Laser Power enters transmission with Rs 72.76 crore HTLS order
Key highlights
- Laser Power won its first commercial HTLS conductor order from Power Grid, worth Rs 72.76 crore.
- Laser Power received a Rs 44 crore CESC Limited EPC order that includes its first 220 kV underground transmission project.
- Q2 FY27 manufacturing revenue rose 29.9% year on year to Rs 524 crore, while EPC revenue fell to Rs 104 crore.
- Laser Power’s order book stood at about Rs 2,543 crore on September 30, 2026, including Rs 1,303 crore of manufacturing orders and Rs 1,240 crore of EPC orders.
powered by IRIS

Laser Power & Infra Limited entered higher-voltage transmission in Q2 FY27 with a Rs 72.76 crore Power Grid high-temperature low-sag, or HTLS, conductor contract and a Rs 44 crore CESC Limited underground-cabling order. The awards, disclosed for the quarter ended September 30, 2026, are Laser Power’s first commercial HTLS and 220 kilovolt, or kV, underground-transmission credentials.
Know Laser Power & Infra inside out
Results, valuation, peers and who's buying, in one view.
What were Laser Power’s first higher-voltage transmission orders?
Laser Power’s first commercial HTLS order is a Rs 72.76 crore Power Grid contract for supplying conductors and reconducting existing transmission lines. Management called the award the most significant development of Q2 FY27 because it moves the advanced-conductor platform from product development and qualification into commercial execution.
HTLS conductors are intended to carry more power through an existing transmission corridor, an application management linked to constraints on land and right-of-way approvals for new lines. Laser Power said it accesses the technology through a licensing agreement with TS Conductors USA and spent about 18 months on testing, qualification and execution readiness before receiving the Power Grid order.
Laser Power also received a Rs 44 crore engineering, procurement and construction, or EPC, order from CESC Limited involving 33 kV and 220 kV underground cabling. The assignment is Laser Power’s first 220 kV underground transmission project, and management said successful delivery could establish a specialised execution reference for land-constrained urban locations where overhead expansion is difficult.
How do the Power Grid and CESC orders change Laser Power’s business?
The orders extend Laser Power beyond the distribution-grade products and EPC work that management said had previously defined its business. The Power Grid contract applies the manufacturing platform to specialised conductors and reconducting, while the CESC project combines cable-related work with EPC execution at 33 kV and 220 kV.
Laser Power’s order book on September 30, 2026 was split between manufacturing and EPC, giving it activity in both operating businesses. Manufacturing represented Rs 1,303 crore of the Rs 2,543 crore total, compared with Rs 1,240 crore for EPC, although the call did not disclose how the Power Grid and CESC orders were allocated within those segments.
During Q2 FY27, Laser Power secured about Rs 357 crore of new orders, taking H1 FY27 inflows to about Rs 449 crore. Management said its H2 FY27 priority is to execute the Power Grid and CESC projects, use the resulting references to pursue further transmission opportunities, and maintain discipline on working capital and capital allocation.
Got a follow-up? Ask IRIS
What did Laser Power’s Q2 FY27 performance show?
Laser Power reported standalone revenue from operations of Rs 628 crore in Q2 FY27, up 20.5% sequentially and 2.1% year on year. Manufacturing revenue increased 29.9% to Rs 524 crore from Rs 404 crore in Q2 FY26, while EPC revenue fell to Rs 104 crore from Rs 212 crore, changing the quarter’s revenue mix toward manufacturing.
Management attributed the lower EPC revenue primarily to heavy rain in project areas that delayed execution. It said deferred revenue and earnings before interest, tax, depreciation and amortisation, or EBITDA, are expected to recover in coming quarters as projects progress, which is a management expectation rather than a reported recovery as of September 30, 2026.
EBITDA was Rs 76 crore, up 15.2% from Q1 FY27 but down from Rs 80 crore a year earlier, and the margin declined to 12.1% from 13.0%. Profit after tax was Rs 31 crore, up 44% sequentially and compared with Rs 32 crore in Q2 FY26.
For H1 FY27, revenue from operations reached Rs 1,150 crore, up 7.5% year on year, while EBITDA increased 7.0% to Rs 142 crore and the EBITDA margin was 12.3%. Manufacturing revenue rose 13.8% to Rs 906 crore, whereas EPC revenue declined 10.7% to Rs 243 crore, showing that manufacturing growth offset the lower weather-affected EPC contribution.
How is Laser Power funding execution and capacity plans?
Laser Power used about Rs 490 crore of initial public offering proceeds in Q2 FY27 to repay identified borrowings. Finance cost declined sequentially to about Rs 33 crore from Rs 36 crore in Q1 FY27, while total borrowings were about Rs 499 crore on September 30, 2026; management said Q2 included only a partial-period benefit because repayment was completed during the quarter.
Working capital was about Rs 1,159 crore at September 30, 2026, compared with about Rs 1,059 crore at the end of Q1 FY27. Inventory increased to about Rs 946 crore from Rs 710 crore amid rain-related execution delays, while trade receivables fell to about Rs 1,382 crore from Rs 1,416 crore and working-capital days declined to 166 from 183.
Laser Power received a provisional letter of intent and in-principle approval for about 40 acres at Vidyasagar Industrial Park in Kharagpur from West Bengal Industrial Development Corporation Limited. The long-term-lease site is intended for an integrated power cable and conductor facility, including higher-value transmission products, with management saying the timing and scale of investment will be phased according to demand visibility, customer requirements, product strategy and expected returns.
Conclusion
Laser Power’s Q2 FY27 orders provide its first commercial credentials in two transmission applications: HTLS reconducting through the Rs 72.76 crore Power Grid contract and 220 kV underground EPC through the Rs 44 crore CESC Limited order. The financial picture was mixed, as manufacturing revenue rose to Rs 524 crore while rain-related EPC delays reduced EPC revenue to Rs 104 crore.
The next disclosures to watch are execution of the Power Grid and CESC Limited projects, progress on the phased Kharagpur facility and conversion of inventory into cash. Management targets an improvement of about 25 to 40 working-capital days by Q4 FY27 and expects operating cash flow to turn positive in FY27 as manufacturing dispatches, EPC certification and billing advance.