NHPC targets Subansiri completion by June 2027 at Rs. 30,072 crore
Key highlights
- NHPC had commissioned 1,250 MW of the 2,000 MW Subansiri Lower Project by 23 October 2026.
- NHPC expects the final 250 MW Subansiri Lower unit to be commissioned by June 2027.
- Subansiri Lower had incurred Rs. 26,936 crore against an anticipated cost of Rs. 30,072 crore at September 2026.
- NHPC’s Half Year FY27 revenue from operations rose 26% to Rs. 8,291 crore.
powered by IRIS

NHPC Limited targets full commissioning of its 2,000 megawatt (MW) Subansiri Lower Project by June 2027, following 1,250 MW commissioned by 23 October 2026. Management said Rs. 26,936 crore, or 90% of the Rs. 30,072 crore anticipated cost, had been spent by September 2026 and no further cost increase was expected.
Know NHPC inside out
Results, valuation, peers and who's buying, in one view.
When will NHPC complete Subansiri Lower?
NHPC plans to commission two additional 250 MW Subansiri Lower units during FY27 and the final 250 MW unit by June 2027. The project has eight units of 250 MW each, of which five had entered service, taking commissioned capacity to 1,250 MW. The fifth unit was successfully commissioned on 23 October 2026.
The schedule would make Subansiri Lower India’s biggest hydroelectric project at 2,000 MW, according to management. The remaining three units represent 750 MW, or 37.5% of the plant’s total capacity, making the commissioning of those units the outstanding execution requirement under the June 2027 plan.
Subansiri Lower’s phased commissioning was also cited as a contributor to NHPC’s operating improvement in the first half of FY27. Generation reached 23,741 million units (MU) in Half Year FY27, up 2,875 MU, or 14%, from 20,866 MU a year earlier; management named partial Subansiri commissioning, higher generation at Parbati-II and Parbati-III, Karnisar Solar generation, and Teesta-V’s return to commercial operation as reasons.
What is NHPC’s Subansiri Lower cost position?
NHPC said it does not anticipate a further rise in Subansiri Lower’s anticipated cost of Rs. 30,072 crore. Expenditure was Rs. 26,936 crore at 30 September 2026, leaving Rs. 3,136 crore between spending to date and the stated anticipated cost while three 250 MW units remained to be commissioned.
Management’s no-increase expectation is a forward-looking statement tied to the project’s 90% cost-incurred position and its June 2027 final-unit schedule. It does not change the fact that Rs. 3,136 crore remained to be spent under the current anticipated cost as of September 2026, while the project still required commissioning of 750 MW.
Part commissioning also changed how Subansiri affected NHPC’s reported expenses. Half-year employee benefit expense increased by Rs. 43 crore to Rs. 793 crore, mainly because expenses for the commissioned portion began being charged to profit and loss. Finance cost increased by Rs. 623 crore to Rs. 1,162 crore, principally because interest on Subansiri-related loans was charged to profit and loss after partial commissioning.
Got a follow-up? Ask IRIS
Which other NHPC projects have near-term commissioning dates?
NHPC has identified Rangit-IV, Pakal Dul and Kiru as projects with commissioning milestones before or during FY27. Jalpower Corporation Limited’s 120 MW Rangit-IV had reached 98% physical progress, completed boxing-up of all three units and begun reservoir filling; its expected commissioning date was December 2026. Management also said the merger of Jalpower Corporation Limited, or JPCL, with NHPC was in process, with a Second Motion Application filed with the Ministry of Corporate Affairs.
Through Chenab Valley Power Projects Limited, or CVPPL, NHPC targets two 1,000 MW Pakal Dul units by March 2027 and full commissioning by June 2027. Pakal Dul was 89% physically complete and had incurred Rs. 10,183 crore against an estimated Rs. 12,728 crore by September 2026; reservoir filling was planned for the end of December 2026. Kiru, a 624 MW project, was 92% complete and targeted all units by March 2027 after reservoir filling was due to start in November 2026.
The projects have different remaining-work profiles. Rangit-IV had spent Rs. 1,916 crore against an estimated Rs. 2,057 crore, while Kiru had spent Rs. 4,105 crore against Rs. 5,409 crore. By contrast, the 540 MW Kwar project was 42% physically complete, had spent Rs. 2,079 crore of its Rs. 4,526 crore estimated cost and was scheduled for May 2028.
How does Subansiri commissioning affect NHPC’s operations?
Subansiri’s partial commissioning helped lift NHPC’s plant availability factor (PAF) to 86.67% in Half Year FY27 from 81.10% in the corresponding previous period. PAF measures the availability of generating capacity. In the second quarter of FY27, PAF was 92.24%, compared with 78.58% a year earlier, with management also citing improved Parbati-II availability and Teesta-V’s resumed operations.
Revenue from operations increased 26% to Rs. 8,291 crore in Half Year FY27 from Rs. 6,579 crore in the prior-year period. Profit after tax rose 27% to Rs. 2,645 crore from Rs. 2,086 crore. In Q2 FY27, revenue rose 33% to Rs. 4,482 crore, compared with Rs. 3,365 crore a year earlier, reflecting the same higher-generation drivers cited by management.
The gain in operating revenue occurred alongside lower other income and higher financing charges. Other income declined Rs. 156 crore to Rs. 338 crore in Half Year FY27 because the previous corresponding period included insurance-claim income. Generation expense declined Rs. 40 crore to Rs. 552 crore, which management attributed to lower water cess for plants in the U.T. of J&K and no water cess in Uttarakhand following a High Court verdict in NHPC’s favour.
Conclusion
NHPC’s disclosed Subansiri plan sets a specific path from 1,250 MW commissioned in October 2026 to the full 2,000 MW by June 2027, with two units targeted in FY27 and one thereafter. The company’s current anticipated cost remains Rs. 30,072 crore, while the project’s partial operation has already contributed to higher Half Year FY27 generation, revenue and PAF.
The next milestones to watch are commissioning of the two further Subansiri units during FY27, the final unit by June 2027, and whether expenditure stays within the remaining Rs. 3,136 crore against the anticipated cost. Management also plans reservoir filling for Pakal Dul by the end of December 2026 and targeted full Kiru commissioning by March 2027, creating several near-term execution events.