Midwest Limited cuts FY27 quartz outlook to Rs 90 crore
Key highlights
- Midwest expects about Rs 90 crore of FY27 quartz revenue on a comfort basis, versus prior Rs 100 crore to Rs 120 crore guidance.
- Q2 quartz revenue was Rs 13.5 crore, compared with almost Rs 3 crore in Q1.
- Midwest plans quartz output of 25,000 tonnes to 30,000 tonnes in Q3 and 35,000 tonnes to 40,000 tonnes in Q4.
- The regular Phase 2 quartz expansion targets Q2 next year, while HPQ may be commissioned in Q3 or Q4 next year.
powered by IRIS

Midwest Limited expects about Rs 90 crore of quartz revenue in FY27, replacing Rs 100 crore to Rs 120 crore as the comfortable planning range after Q2 generated Rs 13.5 crore. Management said an outcome towards Rs 100 crore depends on reaching the 15,000-tonne mark early in January.
Know Midwest inside out
Results, valuation, peers and who's buying, in one view.
Why did Midwest cut its FY27 quartz revenue outlook?
Midwest said about Rs 90 crore is the FY27 quartz revenue figure investors can use on a comfort basis, below the Rs 100 crore to Rs 120 crore top-line range discussed in the preceding quarter. Management linked the revised framing to projected volume and an average selling price of about Rs 9,500 to Rs 9,600 per tonne, while saying revenue could move towards Rs 100 crore if it reaches 15,000 tonnes early in January.
The lower comfortable outcome follows a ramp from a small Q1 base rather than a stated change in quartz pricing. Midwest said Q1 quartz revenue was almost Rs 3 crore, compared with Rs 13.5 crore in Q2, when it sold more solar-grade material. Management put Q2 realisation at close to Rs 8,500 per tonne and said the full-year mix of solar and engineered-stone quartz should realise around Rs 9,000 per tonne, plus or minus.
The comparison shows that Q2 quartz revenue was more than four times the nearly Rs 3 crore reported in Q1, but management did not treat that early ramp as sufficient to retain the prior Rs 100 crore to Rs 120 crore range as its base case. The distinction matters because the Rs 100 crore possibility remains conditional on the January volume milestone, whereas Rs 90 crore is management’s stated comfortable expectation.
How is Midwest planning to raise quartz output?
Midwest plans quartz output of 25,000 tonnes to 30,000 tonnes in Q3 and 35,000 tonnes to 40,000 tonnes in Q4, after a Q2 range of 15,000 tonnes to 20,000 tonnes. Management said Q1 output was only about 3,000 tonnes to 4,000 tonnes, and described Q2 production as four times the Q1 level and in line with its internal plan.
Management separately said it expects to reach 15,000 tonnes by March and then work towards consistent output of 18,000 tonnes over the following year. Its stated objective for the next year is to approach double the current year’s quartz volume. The company identified a progression through 12,000 tonnes, 15,000 tonnes and 18,000 tonnes as the operational path that supports its revenue and margin objectives.
The Q3 and Q4 plan would make the second half more heavily weighted than the first half, consistent with management’s broader comment that Q3 and Q4 should be stronger than Q1 and Q2. Midwest also said granite volume rose about 14% in the first half and approximately 7% in the quarter, providing a separate operating comparison while quartz scales from its lower initial base.
Got a follow-up? Ask IRIS
When will Midwest commission Phase 2 and HPQ?
Midwest expects the regular Phase 2 quartz expansion to be commissioned by Q2 next year, while its high-purity quartz, or HPQ, line may follow in Q3 or Q4 next year. The company said it has started constructing the Phase 2 building and placing machinery orders after stabilising the existing plant at 9,000 tonnes to 10,000 tonnes, according to management.
The commissioning sequence separates regular quartz products for solar and engineered stone from the HPQ line. Midwest said the regular expansion will come first and HPQ will take about one additional quarter, so Phase 2 should not be read as a single commissioning milestone. The HPQ target remains a range between Q3 and Q4 next year rather than a fixed date.
Management’s stated order of execution is relevant to the revenue plan because the FY27 Rs 90 crore expectation is based on the current plant’s volume ramp and average price of Rs 9,500 to Rs 9,600 per tonne. The Phase 2 regular line and the HPQ line are therefore future capacity milestones, not announced contributors to the current FY27 comfortable outcome.
What supports Midwest’s quartz demand and profitability plan?
Midwest said domestic demand can support its ramp to 12,000 tonnes, 13,000 tonnes and 15,000 tonnes before it pursues exports more aggressively. Engineered-stone makers are the principal customer group, with management citing about 40 to 50 slab manufacturers in India. In solar glass, it named Triveni as a customer that is doubling capacity and said it began supplying Gold Plus in Bellary during the quarter.
Management said one solar-glass customer could take 60,000 tonnes to 70,000 tonnes a year at the company’s current scale, particularly when higher-quality quartz enables continuous furnace operation without material mixing. Midwest has also positioned products in Thailand, Vietnam and Europe because it was concerned about potential United States tariffs on India and China. It said shipments are continuing, although exports may not become aggressive until output exceeds 15,000 tonnes.
Midwest expects quartz to report positive earnings before interest, tax, depreciation and amortisation, or EBITDA, and positive profit after tax, or PAT, in the second half of FY27. Management said first-half quartz EBITDA was close to 12%, but noted that Q2 profitability included proceeds from material treated as contaminated and scrapped in Q1 that was later processed and sold. That item contributed to the reported Q2 EBITDA and limits direct extrapolation from that quarter.
At output of 15,000 tonnes to 18,000 tonnes, management expects quartz EBITDA to be above that of the traditional granite business. It said planned savings from 10 electric trucks could amount to Rs 2 crore to Rs 2.5 crore annually, while 6 megawatts of tied-up captive solar power could save another Rs 2 crore a year. Management said the combined Rs 4 crore to Rs 5 crore annual saving estimate excludes quartz because electric trucks are currently used in granite operations.
Conclusion
Midwest’s updated quartz plan places Rs 90 crore, rather than Rs 100 crore to Rs 120 crore, at the centre of its FY27 revenue expectation. The change reflects an operating ramp from about 3,000 tonnes to 4,000 tonnes in Q1 to 15,000 tonnes to 20,000 tonnes in Q2, along with a sales mix spanning solar and engineered-stone products.
The next disclosed markers are Q3 output of 25,000 tonnes to 30,000 tonnes, Q4 output of 35,000 tonnes to 40,000 tonnes and the 15,000-tonne mark targeted by March. Management’s commissioning plan calls for the regular Phase 2 line by Q2 next year and the HPQ line in Q3 or Q4 next year, while the January timing of the 15,000-tonne threshold remains relevant to a move towards Rs 100 crore.