Matangi Rubber Limited plans 4,513 MTPA Bhind capacity for July 2027
Key highlights
- Matangi Rubber plans 4,513 MTPA of combined recycling and solid-tyre capacity in Bhind.
- The two Bhind projects carry estimated capital expenditure of Rs 27.49 crore.
- The recycling project represents 3,910 MTPA and Rs 19.06 crore of the proposed expansion.
- Matangi Rubber had placed no machinery orders for either project as of the red herring prospectus date.
powered by IRIS

Matangi Rubber Limited plans Rs 27.49 crore of new capacity at Bhind, Madhya Pradesh, comprising a 3,910 metric tonnes per annum (MTPA) rubber-recycling plant and a 603 MTPA solid-tyre plant, both scheduled for commercial operations on July 1, 2027. The projects remain based on management estimates and vendor quotations, with no machinery orders placed.
What is Matangi Rubber’s 4,513 MTPA Bhind expansion plan?
Matangi Rubber plans two greenfield manufacturing facilities in Bhind with combined estimated installed capacity of 4,513 MTPA and combined capital expenditure of Rs 27.49 crore. The rubber-recycling project is estimated at Rs 19.06 crore for 3,910 MTPA, while the solid-tyre project is estimated at Rs 8.44 crore for 603 MTPA.
The board approved the fresh-offer objects on May 25, 2026. Alongside the two facilities, Matangi Rubber has allocated Rs 45 crore to repay or prepay certain loans, while the allocation for general corporate purposes is unfinalised and may not exceed 25% of gross fresh-issue proceeds under the Securities and Exchange Board of India’s Issue of Capital and Disclosure Requirements Regulations.
The recycling facility represents 86.6% of the proposed 4,513 MTPA capacity, compared with 13.4% for solid tyres. The capacity mix makes recycling the larger project by output, while the solid-tyre facility would add products intended for material-handling, forklift, trolley and other industrial applications.
How will Matangi Rubber’s recycling plant operate?
Matangi Rubber intends to use the 3,910 MTPA recycling facility to process scrap rubber, primarily used tyres, tubes and flaps, and to undertake devulcanisation. Devulcanisation is a process that breaks sulphur cross-links in vulcanised rubber while retaining the polymer backbone, creating reclaimed rubber that can be blended with virgin rubber for tyres, tubes, flaps and industrial products.
The recycling plant is planned on company-owned Plot No. 80 at Industrial Area, Malanpur, Bhind, covering about 72,453.82 square feet. Matangi Rubber acquired the land from Chambal Pharmacy on April 24, 2025, and states that the facility could reuse internal waste and rejected material, potentially reducing the need for fresh raw materials.
The Rs 19.06 crore project estimate consists of Rs 7.22 crore for the building and boundary wall, Rs 9.82 crore for plant and machinery, and Rs 2.02 crore for miscellaneous assets. The plant-and-machinery estimate is based on Maris’s May 4, 2026 quotation, converted at Rs 111.39 per euro, while Mega India Infrastructure’s building quotation was extended through March 31, 2027.
Matangi Rubber had incurred nil capital expenditure on the recycling project as of October 7, 2026, according to a statutory-auditor certificate dated October 21, 2026. The company had received consent to establish from the MP Pollution Control Board on September 2, 2025, but listed the building plan, height-clearance no-objection certificate, fire clearance, electricity connection and water connection as yet to be obtained.
Got a follow-up? Ask IRIS
How will Matangi Rubber’s solid-tyre plant diversify production?
Matangi Rubber plans the 603 MTPA solid-tyre facility as an extension of its existing rubber-processing capability and raw-material supply chains. The proposed products are intended for industrial uses, including material handling, forklifts and trolleys, which would broaden the company’s stated customer applications beyond the automotive segment.
The facility would use about 6,000 square feet within Plot No. 78 at Industrial Area, Malanpur, Bhind, a leased site spanning approximately 179,563.55 square feet. Matangi Rubber took the plot on lease from Madhya Pradesh Industrial Development Corporation Limited on April 21, 2023, and commercial production at its 2/3-wheeler tyre plant on that plot began on December 27, 2025.
Of the Rs 8.44 crore estimated cost, Rs 7.42 crore is allocated to plant and machinery and Rs 1.01 crore to miscellaneous assets. The machinery plan includes curing presses, tyre-building equipment, 30 material-transfer carts and civil work, based on quotations from Barani Hydraulics India Private Limited, National Electricals and Megha India Infrastructure.
Matangi Rubber disclosed that the solid-tyre project had a building-plan approval and height clearance received on January 29, 2024, an electricity connection received on June 2, 2025, and pollution-board consent received on September 2, 2025. Its fire-plan approval certificate required renewal, while the project had also incurred nil capital expenditure as of October 7, 2026.
What could change Matangi Rubber’s Bhind project costs and timing?
Matangi Rubber states that both Bhind project budgets are based on its business plan, management estimates, vendor quotations and commercial and technical factors, rather than an appraisal by a bank or financial institution. It had not entered into definitive vendor agreements or placed orders for plant, machinery or equipment as of the red herring prospectus date, so suppliers, prices and delivery timing can change.
The company proposes to deploy Rs 19.78 crore of the two-project allocation in fiscal 2027 and Rs 7.72 crore in fiscal 2028. The implementation schedules show civil work and machinery orders beginning on September 1, 2026, machinery delivery from January 1, 2027 to March 31, 2027, installation through May 31, 2027, and trial runs in June 2027.
Matangi Rubber may revise or reschedule deployment if its financial condition, business strategy, access to capital, competition, interest rates or market conditions change. If actual expenditure exceeds the stated allocation, the company says it may use internal accruals or additional equity or debt; if expenditure is lower, the balance may be applied to other disclosed objects or general corporate purposes, subject to applicable law.
Conclusion
Matangi Rubber’s proposed Bhind expansion combines a 3,910 MTPA reclaimed-rubber facility with a 603 MTPA solid-tyre line, backed by Rs 27.49 crore of planned fresh-issue funding. The projects use existing land in Bhind and build on disclosed rubber-processing activities, but their budgets, suppliers and implementation assumptions have not yet been converted into firm machinery orders.
The next disclosed milestone is the July 1, 2027 commercial-operation target for both facilities. Progress depends on converting vendor quotations into purchases, completing the recycling plant’s outstanding approvals, renewing the solid-tyre fire approval and deploying the Rs 19.78 crore scheduled for fiscal 2027.