Energy Infrastructure Trust RIL deal assures 20-year capacity payments
Key highlights
- EIT's March 2019 agreement with RIL runs for 20 years and provides minimum guaranteed capacity payments.
- RIL bears EIT's O&M and capex overruns beyond budget under the disclosed contract structure.
- EIT distributed Rs 7.76 per unit in H1 FY27, equal to 100% of net distributable cash flow.
- PIL's H1 FY27 average throughput was 37.48 MMSCMD, up from 34.49 MMSCMD in H1 FY26.
powered by IRIS

In H1 FY27, EIT said its March 2019 pipeline usage agreement with RIL assures minimum contracted capacity payments for 20 years regardless of actual utilisation, while RIL bears operating and capital expenditure overruns beyond budget. EIT distributed Rs 7.76 per unit, or 100% of net distributable cash flow, for the half year ended September 2026.
Know Energy Infrastructure Trust inside out
Results, valuation, peers and who's buying, in one view.
How does EIT's RIL contract protect cash flow?
EIT's RIL contract protects cash flow through minimum guaranteed contracted capacity payments against reserved pipeline capacity, irrespective of actual capacity utilisation. Management said the pipeline usage agreement was signed in March 2019 for 20 years, giving EIT a contractual base return even if RIL does not physically use all of its reserved capacity.
RIL also bears any operating and maintenance, or O&M, and capital expenditure, or capex, overrun beyond budget under the disclosed structure. EIT said this shifts budget-overrun risk to RIL, while counterparty risk for other customers is addressed through secured sales arrangements, letters of credit and customer security deposits. PIL averaged 37.48 million metric standard cubic metres per day, or MMSCMD, in H1 FY27, while overall pipeline utilisation was about 44%.
The arrangement separates EIT's protected payment from the pipeline's operating throughput. The 44% utilisation rate indicates that PIL retained unused capacity in H1 FY27, even as EIT reported a minimum payment arrangement for RIL's reserved capacity. Management did not disclose the guaranteed payment amount, contracted capacity or the budget used to determine an overrun.
What upside does EIT retain beyond guaranteed payments?
EIT retains upside through a share linked to PIL's cumulative return on capital employed, or ROCE, above a predefined threshold. Management said higher pipeline volumes and tariffs improve PIL's ROCE and that EIT participates in this ROCE-linked return, but did not disclose the numerical threshold, EIT's share of incremental returns or a timetable for reaching it.
The resulting model has two stated drivers: the RIL payment provides the contractual base, while throughput and tariff can affect ROCE-linked upside. In H1 FY27, realised tariff was Rs 82.9 per million British thermal units, or MMBTU, compared with Rs 79.9 per MMBTU for FY26, an increase of 3.8%. The Petroleum and Natural Gas Regulatory Board revised the levelised tariff to Rs 74.6 per MMBTU from January 1, 2026 across all five zones.
EIT passed through its available cash in the first half. The Rs 7.76-per-unit H1 FY27 distribution comprised Rs 4.28 per unit as return of capital and Rs 3.48 per unit as return on capital. Since acquisition through September 2026, EIT reported cumulative distributions of Rs 64.03 per unit as return on capital and Rs 56.02 per unit as return of capital, totalling about Rs 120 per unit.
How did EIT's pipeline volumes change in H1 FY27?
EIT's average pipeline throughput increased to 37.48 MMSCMD in H1 FY27 from 34.49 MMSCMD in H1 FY26 and 34.41 MMSCMD in H2 FY26. Management also compared the H1 FY27 average with the FY26 average of 34.45 MMSCMD, describing the increase as 8.8%. PIL recorded its highest single-day throughput of 46.91 MMSCMD in July 2026.
The customer mix contributed to the higher H1 FY27 volume. RIL accounted for around 23.5 MMSCMD, ONGC for about 4 MMSCMD and regasified liquefied natural gas, or RLNG, for about 10 MMSCMD, nearly double the FY26 level. Management attributed growth to higher liquefied natural gas demand from fertiliser and steel customers, alongside intermittent demand from power and refinery customers.
Volumes softened in August and September 2026 after a shutdown at a key fertiliser customer and a delayed ramp-up at an ONGC domestic field. Those effects were partly offset by demand from steel and fertiliser customers. Management said city gas distribution represented about 34% of volumes, fertilisers about 23%, and refinery and petrochemicals about 21%, showing a broader customer mix than in FY21, when city gas distribution contributed 2%.
Got a follow-up? Ask IRIS
What could change EIT's contracted cash-flow outlook?
EIT's RIL agreement runs for 20 years, but the ROCE-linked component can change with volumes, tariffs and new supply connections. PIL transports about 89% of KG Basin gas production, according to management, and carries 100% of gas from the RIL and BP D6 block. It also carries 100% of gas from ONGC's KG-DWN 98/2 Cluster 2 blocks, with Clusters 1 and 3 representing possible future volumes when production starts.
Management identified LNG terminal connections, compressed biogas and underground coal gasification as potential sources of incremental volume rather than committed cash flows. PIL has signed one compressed-biogas tie-in agreement, while regulatory discussions on injecting compressed biogas into the pipeline network are under way. The existing 44% utilisation rate leaves physical capacity for additional gas volumes if these projects proceed.
The proposed underground coal gasification project in Eluru, Andhra Pradesh, remains conditional on exploration findings, viability and approvals. Management said its first exploration and pilot phase is expected from Q3 2026 to Q4 2027, with commercial production to follow only if the findings support development. It said the project could supply gas from 2030, but did not present it as a committed source of PIL throughput.
What refinancing issue does EIT face in March 2027?
EIT plans to refinance its Rs 1,000 crore Series 1 non-convertible debentures, or NCDs, due in March 2027. Management said it has a three-month call option and is evaluating refinancing alternatives with banks. The Series 1 NCDs carry annual interest of 7.96%, payable quarterly.
EIT held Rs 6,452 crore of debt across three listed, rated and secured NCD series as of September 30, 2026. Series 2, also Rs 1,000 crore, matures in March 2028, while the Rs 4,452 crore Series 3 matures in March 2029. EIT's debt-to-assets-under-management ratio was 44.2% at September 30, 2026, compared with 45.1% at the end of FY26.
Conclusion
EIT's disclosed structure combines a 20-year RIL capacity-payment agreement with a separate ROCE-linked upside mechanism. Minimum contracted payments regardless of utilisation and RIL's responsibility for budgeted O&M and capex overruns provide the stated downside protection, while the increase in average throughput to 37.48 MMSCMD and the Rs 82.9-per-MMBTU realised tariff can influence PIL's ROCE. EIT's Rs 7.76-per-unit H1 FY27 distribution represented 100% of net distributable cash flow.
The next disclosed events to watch are the planned refinancing of the Rs 1,000 crore Series 1 NCDs due in March 2027, the timing of ONGC field ramp-ups and the Q3 2026 to Q4 2027 exploration and pilot work for the proposed Eluru project. Management said any volume contribution from underground coal gasification remains dependent on exploration, viability and approvals.