Z-Tech operates 10 parks amid unreconciled pipeline figures
Key highlights
- Z-Tech lists 10 operational parks, alongside six ready to inaugurate and seven under construction.
- Z-Tech’s stated 57-park pipeline conflicts with status categories that total at least 91 parks.
- Z-Tech projects FY27 revenue from operations of Rs 42 crore, versus Rs 8 crore for FY26.
- Management targets 25 operational parks by year-end, compared with 10 currently listed.
powered by IRIS

Z-Tech lists 10 operational parks in its presentation, while the six project-status categories shown add to at least 91 parks despite a stated total pipeline of 57. The disclosed operating base is therefore 10 parks, with the rest spanning inauguration-ready, construction, award, tendering and active-discussion stages of varying certainty.
Know Z-Tech (India) inside out
Results, valuation, peers and who's buying, in one view.
How many Z-Tech parks are operating?
Z-Tech identifies 10 parks as operational in its parks-status table. The same table separately lists six parks ready to inaugurate, seven under construction, five at award stage, 13 under tendering and more than 50 under active discussion, none of which is labelled operational.
The presentation does not provide park names, opening dates, locations or revenue for the 10 operating sites in the status table. It does, however, refer to the grand opening of Tawi Wonderland Park in Jammu and to an in-house customer relationship management, or CRM, platform intended to streamline park operations, monitoring and management; it does not state whether that park is included in the 10.
Z-Tech describes its Zynq Parks model as an experience-led operations and maintenance, or O&M, platform that converts ready civil spaces into recurring-revenue assets. The stated format includes landmarks, play zones and food and beverage, or F&B, offerings, but the presentation does not disclose footfall, ticket prices, park-level operating income or visitor-repeat rates for the 10 operational parks.
What stages make up the Z-Tech park pipeline?
Z-Tech divides its park list into six stages: 10 operational, six ready to inaugurate, seven under construction, five on award stage, 13 under tendering and 50-plus under active discussion. The labels distinguish projects already operating from those that remain in delivery, procurement or preliminary discussion stages.
The six ready-to-inaugurate parks and seven under-construction parks are identified at later labelled stages than the five award-stage, 13 tendering and 50-plus discussion-stage opportunities. Z-Tech gives no planned inauguration dates for the six parks, completion dates for the seven construction projects, or conversion assumptions for the 13 tendering and 50-plus discussion-stage projects.
The presentation also does not disclose contract values, capital requirements or expected O&M terms by status category. As a result, the table shows the number of projects at each stated stage, but not the likely timing or revenue contribution of parks that have not yet reached operations.
Why does Z-Tech's park table not reconcile with 57 projects?
Z-Tech’s parks page states that the “total pipeline shown” is 57 parks, but its six displayed status categories total at least 91. The minimum comes from 10 operational parks, six inauguration-ready parks, seven under construction, five on award stage, 13 under tendering and 50-plus under active discussion.
The actual total could exceed 91 because the final category is presented as 50-plus rather than a fixed number. Z-Tech does not explain whether the 57 figure represents a subset, whether projects appear in more than one category, or whether the summary and status rows use different definitions.
This distinction affects how the disclosed portfolio can be read. The 10 operational parks are explicitly identified as operating, while at least 81 parks in the displayed categories are not; the presentation does not support treating tendering or discussion-stage projects as operating capacity.
Got a follow-up? Ask IRIS
How does the park portfolio support Z-Tech's FY27 plan?
Z-Tech projects revenue from operations of Rs 42 crore for FY27, compared with Rs 8 crore for FY26, an increase of Rs 34 crore. Management attributes the projected more-than-fivefold increase to park-portfolio expansion, concerted marketing and efforts to maximise revenue from Zynq Parks.
Management identifies F&B expansion, sports and recreation activities, and events-based revenue as areas of focus for FY27. Its park-level revenue map also names gate ticketing, owned F&B corridors, event spaces, retail kiosk leases, adventure activities, sports, premium brand association and golf carts as potential revenue streams.
The Rs 42 crore figure is a projection rather than a reported FY27 result. Z-Tech does not allocate the FY27 projection between the 10 operational parks, the six ready-to-inaugurate parks, the seven projects under construction or any other status category.
What would increase Z-Tech's operating park count?
Z-Tech would need projects in its non-operational categories to move into operations to increase the disclosed base of 10 parks. The presentation specifically identifies six sites ready to inaugurate and seven under construction, but gives no site-level schedule showing when either group is expected to open.
Management states that it is targeting 25 operational parks by year-end. Against the disclosed count of 10 operational parks, meeting that target would mean adding 15 operating parks, although the presentation does not specify which inauguration-ready, construction-stage or other projects are expected to supply those additions.
Z-Tech also says it expanded its revenue team from three people to 20 people and has an order book of about Rs 350 crore. The presentation does not link the order book to individual parks, identify how much relates to Zynq Parks, or state whether the order book includes any of the 13 tendering or 50-plus active-discussion opportunities.
Conclusion
Z-Tech’s presentation separates a defined operating base of 10 parks from a much larger set of projects at different stages. Its stated 57-park pipeline cannot be reconciled with the displayed categories, which total at least 91, so the status table supports a clear distinction between operating parks and projects that remain to be inaugurated, built, awarded, tendered or discussed.
The next disclosed benchmark is management’s target of 25 operational parks by year-end, alongside its FY27 projection of Rs 42 crore in revenue from operations versus Rs 8 crore in FY26. Investors can watch for clarification of the 57-versus-91-plus difference, confirmation of park inaugurations and construction completions, and disclosure of how operating parks contribute to ticketing, F&B, events and other revenue streams.