Monomark says Rs 1,761.92 crore order balance is unverified
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Monomark reported Rs 1,761.92 crore of pending order value as of September 30, 2026.
- O&M services represented Rs 1,696.47 crore, or 96.29%, of Monomark’s pending order balance.
- The Vedanta Silvassa O&M contract had Rs 543.98 crore pending and a September 1, 2031 scheduled completion date.
- Monomark reported FY 2026 revenue from operations of Rs 561.89 crore.
powered by IRIS

Monomark Engineering reported Rs 1,761.92 crore of pending order value on September 30, 2026, but said it had not verified the certainty, timing or actual realisation of the amount. The balance is calculated as total order value less billing already completed, rather than being assured future revenue.
What is Monomark’s unbilled order balance?
Monomark’s pending order balance was Rs 1,761.92 crore on September 30, 2026, calculated from total orders of Rs 2,255.00 crore less Rs 493.08 crore already billed. The figures exclude goods and services tax (GST) and cover Industrial Operations and Maintenance, or O&M, services and industrial project execution.
The distinction is material because the Rs 1,761.92 crore balance is not described as receivables, revenue guidance or a certified collection amount. Monomark says the amount represents the unbilled portion in available records, calculated as the difference between total order value and billing to date. It expressly states that it has not verified or certified the certainty, timing or actual realisation of the pending amount.
Monomark’s pending balance was about 3.14 times FY 2026 revenue from operations of Rs 561.89 crore. This comparison measures the scale of outstanding contracted work against the latest full-year revenue, but conversion depends on client demand, contractual continuity, operating conditions and project execution.
How concentrated is Monomark’s pending order balance in O&M?
O&M services accounted for Rs 1,696.47 crore, or 96.29%, of Monomark’s Rs 1,761.92 crore pending order balance on September 30, 2026. Industrial projects accounted for Rs 65.45 crore, or 3.71%, leaving the unbilled value substantially dependent on O&M contracts.
The pending-order mix was more concentrated in O&M than FY 2026 revenue. O&M generated Rs 450.31 crore, or 80.14%, of FY 2026 revenue from operations, while industrial project execution generated Rs 94.88 crore, or 16.89%. For the period ended June 30, 2026, O&M contributed Rs 127.74 crore, or 89.76%, of total revenue from operations of Rs 142.32 crore.
O&M billing can be influenced by the engagement model. In production-linked O&M arrangements, clients generally provide plant infrastructure, equipment and raw materials, while Monomark manages agreed production activities under a bill of quantities, a key performance indicator sheet or a similar contract framework. Payment may include a minimum production threshold and additional sums for output above agreed levels, tying some billing to operating volumes as well as service scope.
Which Monomark contracts run to 2031?
Monomark’s disclosed O&M purchase-order schedules extend to September 1, 2031, led by a Vedanta Limited Silvassa contract with Rs 543.98 crore remaining. An Adani Murmugao Port Terminal Private Limited contract had Rs 87.87 crore pending and was scheduled to end on July 31, 2031.
Together, these two contracts represented Rs 631.85 crore, or 35.86%, of the total pending balance of Rs 1,761.92 crore. The Vedanta Silvassa contract had a total order value of Rs 546.10 crore, with only Rs 2.12 crore billed by September 30, 2026, making its remaining value alone 30.87% of the pending balance.
Other large O&M balances included Rs 288.65 crore at Hindustan Zinc Limited’s Zawar Mines, scheduled through August 31, 2030; Rs 256.58 crore for Runnaya Green Tech Limited’s Biliya logistics, equipment and manpower work, scheduled through June 15, 2028; and Rs 166.26 crore at Hindustan Zinc’s Agucha mine, scheduled through August 31, 2027. Monomark says it has not independently verified the feasibility of stated completion dates and does not guarantee that remaining work or billing will be completed within those schedules.
Got a follow-up? Ask IRIS
Why does Monomark say the pending amount may not be realised?
Monomark says there is no assurance that the Rs 1,761.92 crore pending balance will be billed or materialise in future. The disclosure applies to both O&M and industrial-project balances, including contracts with stated purchase-order completion dates.
The company reported prior order-book execution rates of 97.99% in FY 2024, 94.96% in FY 2025, 106.50% in FY 2026 and 99.35% for the period ended June 30, 2026. The FY 2026 rate above 100% means the Rs 532.44 crore of orders executed exceeded the Rs 499.95 crore opening order-book amount; it does not establish that the September 2026 order balance will be realised.
Contract continuity is also a condition for conversion. Monomark disclosed two cancellation or termination instances in the preceding three fiscal years and the stub period because customers changed their operational methodology. It also states that contracts and purchase orders contain termination clauses, including potential termination following breaches of obligations or covenants.
What dependencies could affect Monomark’s order-book conversion?
Monomark’s order-book conversion is linked to metals-sector activity and repeat-client relationships. The metal industry generated Rs 470.22 crore, or 83.68%, of FY 2026 revenue from operations, up from Rs 365.56 crore, or 76.98%, in FY 2025. Cement revenue fell to Rs 50.60 crore, or 9.01%, in FY 2026 from Rs 65.90 crore, or 13.87%, in FY 2025.
Customer concentration is also visible in historical billing. Vedanta Group companies generated Rs 437.53 crore in FY 2026, equivalent to about 77.87% of total FY 2026 revenue of Rs 561.89 crore. Monomark also reported that repeat clients generated 87.30% of FY 2026 business, using a definition that requires the customer to have been billed in the immediately preceding fiscal year.
Execution requires personnel and equipment as well as customer work requirements. Monomark had 28 ongoing projects as of September 30, 2026, comprising 21 O&M projects and seven industrial execution projects, and owned 232 vehicles and industrial machines. It hired additional machinery when its owned fleet was insufficient, incurring equipment-hire charges of Rs 15.65 crore in FY 2026.
Conclusion
Monomark’s Rs 1,761.92 crore pending order balance quantifies work not billed as of September 30, 2026, but it does not establish future revenue or collections. O&M represented 96.29% of the amount, while two contracts scheduled into 2031 represented 35.86%, making execution and continuation of long-duration O&M assignments central to eventual billing.
The next points to watch are progress against the Rs 543.98 crore Vedanta Silvassa O&M balance and the Rs 87.87 crore Adani Murmugao Port Terminal assignment, both scheduled into 2031. Monomark says it intends to hire and deploy additional technical and non-technical staff to execute its order book and pursue further O&M and project work, while the feasibility of contract timelines remains unverified.