Current Infraprojects targets 8,000 roofs by April 2027
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Current Infraprojects targets 8,000 JVVNL rooftop systems by a maximum of 10 April 2027.
- Current Infraprojects had installed about 100 systems and targets around 1,500 installations a month.
- Management expects Current Infraprojects to bill around 75% of the Rs 44.76 crore project in the coming quarter.
- Current Infraprojects reported a Rs 329 crore order book and around Rs 53 crore of September 2026 consolidated revenue.
powered by IRIS

Current Infraprojects Limited plans to complete 8,000 PM Surya Ghar rooftop solar installations by a maximum of 10 April 2027 under a Rs 44.76 crore JVVNL order, after installing about 100 systems. Management targets around 1,500 installations a month and expects to bill roughly 75% of the project in the coming quarter.
Know Current Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
How will Current Infraprojects execute 8,000 rooftop installations?
Current Infraprojects will target around 1,500 rooftop installations a month to complete the 8,000-consumer JVVNL assignment by mid-April 2027. Management said every consumer installation under the project carries 1.1 kilowatts of rooftop solar capacity. It said the company had already put manpower and the execution team at site, established a site store, placed some manufacturer purchase orders, and received distribution company, or DISCOM, approvals.
Current Infraprojects had already installed about 100 consumer rooftop systems when management discussed the project. Full-scale on-site work was due to begin within three or four days of the call, according to management. The company said this early installation count put it ahead of the DISCOM's wider push for the programme, although the stated completion deadline remained the end of the financial year or a maximum of 10 April 2027.
When will Current Infraprojects bill the JVVNL order?
Current Infraprojects expects to bill around 75% of the JVVNL project in the coming quarter. Management linked that expectation to the planned installation ramp-up of around 1,500 systems a month after full-scale site work starts. It said the remaining 25% would be received annually during the maintenance period rather than forming part of the initial bulk billing.
The planned billing is sizeable against Current Infraprojects' consolidated revenue of around Rs 53 crore for September 2026. Management said around Rs 50 crore came from standalone operations and around Rs 3 crore from consolidation. Within standalone revenue, it put electrical and solar activities at around Rs 35 crore to Rs 40 crore, making the 8,000-system rooftop assignment part of its established operating segments.
How will Current Infraprojects receive PM Surya Ghar payments?
Current Infraprojects said more than 55% to 60% of the project payment is expected to be credited through central financial assistance, or CFA, after installation and meter completion. Management said the company must upload the consumer number and site photographs on the PM Surya Ghar portal to initiate this process. The payment mechanism therefore requires both physical commissioning and online documentation for each of the 8,000 sites.
Management also described around 25% of payment as coming from the DISCOM, while another 25% would come over the next five years. These comments distinguish payment components from the company's estimate that around 75% of the project can be billed in the coming quarter. The transcript does not provide a detailed reconciliation between the 55% to 60% CFA portion, the DISCOM portion and the maintenance-period receipts, leaving the timing of cash collection subject to installation, metering and processing stages.
Got a follow-up? Ask IRIS
How material is the JVVNL order to Current Infraprojects?
Current Infraprojects reported an order book of Rs 329 crore, so the Rs 44.76 crore JVVNL project equals about 13.6% of that total by simple comparison. This compares a confirmed rooftop order with the company's disclosed order book, rather than its pipeline. The project also has a defined operating target of 8,000 installations by 10 April 2027, unlike broader tender opportunities.
Management put its solar and electrical pipeline at around Rs 400 crore to Rs 500 crore, with more than Rs 200 crore relating to solar alone. It said its recent tender conversion rate was around 15% to 20%, so those pipeline figures are not confirmed orders. Management also said it avoids taking projects solely to expand order book, and cited expected gross margins of around 17% to 20%, profit-before-tax margins of 10% to 12%, and profit-after-tax margins of around 8% to 10% while bidding.
What does the rollout mean for Current Infraprojects cash flow?
Current Infraprojects expects cash flow to increase positively in the coming months and over the next six months, management said. It explained that some prior material supplies had generated only 60% to 70% payment at the supply stage, with full payment received on commissioning. For the JVVNL project, the steps from installation to metering, portal upload and payment processing will therefore affect the conversion of billed work into cash receipts.
An analyst said borrowings had risen from Rs 33 crore to Rs 49 crore in the first half. Management replied that working-capital limits had increased by around Rs 16 crore, comprising around Rs 11 crore and Rs 5 crore additions for new projects. It described working-capital limits of around Rs 25 crore to Rs 30 crore and cited a combined Rs 50 crore figure that included normal and non-fund-based limits.
What other execution areas is Current Infraprojects pursuing?
Current Infraprojects said it plans broadly equal expansion across solar, electrical and other existing segments over the next two to three years. Management said it did not intend to scale solar by five or 10 times without proportionate expansion in electrical activities. It expects revenue mix to remain broadly similar, while commissioned renewable energy service company, or RESCO, projects add fixed revenue and cash-flow streams.
Current Infraprojects is also bidding for gas-insulated switchgear, or GIS, substation work through joint ventures because it does not yet hold all required qualifications independently. Management said one GIS project was under bidding and that government DISCOMs and transmission departments were opening GIS tenders. The company also cited a Rs 50 crore battery energy storage system, or BESS, empanelment at Lakshadweep, while describing Uttarakhand and Haryana BESS tenders costing more than Rs 200 crore each as active opportunities.
Conclusion
The JVVNL order gives Current Infraprojects a specific Rs 44.76 crore execution programme with 8,000 1.1-kilowatt rooftop systems, around 100 already installed and a monthly target of about 1,500. Management's forecast of billing around 75% in the coming quarter puts delivery pace at the centre of the project's near-term contribution, compared with September 2026 consolidated revenue of around Rs 53 crore.
The next measures to watch are whether Current Infraprojects maintains its 1,500 monthly installation target, reaches the stated maximum completion date of 10 April 2027, and converts meter completion and portal uploads into receipts. Management has also forecast positive cash-flow improvement over the coming six months while reporting first-half borrowings of Rs 49 crore, making collection progress alongside commissioning relevant to the plan.