Techno has 85% of smart-meter book installed by October
Key highlights
- Techno installed 85% of its 2.24 million awarded smart-meter portfolio by 30 October 2026, versus 70% at FY26 close.
- Techno's four-state smart-meter portfolio has a stated value of about Rs 2,612 crore and a 120-month project structure.
- Madhya Pradesh AMI 1 is 100% installed and certified and has entered its 93-month O&M phase.
- Jammu and Kashmir AMI 2 is due within Q3 FY27, while Jharkhand AMI 3 and Tripura AMI 4 are due within Q4 FY27.
powered by IRIS

Techno Electric & Engineering Company Limited had installed 85% of its 2.24 million awarded smart meters as at 30 October 2026, up from 70% at FY26 close, positioning its Rs 2,612 crore four-state portfolio to move from deployment into 93-month operation and maintenance (O&M) contracts.
Know Techno Electric & Engineering Company inside out
Results, valuation, peers and who's buying, in one view.
How far has Techno progressed with smart-meter installation?
Techno had completed 85% of portfolio-wide installation as at 30 October 2026, compared with 70% at the close of FY26. The 15-percentage-point increase brings the 2.24 million-meter programme closer to completion across Madhya Pradesh, Jammu and Kashmir, Jharkhand and Tripura.
The portfolio has two completed projects and three projects still in installation. Madhya Pradesh AMI 1 is completed, while Jammu and Kashmir Lot-B is also completed; Jammu and Kashmir AMI 2 was due to finish installation within Q3 FY27, and Jharkhand AMI 3 and Tripura AMI 4 were each due within Q4 FY27.
The completed projects provide separate evidence of delivery progress. Madhya Pradesh AMI 1 is 100% installed and certified and has entered the 93-month O&M phase, while Jammu and Kashmir Lot-B has delivered 2.5 lakh meters, is 100% live and has a stated project value of Rs 383.39 crore.
What is the value and duration of Techno's smart-meter book?
Techno's smart-meter awards cover 2.24 million meters, have a total project value of about Rs 2,612 crore and run for 120 months. The stated project period consists of 27 months of installation followed by 93 months of O&M.
The Rs 2,612 crore figure applies to the combined four-state portfolio rather than one individual project. Techno presents smart metering as the annuity component of its power-infrastructure engine, alongside its separate transmission engineering, procurement and construction (EPC) business and tariff-based competitive bidding (TBCB) assets.
The contract structure means that project activity extends beyond the installation deadline. Madhya Pradesh AMI 1 has already made that transition into its 93-month O&M period, while the three projects listed as on schedule were expected to complete installation by Q3 or Q4 FY27. The presentation does not disclose project-level O&M revenue, payment timing or annual cash flow.
Got a follow-up? Ask IRIS
How does the 93-month O&M phase create contracted cash flows?
Techno says the 93-month O&M phase produces contracted cash flows after the 27-month installation period. Across the 120-month structure, management describes the portfolio as providing 10-year visibility.
The model is intended to retain operating activity after meter deployment is completed. Under the disclosed framework, Techno operates and maintains the installed meter base for 93 months; Madhya Pradesh AMI 1 is the portfolio's identified example already in this phase, whereas Jammu and Kashmir AMI 2, Jharkhand AMI 3 and Tripura AMI 4 remained under installation at Q2 FY27.
Techno also says its DBFOOT structure limits upfront capital at risk while preserving long-term returns. The presentation does not expand the abbreviation, quantify capital deployed in smart metering or give project-level return measures, but it identifies the 93-month contractual period as the mechanism behind the annuity profile.
What can Techno monetise after projects are completed?
Techno says completed special-purpose vehicles (SPVs) can be monetised, creating a possible capital-recycling route after project completion. This is presented as an opportunity, not as a completed transaction, and the Q2 FY27 presentation discloses no buyer, valuation, timetable or sale proceeds.
Two projects were marked completed at Q2 FY27: Madhya Pradesh AMI 1 and Jammu and Kashmir Lot-B. The former is certified and in O&M, while the latter is 100% live after delivery of 2.5 lakh meters under a Rs 383.39 crore project, providing the disclosed operating milestones behind the monetisation opportunity.
Techno also identifies advanced metering infrastructure (AMI) as a foundation for future data-driven energy services. It does not disclose a revenue target, launch date, customer contract or defined service for those potential offerings; the current disclosed commercial base remains the Rs 2,612 crore portfolio and its 93-month O&M phase.
Conclusion
Techno's 2.24 million-meter programme has progressed from awarded work toward an operating portfolio, with installation reaching 85% on 30 October 2026 from 70% at FY26 close. Its Rs 2,612 crore book combines a 27-month build period with 93 months of O&M, and Madhya Pradesh AMI 1 has already entered that contracted operating stage.
The next disclosed milestones are installation completion for Jammu and Kashmir AMI 2 within Q3 FY27 and for Jharkhand AMI 3 and Tripura AMI 4 within Q4 FY27. Further certification and O&M transitions would show whether the remaining installation base follows Madhya Pradesh AMI 1, while any SPV monetisation update would address an opportunity for which Techno has provided no transaction value or timetable.