Stallion pushes Bhilwara R32 and Mambattu completion to Q1
Key highlights
- Stallion expects Bhilwara R32 trials by March and production from April.
- The 10,000-metric-tonne Bhilwara plant is not expected to add FY27 revenue.
- Mambattu is expected to be completed in the first quarter after a redesign nearly doubled its cost scope.
- Stallion reported H1 FY27 revenue from operations of Rs 257.48 crore, up 19.18% year on year.
powered by IRIS

Stallion India Fluorochemicals Limited expects its 10,000-metric-tonne Bhilwara R32 plant to begin production in April and its Mambattu facility to be completed in the first quarter, so neither project is expected to add revenue in financial year 2027 (FY27). Management cited funding received in April, monsoon disruption and design changes.
Know Stallion India Fluorochemicals inside out
Results, valuation, peers and who's buying, in one view.
Why will Stallion's R32 plant miss FY27 revenue?
Stallion's Bhilwara R32 project will miss FY27 revenue because management now expects trials to finish by March and production to begin in April. On the November 19, 2026 earnings call, management gave this timeline for the 10,000-metric-tonne Rajasthan facility and said it did not expect R32 revenue in the current financial year.
Management described the shift as a late start rather than a delay from the plant's planned 12-month construction period. It said funding was originally expected by December but was received in April after volatility delayed its funding plans. Work began in April, moving the project timeline by three to four months, according to management.
An analyst noted that expectations discussed previously had moved across July, October and January before the latest schedule of March trials and April production. Management said it had expected a December start-up and production by February, but it now considers the April production target the realistic timetable.
What moved Bhilwara R32 production into April?
Late funding, monsoon-related foundation rework and certification-led design changes moved Stallion's expected Bhilwara production into April. Management said rain in the area's clayey and loamy soil disrupted excavated foundations, requiring the work to be redone after the April construction start.
Stallion also said parts of the original plant design required changes to comply with Indian regulations for boilers and pressure vessels. The technology-transfer and design teams had worked to international standards, but certain foreign equipment and components lacked the certifications needed in India, including Indian Boiler Regulations and Petroleum and Explosives Safety Organisation approvals.
Management said it had anticipated and mitigated several other risks, including transport issues and disruption connected with the Gulf crisis. It nevertheless said design changes had delayed execution despite an earlier internal plan to finish the project by December after the funding arrived.
How advanced is Stallion's Bhilwara project?
Stallion said construction at Bhilwara was largely complete and plant-and-machinery installation had started by November 19, 2026. Management said all plant equipment had reached the site, while only mopping-up construction activities remained before the project moved through trials and into planned April production.
Management said it did not foresee additional difficulties or delays, while presenting April production as a current plan rather than a completed commissioning milestone. It said regulatory permissions had not caused problems and that Rajasthan's administration and electricity departments had provided support where needed.
Stallion attributed its targeted 12-month greenfield construction timetable to intensive site supervision and round-the-clock work. Its chairman said he was at the Bhilwara site five days a week, with senior management monitoring schedules, while two teams worked 12-hour shifts. Management compared this with what it described as a usual minimum 24-month build period for a chemical-process greenfield project and 18 months for the fastest comparable Chinese construction.
Got a follow-up? Ask IRIS
Why is Stallion completing Mambattu in Q1?
Stallion expects to complete Mambattu in the first quarter because it expanded and redesigned the facility before beginning operations. The Andhra Pradesh site was initially intended primarily for hydrofluoroolefin, or HFO, blending, but management said it was broadened to include helium, hydrocarbons and other activities across the entire acreage.
Management said it chose not to start the plant and later carry out expansion that could interrupt operations. That decision resulted in a redesign that nearly doubled the project's cost scope. It said most work was complete, with construction finished apart from limited work including the office building.
Mambattu is not dependent on Bhilwara, but Stallion called the two facilities complementary because R32 would account for 60% of Mambattu's production requirements. Management said Mambattu's full business scope would emerge alongside R32 production, and that the revenue contribution expected from Mambattu in FY27 would instead move into the first quarter.
What do the project shifts mean for Stallion's FY27 targets?
Stallion maintained that it can meet its FY27 revenue objective without R32 or Mambattu revenue. Management said it had discussed revenue of Rs 500 crore for the year, or Rs 560 crore if it achieved 30% year-on-year growth, and later raised its internal target to Rs 560 crore.
The company reported first-half FY27 revenue from operations of Rs 257.48 crore, up 19.18% year on year, while total income rose 22.07% to Rs 264.05 crore. Operating earnings before interest, tax, depreciation and amortisation before employee stock-option expenses increased 36.39% to Rs 41.10 crore, and operating profit after tax before those expenses rose 40.16% to Rs 30.53 crore.
Second-quarter revenue from operations rose 28.86% year on year to Rs 136.03 crore, although operating earnings before interest, tax, depreciation and amortisation before employee stock-option expenses grew 0.43% and operating profit after tax before those expenses increased 4.78%. Management said the second half is normally stronger and reiterated that it expects to meet its FY27 commitment without R32.
For the following year, management said 7,000 tonnes of R32 output could contribute Rs 350 crore to Rs 400 crore of revenue. It said this could support revenue of about Rs 1,000 crore alongside normal business growth, but this was management's projection rather than reported revenue or formal guidance.
Conclusion
The combined effect is a shift in the timing of Stallion's two expansion projects rather than their withdrawal. Bhilwara is planned to move from March trials to April production, while Mambattu is scheduled for first-quarter completion after an expanded design nearly doubled its cost scope. Neither facility is expected to contribute revenue in FY27, even as management continues to target Rs 560 crore of revenue for the year.
The next disclosed milestones are Bhilwara trials by March, planned April production and Mambattu's first-quarter completion. Management also said environmental studies for a proposed HFO plant had begun, but construction activity would start only after Bhilwara had stabilised and operated smoothly for three to five months; funding remains undecided among equity issuance, debentures and debt.