Megatherm targets Rs 110 crore transformer revenue by FY27
Key highlights
- Megatherm targets Rs 110 crore of transformer revenue in FY27, compared with Rs 50 crore cited for FY25.
- Megatherm’s 13.2 MVA inverter-duty transformer received CPRI Bhopal validation in August 2025.
- Megatherm targets 150 MVA to 160 MVA of transformer capacity per month by H2 FY27.
- Megatherm cites 2,000 MVA Kharagpur capacity that could rise to 3,000 MVA with minimal investment.
powered by IRIS

Megatherm Induction Limited is targeting Rs 110 crore of transformer revenue in FY27, compared with Rs 50 crore in FY25, after its 13.2 MVA inverter-duty transformer received CPRI Bhopal validation in August 2025. Megatherm identifies inverter-duty transformers as its primary revenue engine for renewable-energy diversification, with vendor approvals still in progress.
Know Megatherm Induction inside out
Results, valuation, peers and who's buying, in one view.
What transformer revenue is Megatherm targeting by FY27?
Megatherm is targeting Rs 110 crore of transformer revenue in FY27, up Rs 60 crore from the Rs 50 crore transformer revenue figure it cites for FY25. The FY27 target covers inverter-duty transformers, power transformers, distribution transformers and industrial transformers, rather than inverter-duty transformers alone.
The presentation separately identifies Rs 40 crore of FY27 revenue potential from induction furnace transformers. Together, the Rs 110 crore target for IDT, power, distribution and industrial products and the Rs 40 crore induction furnace transformer potential amount to Rs 150 crore, although Megatherm does not provide a product-level revenue split.
Megatherm also states a Rs 250 crore target by FY31, but the presentation does not provide yearly revenue milestones between FY27 and FY31. The FY27 figure is therefore a management target, supported by the planned capacity ramp, product testing and approval process rather than by disclosed orders or an order book.
What has Megatherm completed for its solar transformer launch?
Megatherm says its 13.2 MVA, or megavolt-amperes, inverter-duty transformer passed CPRI Bhopal validation in August 2025. This testing milestone supports its plan to supply inverter-duty transformers, or IDTs, and multi-winding transformers to renewable-energy applications.
Megatherm lists IDTs and multi-winding transformers in a 5 MVA to 40 MVA range. Its broader transformer offering includes converter transformers for induction melting and heating equipment, alternating-current to direct-current drives and industrial rectifiers, alongside electric arc furnace, ladle refining furnace, distribution and power transformers.
Vendor approvals remain in progress, according to the presentation. The disclosed CPRI validation does not establish production orders, customer acceptance or FY27 sales, so completion of those approvals is a stated step between the August 2025 product test and the Rs 110 crore FY27 target.
Megatherm places the Indian renewable transformer market opportunity at about Rs 30,000 crore and links its strategy to India’s 500 GW renewable-energy capacity target for 2030. It names Enersure, Renew, Jackson and Tata Solar as clients, but does not disclose contract values, order timing or whether these customers have approved the new IDT range.
Got a follow-up? Ask IRIS
What transformer capacity is Megatherm planning by H2 FY27?
Megatherm is targeting transformer capacity of 150 MVA to 160 MVA per month by H2 FY27. The target is supported by its transformer facility at Vidyasagar Industrial Park, Kharagpur, West Bengal, which the presentation says has 2,000 MVA capacity.
The Kharagpur facility is intended to manufacture converter-duty transformers, IDTs, ladle refining furnace and arc furnace transformers, and industrial or power transformers. Megatherm specifies that the industrial and power transformer range will extend to 50 MVA in the 132 kilovolt class.
Megatherm says the 2,000 MVA facility capacity can increase to 3,000 MVA with minimal investment. The presentation does not define the time basis for the 2,000 MVA figure, so it cannot be directly compared with the 150 MVA to 160 MVA monthly target.
The company has also initiated construction of a fourth production facility after assessing market feedback and its current order pipeline. Megatherm says that project will scale transformer manufacturing capacity, but it does not disclose its commissioning date, cost or incremental MVA capacity.
What economics does management expect from inverter-duty transformers?
Megatherm cites an EBITDA margin of about 15% for IDTs, compared with an 8% to 10% industry range cited in its presentation. EBITDA means earnings before interest, tax, depreciation and amortisation, and the 15% figure is management’s stated IDT margin expectation rather than a reported FY27 outcome.
The company says it has invested Rs 30 crore of capital expenditure in the transformer initiative and expects asset turnover of 5 times. Megatherm does not specify the period for the expected turnover, the asset base included in the calculation or whether the measure applies only to the Rs 30 crore investment.
The FY25-to-FY27 comparison shows that management expects transformer revenue to rise from Rs 50 crore to Rs 110 crore. The separate Rs 40 crore induction furnace transformer potential indicates that the renewable-focused IDT expansion is being pursued alongside furnace transformer applications.
Megatherm says its differentiation will come from testing infrastructure and export readiness. Its presentation also cites more than 3,000 installations in over 50 countries across five continents, but it does not disclose export orders, overseas approvals or revenue targets specifically for IDTs.
Conclusion
Megatherm’s disclosed plan combines its August 2025 CPRI Bhopal validation of a 13.2 MVA IDT with a target of Rs 110 crore in FY27 transformer revenue, versus Rs 50 crore in FY25. That target includes IDTs and power, distribution and industrial transformers, while Rs 40 crore of separate potential is identified for induction furnace transformers.
The next disclosed points to watch are vendor approvals, the 150 MVA to 160 MVA monthly capacity target by H2 FY27 and progress on the fourth production facility. Management also says the Kharagpur facility’s 2,000 MVA capacity can rise to 3,000 MVA with minimal investment, while its Rs 250 crore FY31 target has no disclosed annual milestones.