Puravankara Limited maintains FY27 sales goal despite delays
Key highlights
- Puravankara retained its Rs 11,200 crore FY27 sales guidance after reaching Rs 4,201 crore, or 37.5%, in H1 FY27.
- Puravankara's Q2 FY27 presales rose 109% year on year to Rs 2,762 crore.
- Puravankara said Cuffe Parade could move from Q4 to April or May of the next financial year.
- Puravankara guided for about Rs 6,000 crore of FY27 collections and said it should exceed Rs 1,000 crore of operating surplus.
powered by IRIS

Puravankara maintained its Rs 11,200 crore financial year 2027 sales guidance on November 3, 2026, after first-half combined sales and asset monetisation reached Rs 4,201 crore, or 37.5% of the target, although management said approval-system delays and a possible Cuffe Parade shift could postpone some launches.
Know Puravankara inside out
Results, valuation, peers and who's buying, in one view.
Can Puravankara meet its FY27 sales guidance?
Yes, management said Puravankara remains confident of achieving its Rs 11,200 crore financial year 2027, or FY27, sales guidance despite potential changes to the launch calendar. The company reported Rs 4,201 crore of first-half sales and asset monetisation, equal to 37.5% of the annual target, with the guidance explicitly including Rs 650 crore of commercial sales.
The first-half total combines residential and commercial sales of Rs 3,575 crore with the September exit from Purva Zentech, which had an enterprise value of about Rs 626 crore. Management described the target as remaining intact even if one western project moves to the fourth quarter and two or three southern projects move into the next financial year.
Puravankara's underlying second-quarter presales were Rs 2,762 crore, up 109% year on year, on sales volume of 2.38 million square feet. That quarterly performance was supported by a 32% increase in average price realisation to Rs 11,607 per square foot, while customer collections rose 24% to Rs 1,301 crore.
Which Puravankara launches are awaiting approvals?
Puravankara said several South India launches are at or near final approvals, with Winworth-3 in Cochin expected to receive Real Estate Regulatory Authority, or RERA, approval within two or three days of the November 3 call. Management said this timing should allow a launch during the current quarter.
Grand Hills has received development-plan approval and is expected to launch in the fourth quarter, according to management. Hennur Road was in its last approval stage, followed by RERA, which management did not expect to extend beyond November; Kanakapura Road was expected to receive approval on the call date and RERA within seven to 10 days.
The approval delays in Bengaluru arose from an upgrade to the approval system's computer platform, management said. Puravankara had previously guided for about 12 projects in the South, and management acknowledged that some could move into the next year, while saying most should still arrive within FY27.
Will Puravankara's Cuffe Parade launch move to next year?
Cuffe Parade could move to April or May of the next financial year, but Puravankara was still targeting a fourth-quarter launch when it spoke on November 3. Management said the approval process was progressing and described the project as the main exception among launches planned across Mumbai and Pune.
For Pali Hill, Puravankara said all requisite approvals had been received and RERA was expected by November 20 or slightly earlier, enabling a launch in the current quarter. Deonar Baug approvals were in process and management continued to target a fourth-quarter launch, making its timing less uncertain than Cuffe Parade's.
The possible slippage matters because the analyst identified Deccan, Deonar Baug and Cuffe Parade as large Mumbai projects weighted toward the second half. Management nevertheless said the western pipeline appeared on track, with the stated caveat that Cuffe Parade may shift to the first quarter of the next financial year.
Got a follow-up? Ask IRIS
What supports Puravankara's sales plan despite delayed launches?
Puravankara's management based its confidence on the first-half Rs 4,201 crore combined achievement, the planned commercial contribution and a pipeline it described as long and strong. At September-end, the company had 33.61 million square feet in its ongoing portfolio and a planned 14.5 million-square-foot launch programme, subject to approvals and launch readiness.
That planned launch programme had estimated gross development value, or GDV, of about Rs 22,600 crore. During the first half, Puravankara also added development opportunities with estimated GDV of Rs 14,100 crore across Bengaluru, Mumbai and Greater Noida, expanding its redevelopment portfolio and geographic coverage.
Management also cited early sales evidence from recently introduced projects. Purva Heritage sold about 30% during launch, while Miami had received RERA in August and recorded about three transactions during August and September, when demolition was under way, at transaction prices of about Rs 1.55 lakh per square foot.
How do collections and construction affect Puravankara's target?
Puravankara expects collections from earlier large sales to follow construction milestones, rather than immediately match booking growth. First-half collections were Rs 2,500 crore, up 31% year on year, while the company said Northern Light and Estrella, which generated substantial sales in the previous fourth quarter and the current first quarter, had started construction after contracts were awarded.
Management said these projects would reach billable and collectable milestones during the current and coming quarter. It retained annual collections guidance of about Rs 6,000 crore and said operating surplus should exceed Rs 1,000 crore, although the second-quarter operating surplus included certain collections from the Purva Zentech exit.
Execution also increased reported revenue conversion: Puravankara handed over 977 homes covering about 0.97 million square feet in the second quarter, taking first-half handovers to 1,722 homes. Second-quarter revenue from operations rose to Rs 1,033 crore from Rs 644 crore a year earlier, while net debt fell Rs 470 crore to Rs 2,366 crore.
Conclusion
Puravankara's retained Rs 11,200 crore FY27 target rests on Rs 4,201 crore of first-half sales and monetisation, a Rs 650 crore commercial-sales component, and planned launches across the South and West. The central execution issue is not a change in guidance, but whether approval timing converts the 14.5 million-square-foot planned programme into saleable inventory within the financial year.
The next markers are RERA timing for Winworth-3, Hennur Road, Kanakapura Road and Pali Hill, plus the fourth-quarter decisions on Grand Hills and Deonar Baug. Investors should also watch whether Cuffe Parade stays in the fourth-quarter schedule or moves to April or May, and whether collections progress toward management's Rs 6,000 crore annual guidance as project milestones are reached.