Current Infra keeps Rs 200 crore FY27 target despite H1 gap
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Current Infra reported Rs 53.60 crore of consolidated total income in H1 FY27, up 19.46% year on year.
- Management retained its Rs 200 crore FY27 turnover target, requiring Rs 146.40 crore in H2.
- Current Infra’s Rs 44.76 crore JVVNL contract covers 8,000 PM Surya Ghar rooftop solar plants.
- Current Infra expects about 60% completion of roughly Rs 100 crore of RDSS work by March.
powered by IRIS

Current Infraprojects Limited kept its Rs 200 crore FY27 turnover target after reporting Rs 53.60 crore of consolidated total income in H1 FY27, with management citing historically heavier H2, particularly fourth-quarter, infrastructure billing and recently won solar and electrical engineering, procurement and construction projects.
Know Current Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
Can Current Infra meet its Rs 200 crore FY27 target?
Current Infra said it remains sure of achieving Rs 200 crore of turnover in FY27, although this requires Rs 146.40 crore of income in H2 after Rs 53.60 crore in H1. H2 would therefore need to deliver about 2.73 times H1 income, making execution and billing in the remaining six months central to management’s target.
Management said the pattern reflects the infrastructure-project cycle rather than a change in the FY27 outlook. Rainy-season conditions affect first-half execution, while milestone billing completed in March means that April, May and June billing mainly covers work already completed. Management said its last three or four years show H2 as the larger billing period, with Q4 contributing the most.
The Rs 200 crore target is the lower end of an earlier Rs 200 crore to Rs 250 crore range cited by an analyst during the call. Management did not provide a quarterly revenue bridge or disclose the amount of order-book revenue already recognised in H1 FY27, so the extent of the expected H2 conversion cannot be calculated from the call.
Which Current Infra projects could support H2 FY27 billing?
Current Infra identified the Rs 44.76 crore Jaipur Vidyut Vitran Nigam Limited, or JVVNL, PM Surya Ghar order as its largest project planned for FY27 execution. The contract covers design, supply, installation, testing and commissioning of 8,000 rooftop solar plants, with management describing the installations as 1.1 kilowatts each.
The other major projects named for H2 execution were a Rs 10.42 crore, 3-megawatt rooftop solar project for Bank Note Press, Dewas, and Border Security Force orders worth Rs 8.93 crore in Barmer. Current Infra also referred to Rs 12.16 crore of JVVNL turnkey work for 33/11 kilovolt substations and associated infrastructure in Rajasthan’s Baran Circle.
Management said it had converted more than Rs 100 crore of orders from its bid list in the preceding six months. It also said Rs 100 crore to Rs 120 crore of projects remained in the pipeline and might be awarded within one or two months, while cautioning that these opportunities may not be awarded. The pipeline is therefore not confirmed revenue for FY27.
Current Infra has also been empanelled for a Lakshadweep Electrical Department project with a total project cost of around Rs 50 crore and a battery energy storage system link. Management did not disclose the value that could be awarded to Current Infra, so the empanelment cannot be treated as a confirmed contribution to the Rs 200 crore turnover target.
Got a follow-up? Ask IRIS
How did Current Infra perform in H1 FY27?
Current Infra reported 19.46% year-on-year growth in consolidated total income to Rs 53.60 crore in H1 FY27, from Rs 44.87 crore in H1 FY26. Earnings before interest, tax, depreciation and amortisation, or EBITDA, increased 29.29% to Rs 10.21 crore, while the EBITDA margin rose by 137 basis points to 19.11% from 17.74%.
Profit after tax, or PAT, was Rs 5.01 crore in H1 FY27, up 28.79% year on year. The PAT margin increased by 64 basis points to 9.39% from 8.75%. EBITDA and PAT grew faster than total income, alongside the reported expansion in both margins.
Current Infra also said H1 FY27 operating cash flow was negative, without quantifying the amount, and management expects it to turn positive in H2. The company’s renewable energy service company, or RESCO, portfolio contributed around Rs 3 crore of revenue in H1 FY27 from four operational plants with aggregate capacity of 9.41 megawatts.
The RESCO assets include three 2.52-megawatt PM-KUSUM plants at Phalodi and a 1.85-megawatt plant at IIT (ISM), Dhanbad, under the Solar Energy Corporation of India framework. Management said the Rajasthan plants generate more than 5 to 5.5 units per kilowatt a day, while the Dhanbad plant generates around 4 to 4.5 units per kilowatt a day.
What could affect Current Infra’s H2 execution and cash flow?
Current Infra’s H2 execution depends in part on progress in roughly Rs 100 crore of Revamped Distribution Sector Scheme, or RDSS, orders. Management said around 23% to 25% of this work was complete and expected about 60% completion by March, subject to fund availability and land access for project work.
Management said its current distribution-company projects are supported by central government funds and generally receive payment within 10 to 20 days after an invoice is submitted. This comment applied specifically to the distribution companies, or DISCOMs, being served. Billing, invoice acceptance and collection will determine whether this payment cycle supports the forecast positive H2 operating cash flow.
Current Infra said longer-duration government projects generally include price-variation clauses to address movements in copper, aluminium and steel prices. Management also said it monitors material prices daily and may book requirements for the following three to six months when it expects prices to rise.
The company acknowledged that infrastructure projects can face client-side delays and cost overruns, including salary and other expenses. Its chief financial officer said some other current assets consist of supplier advances for materials and order booking, with individual advances of around Rs 2 crore or Rs 3 crore and the highest at Rs 3 crore. These advances support procurement but make billing and collections relevant to working-capital management.
Conclusion
Current Infra’s retained Rs 200 crore FY27 target depends on a substantial H2 acceleration from Rs 53.60 crore of H1 income. The company reported year-on-year growth in income, EBITDA and PAT margins, while identifying the Rs 44.76 crore JVVNL rooftop-solar contract, Bank Note Press work and Border Security Force orders as major FY27 execution projects.
The next disclosures to watch are progress toward the planned 60% RDSS completion by March, billing from the 8,000-house JVVNL programme and whether Rs 100 crore to Rs 120 crore of pipeline opportunities convert into awards within the indicated one or two months. Management’s expected positive H2 operating cash-flow turn will also depend on project billing and collection timing.