Laser Power & Infra Q2 Revenue Rises 2.1%, Profit Falls 5%
Key highlights
- Laser Power & Infra reported Q2 FY27 revenue of ₹628.2 crore, up 2.1% year-on-year.
- Reported Q2 FY27 net profit was ₹30.2 crore, down 5.0% year-on-year.
- The September 30 order book stood at ₹2,542.6 crore, split between ₹1,303 crore of manufacturing and ₹1,240 crore of EPC orders.
- Power Grid awarded Laser Power & Infra its first commercial HTLS conductor order worth ₹72.76 crore.
powered by IRIS

Laser Power & Infra Ltd reported Q2 FY27 revenue from operations of ₹628.2 crore, up 2.1% year-on-year, while its reported net profit fell 5.0% to ₹30.2 crore. The quarter reflected strong manufacturing activity but slower EPC execution after heavy rains, even as the company secured initial orders in higher-voltage transmission products.
Know Laser Power & Infra inside out
Results, valuation, peers and who's buying, in one view.
What did Laser Power & Infra report for Q2 FY27?
Laser Power & Infra reported revenue of ₹628.2 crore for the quarter ended September 30, 2026, compared with year-on-year growth of 2.1%. Its investor presentation reported EBITDA of ₹75.9 crore, translating into an EBITDA margin of 12.1%, compared with 13.0% a year earlier.
The company reported net profit of ₹30.2 crore, down 5.0% year-on-year, in the results summary. Separately, its investor presentation listed profit after tax of ₹30.6 crore and a PAT margin of 4.9%. The reported materials therefore show a small difference in the stated quarterly PAT figure, while both indicate profit was about ₹30 crore.
For the first half of FY27, Laser Power & Infra reported revenue of ₹1,149.8 crore and PAT of ₹51.7 crore. The company said the quarter's manufacturing operations were the main contributor to revenue growth, while EPC activity was affected by weather-related delays.
Why did revenue growth remain modest despite manufacturing growth?
Revenue growth remained modest because weather disruptions slowed execution in the EPC business, despite a 29.9% year-on-year increase in manufacturing revenue. Management said heavy rains affected project activity during the quarter, limiting the contribution from EPC operations to consolidated revenue.
The contrast between the two businesses is important because the order book was broadly split between manufacturing and EPC. At September 30, the order book stood at ₹2,542.6 crore, including ₹1,303 crore of manufacturing orders and ₹1,240 crore of EPC orders. This order book was lower than the ₹2,788 crore cited on the August 2026 earnings call.
Management maintained its FY27 revenue growth guidance of 10% to 15%. It also indicated an H2 EBITDA margin target of 12.5% to 13.0%, compared with the 12.1% margin reported for Q2. These are management targets rather than reported outcomes and depend on project execution during the second half.
Which high-voltage transmission orders did Laser Power & Infra win?
Laser Power & Infra won its first commercial HTLS conductor order from Power Grid worth ₹72.76 crore after roughly 18 months of testing and qualification. HTLS, or high-temperature low-sag conductor technology, is used for transmission upgrades where higher power transfer is required without proportionately expanding transmission corridors.
The company also received an order of about ₹44 crore from CESC for 33 kV and 220 kV underground cabling. Management said the execution period for this work is roughly one year. The two orders mark an entry into higher-voltage transmission work alongside the company's existing distribution-grade product portfolio.
Management linked demand visibility to India's grid modernisation and renewable-energy capacity expansion. However, it did not restate a numerical value for its HTLS tender pipeline during the call. It said it expected further orders by the end of the year, without disclosing the size or timing of any potential awards.
Got a follow-up? Ask IRIS
What are the company's capacity and working-capital plans?
Laser Power & Infra received a provisional letter of intent and in-principle approval for about 40 acres at Vidya Sagar Industrial Park for a Haridwar manufacturing facility on a long-term lease. The company had previously discussed phased capital expenditure and improved utilisation at its existing 85,000 MT capacity.
The company reiterated its focus on working-capital efficiency and targeted an improvement of 25 to 40 working-capital days by Q4 FY27. Management also targeted positive operating cash flow for FY27. These objectives are relevant because EPC contracts can require material procurement and extended collection cycles before cash is realised.
On borrowings, management said about ₹490 crore of IPO proceeds was used during Q2. Total borrowings were about ₹499 crore at September 30. The earlier August call had cited gross debt of about ₹360 crore alongside fixed deposits of about ₹240 crore, so investors should rely on the latest reported September 30 borrowing figure when assessing leverage.
How does the Q2 performance affect investors and operations?
The Q2 performance shows that manufacturing growth partly offset delayed EPC execution, but it was not enough to produce stronger consolidated revenue growth or maintain the prior-year EBITDA margin. The 12.1% EBITDA margin was 0.9 percentage points below the 13.0% margin reported a year earlier.
For investors, the key operational indicators are the pace of EPC execution after the monsoon period, conversion of the ₹2,542.6 crore order book, and delivery of working-capital improvement. The Power Grid HTLS order and CESC underground-cabling order provide evidence of activity in higher-voltage applications, but their financial contribution will depend on execution schedules.
The company held its Q2 and H1 FY27 earnings call on November 13, 2026, and subsequently uploaded the audio recording on its website. It said the call transcript would be filed with NSE and BSE and uploaded to the website in due course, without specifying a date.
Conclusion
Laser Power & Infra's Q2 FY27 results combined modest consolidated revenue growth with lower reported profit, as manufacturing growth was offset by weather-related EPC delays. Its new Power Grid and CESC awards add higher-voltage transmission work to the order pipeline, while the ₹2,542.6 crore order book provides the base for future execution.
The next areas to watch are the company's stated 10% to 15% FY27 revenue growth guidance, the H2 margin target of 12.5% to 13.0%, and progress toward improving working-capital days by 25 to 40 days by Q4 FY27. Investors will also await the exchange-filed call transcript for any additional details on project execution and new orders.