Deccan Gold Mines starts Altyn-Tor commissioning with 5.67 tonnes
Key highlights
- Deccan Gold is commissioning Altyn-Tor using about 30,000 tonnes of run-of-mine and semi-processed material.
- Altyn-Tor has 5.67 tonnes of reported gold across open-pit resources, tailings and low-grade stockpiles.
- Management plans to process tailings and stockpiles for two to five years before a possible underground transition.
- Avelum Partners receives 83% of project revenue, and Deccan Gold said its effective revenue interest is 49%.
powered by IRIS

Deccan Gold Mines has started commissioning the Altyn-Tor processing plant in Kyrgyzstan using about 30,000 tonnes of run-of-mine and semi-processed material, with management reporting 5.67 tonnes of gold in current resources, tailings and stockpiles. The larger production plan depends on a proposed underground move after four to five years.
Know Deccan Gold Mines inside out
Results, valuation, peers and who's buying, in one view.
Has Deccan Gold started commercial production at Altyn-Tor?
Deccan Gold has started plant commissioning at Altyn-Tor, not reported an established commercial-production phase. Management said first gold doré was produced in 2026, the Merrill-Crowe recovery system was started, leaching commenced and a first doré-bar consignment was dispatched to a refinery. Merrill-Crowe is a recovery process used after leaching, and management said it would await refinery results while completing commissioning.
The immediate task is to commission the whole processing circuit during winter rather than run only the leaching tanks. Management said about 30,000 tonnes of material, including run-of-mine ore and semi-processed material, are available for this work. Run-of-mine ore is material mined before processing. Management said results from the quarter should be available to present at the end of December.
How much gold inventory does Altyn-Tor have?
Deccan Gold reported 5.67 tonnes of gold available above the planned underground development level at Altyn-Tor. This comprises 4.5 tonnes of in-situ resource within the planned open pit, at an average grade of 1.69 grams per tonne, and about 1.09 tonnes in tailings and low-grade stockpiles. Tailings are residue from prior processing, while stockpiles are material kept for later treatment.
Management said the 5.67-tonne inventory will supply the initial operating phase, which is intended to process tailings and low-grade stockpiles for the next two to five years. It said operating expenditure, or opex, is expected to be lower in that period because there is no active mining. Before tailings leaching begins, however, the plant must process the available 30,000 tonnes to establish how the complete circuit performs.
The inventory excludes the deeper target below the boundary set for underground development. Management said areas above an upper level had already been mined since the operation began in 2003, while the 4.5-tonne in-situ resource sits within the planned open pit. The stated 5.67 tonnes is therefore the available inventory up to the lower boundary, rather than an estimate of the deeper underground resource.
How does Deccan Gold receive Altyn-Tor revenue?
Deccan Gold receives its economic interest through Avelum Partners, which has a revenue-sharing arrangement with Kyrgyzaltyn, a Kyrgyz government company. Management said Kyrgyzaltyn receives 17% of project revenue and Avelum Partners receives 83%. It described Avelum Partners as Deccan Gold's subsidiary for the Altyn-Tor project.
Deccan Gold holds 60% of Avelum Partners and management said this translates into an effective 49% interest in project revenue. It said Hira Group holds 26% of Avelum Partners and Medetbek holds 14%. The company therefore does not claim all Altyn-Tor revenue directly; its participation follows both the 83% allocation to Avelum Partners and its ownership of that entity.
Revenue timing remains unresolved while commissioning continues. Deccan Gold said the first doré consignment has been sent to a refinery but that it would wait for results while moving towards full processing-plant commissioning. The stated near-term reporting point is the end of December, after work on the 30,000 tonnes of available material.
Got a follow-up? Ask IRIS
When could Deccan Gold begin underground mining at Altyn-Tor?
Deccan Gold plans to move Altyn-Tor underground after four to five years of processing low-grade stockpiles and tailings. Management said initial drilling had shown continuity of ore bodies below the current lower boundary and identified a target to add another 3 tonnes of gold. This target is separate from the 5.67 tonnes reported for the current phase.
Management said underground ore could grade about 2.5 to 3 grams per tonne, compared with 1.69 grams per tonne for the 4.5-tonne in-situ open-pit resource. It said the higher grade could increase yield and production capacity, and that output could potentially double the projected 700 to 750 kilograms once underground mining begins. Management presented this as a later-stage possibility, not as current output guidance.
The project sequence starts with processing material already on site, where management expects lower opex because mining is not required. An underground transition would follow exhaustion of the low-grade sources and tailings, and would depend on advancing drilling evidence into a larger defined resource and executing an underground mine plan.
What does Altyn-Tor add to Deccan Gold's growth plan?
Deccan Gold described Altyn-Tor as its second production inflection point after the Swarnagiri mine in Andhra Pradesh. Management said Swarnagiri began production in July 2026 and the Kyrgyzstan project was inaugurated in September 2026. It presented these projects as evidence of its ability to develop mining operations, while identifying critical minerals as a third growth platform.
Swarnagiri is at a more advanced operating stage than Altyn-Tor. Management said Swarnagiri had reached monthly production of about 40 to 45 kilograms, produced 135 kilograms and sold 50.4 kilograms of refined bullion. Altyn-Tor, by contrast, has produced first doré and dispatched a first refinery consignment while the plant is being commissioned on 30,000 tonnes of available material.
Altyn-Tor also broadens Deccan Gold's portfolio beyond India through a Kyrgyzstan revenue-sharing asset. Its immediate plan is processing and recovery from tailings, low-grade stockpiles and other available material. The longer-term case depends on the reported 2.5-to-3-grams-per-tonne underground grade range, additional drilling and the planned shift underground after four to five years.
Conclusion
Altyn-Tor has moved from construction into commissioning, with first doré produced, leaching started, the Merrill-Crowe system operating and a refinery dispatch completed. The reported 5.67 tonnes of gold provides the basis for the initial phase, which management intends to run on stockpiles and tailings rather than immediate underground extraction. The comparison with Swarnagiri shows that Altyn-Tor remains earlier in its operating development.
The next disclosed milestone is management's planned end-December update on commissioning results from the available 30,000 tonnes of material. Investors will also watch for tailings leaching, progress through the planned two-to-five-year stockpile phase, drilling aimed at another 3 tonnes of gold below the current boundary and the proposed underground transition after four to five years.