,199 MW in Q2 FY 2027, its highest level in the five reported quarters.
Premier Energies defines effective capacity as actual installed capacity adjusted for working days and product specification. Its Q1 FY 2027 effective-capacity utilisation excludes the newly commissioned Seetharampur plant, which is relevant when comparing the 92% cell and 63% module figures for that quarter with the 99% and 55% figures in Q2 FY 2027.
Got a follow-up? Ask IRIS
When will Premier Energies commission its ingot-wafer plant?
Premier Energies targets commissioning 5 GW of its 10 GW ingot-wafer plant in December 2027 and the remaining 5 GW in December 2028. Land acquisition is complete, while site development and design work are under way and machinery orders for the first phase have been placed.
The two-stage schedule provides the only disclosed timing for the 10 GW project. Premier Energies does not state a target efficiency, product format, investment amount or commercial-output date beyond the December 2027 and December 2028 commissioning targets, so the presentation does not quantify the timing of sales from either 5 GW phase.
Premier Energies also disclosed progress on two other projects with 2027 targets. For the 6 GWh battery energy storage system, or BESS, Phase I, site development and civil construction are in progress, RCT has been signed as technology and equity partner, and the target commissioning date is July 2027. For aluminium frames, site development is under way, machinery orders have been placed and commissioning is targeted for September 2027.
These disclosed projects span cells, ingot-wafers, storage and frames, but the presentation gives distinct project milestones rather than a combined commissioning date. The nearest stated target is the BESS Phase I in July 2027, followed by aluminium frames in September 2027 and the first 5 GW ingot-wafer phase in December 2027.
What does Premier Energies' order book show about demand?
Premier Energies reported an order book of 10,729 MW worth Rs 16,600 crore as of 30 September 2026, with cells and modules each representing 48% of order-book value. Domestic orders accounted for 99% of value and export orders for 1%.
The order-book bridge below uses the presentation's reported values. It shows Rs 4,220 crore of new orders during the quarter, compared with Rs 2,630 crore of sales, producing a Rs 1,590 crore increase from the June 2026 opening balance to the September 2026 closing balance.
The bridge closes at Rs 16,590 crore because the source reports its chart values at one decimal place in INR billion, while the headline order-book figure is Rs 16,600 crore and the source notes that numbers are rounded to the nearest whole number. Cells and modules together account for 96% of value, while transformers contribute 2% and engineering, procurement and construction, or EPC, contributes 1%; percentages may not total 100% because of rounding.
The order-book comparison shows new orders exceeded quarterly sales by Rs 1,590 crore in the June-to-September 2026 period. The presentation provides order-book composition and geography, but it does not disclose customer names, delivery dates, cancellation terms or how the 10,729 MW is distributed between cells, modules, transformers and EPC.
Conclusion
Premier Energies has outlined manufacturing additions across a 7 GW cell plant and a 10 GW ingot-wafer project while reporting 99% cell utilisation in Q2 FY 2027. Its Rs 16,600 crore order book at 30 September 2026 was concentrated in cells and modules, which together represented 96% of value, and was 99% domestic by value.
The next disclosed milestones are commercial production at the 7 GW cell plant, BESS Phase I commissioning targeted for July 2027, aluminium-frame commissioning targeted for September 2027, and the first 5 GW ingot-wafer phase targeted for December 2027. The second 5 GW ingot-wafer phase is targeted for December 2028, and production and utilisation figures will show how operations change as the new capacity enters operation.