IndianOil refinery expansions target December 2026 finish
Key highlights
- IndianOil expects to complete refinery expansions at Panipat, Gujarat and Barauni by December 2026, adding 17.3 MMTPA of capacity.
- The three expansions were 90.1% to 95.0% physically complete as of September 30, 2026, with combined approved costs of Rs 75,280 crore.
- The projects would increase combined capacity at the three refineries from 34.7 MMTPA to 52.0 MMTPA, a 50% rise.
- IndianOil spent Rs 12,162 crore on capital expenditure in H1 FY 2026-27 against a full-year target of Rs 32,700 crore.
powered by IRIS

IndianOil plans to complete refinery expansions at Panipat, Gujarat and Barauni by December 2026, adding 17.3 million metric tonnes per annum (MMTPA) of capacity. As of September 30, 2026, the three projects were 90.1% to 95.0% physically complete, with combined gross approved costs of Rs 75,280 crore.
Know Indian Oil Corporation inside out
Results, valuation, peers and who's buying, in one view.
Which IndianOil refinery expansions are due in December 2026?
IndianOil has scheduled the Panipat, Gujarat and Barauni refinery expansions for completion in December 2026. Together, they will lift the three refineries’ combined capacity from 34.7 MMTPA to 52.0 MMTPA, an increase of 17.3 MMTPA. IndianOil reported these timelines in its major-projects update as of September 30, 2026.
Panipat is the largest of the three additions, moving from 15 MMTPA to 25 MMTPA and contributing 10 MMTPA of the total increase. Gujarat is planned to rise from 13.7 MMTPA to 18 MMTPA, adding 4.3 MMTPA, while Barauni is set to increase from 6 MMTPA to 9 MMTPA, adding 3 MMTPA. Panipat represents about 58% of the planned 17.3-MMTPA addition.
How far has IndianOil progressed on the refinery projects?
IndianOil had completed 95.0% of the Panipat expansion, 92.5% of the Barauni expansion and 90.1% of the Gujarat expansion by September 30, 2026. The difference between the most advanced and least advanced refinery project was 4.9 percentage points, while all three retained the same December 2026 expected completion date.
The Panipat project was both the largest by capacity addition and the furthest advanced by physical progress. Its Rs 38,231 crore gross approved cost exceeds the Rs 18,936 crore for Gujarat and Rs 18,113 crore for Barauni. Gujarat had the lowest reported completion percentage despite its 4.3-MMTPA planned increase being larger than Barauni’s 3-MMTPA increase.
The reported figures are physical-progress measures rather than confirmation that added capacity has entered operation. IndianOil gives December 2026 as the expected completion date for all three refinery projects, but does not provide individual commissioning dates, start-up dates or phased capacity ramp-up details for Panipat, Gujarat or Barauni.
How is IndianOil deploying capital expenditure in FY 2026-27?
IndianOil incurred provisional capital expenditure of Rs 12,162 crore during H1, or the first half, of financial year (FY) 2026-27, against a full-year capital-expenditure target of Rs 32,700 crore. Refinery spending was Rs 6,083 crore, the largest disclosed segment allocation for the first half and exactly half of total reported H1 expenditure.
Marketing received Rs 3,396 crore and petrochemicals received Rs 1,306 crore in H1 FY 2026-27, compared with Rs 582 crore for pipelines. Gas spending was Rs 133 crore, research and development received Rs 109 crore, exploration and production received Rs 121 crore, and other expenditure was Rs 432 crore. Refinery, marketing and petrochemicals together accounted for Rs 10,785 crore of the Rs 12,162 crore total.
The H1 FY 2026-27 spending level equals about 37% of the Rs 32,700 crore annual target, based on IndianOil’s provisional figures. The segment data cover refinery, marketing, petrochemicals, pipelines, gas, research and development, exploration and production, and other activities, rather than only the three refinery expansions with Rs 75,280 crore of gross approved costs.
Got a follow-up? Ask IRIS
What other IndianOil projects are nearing commissioning?
IndianOil reported that the PX-PTA Complex at Paradip Refinery and the New Mundra Panipat Crude Oil Pipeline were under commissioning as of September 30, 2026. The Paradip complex was mechanically completed in September 2026, while the pipeline across Gujarat, Haryana and Rajasthan was mechanically completed in July 2026.
The PX-PTA Complex has a gross approved cost of Rs 13,805 crore, and the New Mundra Panipat Crude Oil Pipeline has a gross approved cost of Rs 9,028 crore. IndianOil does not report a physical-progress percentage or an expected completion date for either asset in this update, instead identifying both as under commissioning after their respective mechanical-completion milestones.
A Poly Butadiene Rubber Plant at Panipat had reached 92.2% physical progress and was expected to be completed in December 2026, with a gross approved cost of Rs 2,949 crore. By comparison, the New R&D Campus-II in Faridabad, Haryana was 65.6% complete and had a July 2027 expected completion date, with a gross approved cost of Rs 3,220 crore.
What does the expansion programme change for IndianOil operations?
IndianOil’s disclosed programme would increase capacity at the three named refineries by 50% overall, from 34.7 MMTPA to 52.0 MMTPA, if the projects are completed as planned. The increase is concentrated at Panipat, where capacity is intended to rise by 10 MMTPA, compared with 4.3 MMTPA at Gujarat and 3 MMTPA at Barauni.
The planned refinery additions follow standalone refinery throughput of 18.1 million metric tonnes in Q2, or the second quarter, of FY 2026-27, down from 19.2 million metric tonnes in Q1, or the first quarter. Capacity utilisation also declined to 102.3% in Q2 from 109.4% in Q1, while use of high-sulphur crude increased to 54.6% from 48.9%. These operating figures are separate from the project capacity targets.
Conclusion
IndianOil’s three December 2026 refinery expansions form a Rs 75,280 crore programme that would add 17.3 MMTPA across Panipat, Gujarat and Barauni. Physical progress of 90.1% to 95.0% as of September 30, 2026 shows that all three projects were approaching their stated completion date, although IndianOil did not disclose individual commissioning or ramp-up schedules.
The next disclosed milestones are the December 2026 expected completions for the three refineries and the 92.2%-complete Poly Butadiene Rubber Plant at Panipat. IndianOil’s progress toward its Rs 32,700 crore FY 2026-27 capital-expenditure target after provisional H1 spending of Rs 12,162 crore, and the July 2027 target for the Faridabad R&D Campus-II, are also scheduled developments to watch.