Suntech plans Rs 135 crore core order execution by March 2027
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Suntech reported a Rs 204.20 crore order book at the end of H1 FY27.
- Suntech plans to execute Rs 135 crore of construction and piling foundation orders before March 2027.
- Suntech expects to complete 100% of its Rs 9.50 crore equipment-rental backlog in FY27.
- H1 FY27 revenue rose 47.62% to Rs 99.84 crore and net profit increased 98.94% to Rs 6.02 crore.
powered by IRIS

Suntech Infra Solutions Limited plans to execute Rs 135 crore of its Rs 194.70 crore construction and piling foundation order book by March 2027, while management expects to complete its Rs 9.50 crore equipment-rental backlog in FY27. The company reported a total order book of Rs 204.20 crore in H1 FY27.
Know Suntech Infra Solutions inside out
Results, valuation, peers and who's buying, in one view.
How much of Suntech's order book is due by March 2027?
Suntech said Rs 135 crore of its Rs 194.70 crore construction and piling foundation order book is planned for execution before March 2027. Management gave the segment-specific timeline during its November 23, 2026 earnings call, covering the half year ended September 30, 2026. It said the remaining construction and piling foundation work would be finished in FY28.
Suntech also expects to complete 100% of the Rs 9.50 crore equipment-rental order book in FY27. The two segment statements imply execution of Rs 144.50 crore of the Rs 204.20 crore total order book by March 2027. In an earlier response, management referred to Rs 144 crore of orders being executed before March, while the later breakdown specified Rs 135 crore for the core construction segment.
The execution schedule is chiefly tied to the construction and piling foundation business, which represents Rs 194.70 crore of the Rs 204.20 crore backlog. Rental accounts for Rs 9.50 crore, but management expects that entire amount to be completed within FY27. Therefore, progress at foundation and civil-work sites will determine most of the stated near-term order conversion.
What work makes up Suntech's current order book?
Suntech's Rs 204.20 crore order book consists of Rs 194.70 crore in construction and piling foundation work and Rs 9.50 crore in equipment rental. During H1 FY27, it secured Rs 87.70 crore of new construction and piling foundation orders. Management described the core portfolio as covering civil, structural, piling and foundation work.
Suntech said it has executed projects across refineries, petrochemicals, renewable energy, high-rise buildings, information-technology parks, metros and rail infrastructure, including at Mundra, Dahej, Bihar and Pachpadra. It did not provide an order-book split by client, project, location or industry. Management said industrial houses currently contribute 45% to 50% of business and real estate contributes 15% to 20%.
Beyond confirmed orders, Suntech reported an opportunity pipeline of more than Rs 800 crore. Management said it expected Rs 100 crore to Rs 150 crore of orders at advanced stages to be secured within 30 to 45 days of the November 23 call, and hoped to secure 20% to 25% of the total pipeline before the end of March 2027. These were management expectations rather than confirmed orders.
Got a follow-up? Ask IRIS
What H1 FY27 performance supports Suntech's execution plan?
Suntech reported revenue from operations of Rs 99.84 crore in H1 FY27, up 47.62% from Rs 67.64 crore in H1 FY26. Construction and piling foundation revenue rose 44.8% to Rs 90.47 crore, while construction equipment rental revenue increased 81.83% to Rs 9.93 crore. The core segment remained the larger revenue contributor despite faster rental growth.
Earnings before interest, taxes, depreciation and amortisation (EBITDA) increased 46.66% to Rs 18.09 crore, with an EBITDA margin of 18.12%. Net profit rose 98.94% to Rs 6.02 crore from Rs 3.02 crore a year earlier. Management said profit before tax margin increased to 9.1% from 6.4%, while net profit margin rose by 156 basis points to 6.03%.
Suntech spent Rs 8.05 crore on capital expenditure in H1 FY27 and expanded its owned fleet to 103 machines from 100. Management said the company has more than 700 professionals and maintains its fleet in-house. It also cited activity-wise standard operating procedures, key-performance-indicator-linked reviews, weekly management information systems, enterprise-resource-planning-based fleet tracking and tighter project costing.
What could affect Suntech's March 2027 order execution?
Suntech said it expects to execute the Rs 135 crore of core orders if conditions remain broadly in line with its plan, but it identified possible construction restrictions in the National Capital Region as a risk to activity. Management said H1 includes three monsoon months and typically accounts for 40% of construction activity, compared with 60% in H2. It said monsoon conditions can reduce site productivity.
Management did not give a fixed H2 FY27 revenue forecast. It said it expected higher H2 productivity to support execution because a similar volume of work can be completed more efficiently outside the monsoon period. The company also said that, if conditions go as planned, it expects to achieve the stated Rs 135 crore execution of core orders.
Working-capital timing will also be relevant to project delivery. Suntech said receivables generally range from 30 to 45 days, consumables inventory is roughly 90 days and raw-material inventory is under 30 days. Supplier payments are managed over 45 to 60 days, while management reported Rs 20 crore of surplus cash flow from operating activities and working-capital facilities with HDFC Bank, Kotak and ICICI Bank.
Conclusion
Suntech has provided a conversion timetable for most of its Rs 204.20 crore H1 FY27 order book: Rs 135 crore of construction and piling foundation work and Rs 9.50 crore of rental work are expected to be executed by March 2027. The plan follows 47.62% revenue growth to Rs 99.84 crore in H1 FY27, led by the Rs 90.47 crore core construction and foundation segment.
The next items to watch are progress on the more than Rs 800 crore order pipeline, execution of the Rs 135 crore core-order target, and the planned Rs 15 crore to Rs 20 crore equipment investment over the next 90 to 120 days. Management also said it plans to increase the fleet beyond 120 machines over the next two years, although equipment choices had not been finalised.