Stallion expects Rs 200 crore funding after Bhilwara overrun
Key highlights
- Stallion said Bhilwara has a Rs 40 crore cost overrun, including more than 90 iso-tank containers and additional equipment.
- Management estimated Rs 150 crore of working-capital need for the R32 start-up.
- Stallion expects about Rs 200 crore of funding as working-capital and next-plant capex requirements overlap.
- Stallion said Rs 120 crore of bank overdraft capacity was unused at the time of the call.
powered by IRIS

Stallion India Fluorochemicals expects about Rs 200 crore of funding after its Bhilwara project incurred a Rs 40 crore cost overrun, with management citing R32 working capital and the next plant’s capital expenditure as overlapping requirements. The overrun is being funded internally and includes more than 90 iso-tank containers and additional equipment.
Know Stallion India Fluorochemicals inside out
Results, valuation, peers and who's buying, in one view.
Why did Bhilwara’s cost rise by Rs 40 crore?
Stallion said the Bhilwara project has a cost overrun of about Rs 40 crore, which it is currently funding from internal resources. Management attributed the additional spending to the purchase of more than 90 iso-tank containers and other equipment needed for the facility’s logistics and operations.
The containers are intended for both outgoing product shipments and incoming raw materials, according to management. Stallion said it chose ownership over leasing or paying higher usage charges because owned containers would give it greater operating flexibility. The call did not split the Rs 40 crore overrun between containers, equipment and other project costs.
The extra spending comes as Bhilwara moves towards commissioning. Management said trials were projected to conclude by March, production was expected to begin in phases during April, and operations could stabilise at 100% by May. Chemical-process reactors are to be started sequentially, rather than simultaneously, which means output will build during the commissioning period.
How much funding does Stallion expect to need?
Stallion expects about Rs 200 crore of funding to bridge an estimated Rs 150 crore R32 working-capital requirement and the planned capital expenditure for its next plant. Management said the requirements would overlap as Bhilwara starts production and the next project is considered around July or August.
The immediate Rs 150 crore requirement reflects the quota-year inventory cycle, management said. Materials arriving in November and December were expected to remain tied up through February, while the R32 facility would also need to be started. Management said Stallion could become cash-surplus again after this material is liquidated.
Stallion also said it had an unused Rs 120 crore overdraft facility with its bank. Management did not regard that availability as removing the broader funding need because the same capital may be required first for working capital and subsequently for the next plant’s capital expenditure.
Management had not selected a financing route at the time of the call. It said debt, debentures, a qualified institutional placement, or QIP, and a preferential issue were possible, while indicating that a rights issue was not its preferred route. No funding timetable, issue size, valuation or final instrument was disclosed.
Got a follow-up? Ask IRIS
Where have Stallion’s previous fundraising proceeds been used?
Stallion said proceeds from its initial public offering, or IPO, and the Bhilwara rights issue were largely used or committed to their specified projects. Management said about Rs 160 crore was raised through the IPO for two projects, while Rs 40 crore represented an offer for sale, or OFS, rather than project funding.
Management said most of the IPO proceeds had been spent. Mambattu remained short by about Rs 10 crore to Rs 15 crore after Stallion expanded that project beyond the IPO mandate, and management said this gap would be met through internal accruals. About Rs 50 crore from the Bhilwara rights issue remained at the time of the call and was expected to be spent during that month.
Stallion also addressed an analyst’s question on other current assets, which had increased to about Rs 160 crore from Rs 22 crore. Management said Rs 129 crore of this balance was capital advances for Bhilwara’s engineering, procurement and construction, or EPC, contract, while other advances had been made to suppliers. This means that a significant part of the balance-sheet increase was committed to project execution rather than available as unrestricted cash.
What could change Stallion’s funding requirement?
Stallion’s requirement could change with the pace of Bhilwara commissioning, the release of inventory into sales, and the timing of the next plant. Management expects phased R32 production in April and stabilisation by May, then envisages starting work on another plant around July or August once Bhilwara has settled into operations.
Management said the next plant’s capital expenditure would be about Rs 200 crore, although it did not provide a full project specification in the funding discussion. It separately said Bhilwara currently has no hydrofluoroolefin, or HFO, facility and described HFO as the second plant under planning. Management estimated Indian HFO demand at 500 to 600 tonnes currently and said it could rise above 2,500 tonnes as the transition accelerates from 2028 to 2032.
Cash conversion is another variable. Management said higher inventory had helped Stallion record Rs 20 crore of profit after tax, or PAT, in a previous quarter by ensuring product availability when demand arose. It also said paying all creditors at quarter-end had previously made operating cash flow appear negative, while returning to normal creditor balances made cash flow positive. These were management’s explanations of past cash-flow movements, not a forecast of future cash generation.
Conclusion
Stallion’s estimated Rs 200 crore funding requirement follows the Rs 40 crore Bhilwara overrun and reflects the overlap between R32 working capital, a Rs 120 crore unused overdraft facility, and preparations for the next plant. The company said its earlier IPO and rights-issue funding was substantially spent or committed, leaving internal accruals and a new financing choice as central considerations.
The next disclosed milestones are the projected completion of Bhilwara trials by March, phased production in April and stabilisation by May. Investors can also watch whether Stallion begins the next plant around July or August and whether management chooses debt, debentures, a QIP or a preferential issue to meet the anticipated funding requirement.