NLC India puts 4 MW hydrogen project into implementation
Key highlights
- NLC India won four partially explored critical-mineral blocks, with two each in Chhattisgarh and Telangana.
- NLC India's 4 MW Neyveli green-hydrogen project is under implementation with an 18-month timeline.
- NLC India proposes 4 MTPA of beach-sand wet-concentration capacity with tentative investment of Rs 200 crore.
- NLC India's proposed surface gasification capacities are 0.6 MTPA at Barsingsar, 2.0 MTPA at Pachwara and 3.0 MTPA at Machhakata.
powered by IRIS

NLC India Limited has put its 4 MW solar-input green-hydrogen project at Neyveli into implementation, while completing pre-exploration in two Chhattisgarh critical-mineral blocks and beginning a rare-earth-from-fly-ash pilot. Its November 2026 presentation shows diversification projects ranging from conceptualisation and pre-feasibility to implementation.
Know NLC India inside out
Results, valuation, peers and who's buying, in one view.
What is NLC India doing in critical minerals?
NLC India has won four partially explored critical-mineral blocks, comprising two each in Chhattisgarh and Telangana. It has completed pre-exploration activities in the two Chhattisgarh blocks, whereas the presentation reports only the award status for the Telangana blocks. The presentation does not identify the minerals, reserve estimates, investment requirement or production timetable for the four blocks.
NLC India has also signed a memorandum of understanding with IPICOL for beach-sand mineral mining and processing facilities in Odisha, and another with KABIL for acquiring overseas critical-mineral blocks. These arrangements add domestic beach-sand processing and potential overseas acquisitions to the four awarded blocks, but the presentation gives no transaction terms, locations of overseas blocks or expected output. It separately lists beneficiation studies for high-purity silica from lignite-associated sand among 13 research projects with institutions.
Beach sand remains at a pre-feasibility stage. NLC India proposes a first-stage wet concentration plant with 4 million tonnes per annum (MTPA) capacity and a heavy-mineral separation plant with 0.4 MTPA feed capacity. The proposal requires 1,500 hectares, or 3,700 acres, and carries a tentative investment of Rs 200 crore with potential employment of 400 people.
How far has NLC India progressed with coal gasification?
NLC India has proposed surface coal-gasification projects at Barsingsar, Pachwara and Machhakata, but none is described as under construction. The disclosed capacities are 0.6 MTPA at Barsingsar, 2.0 MTPA at Pachwara and 3.0 MTPA at Machhakata. Machhakata is the largest of the three proposals, with five times Barsingsar's stated capacity.
The three sites are at different preparation stages. Review of a draft report is under way for Barsingsar, while NLC India says a consultant will be engaged to prepare a report for Machhakata. Pachwara is identified as proposed at 2.0 MTPA, but the presentation gives no corresponding report status, capital expenditure, implementation date or expected product mix.
NLC India has signed a collaboration with IFFCO and IPICOL for a coal-gasification-based fertiliser production facility in Odisha. Separately, the Ministry of Coal has reserved two Gujarat lignite blocks, Dipside Tadeshwar and Dungra, and Dipside Valia and Rajpardi, for underground coal gasification by NLC India. The company says 90% of lignite in these blocks is within 300 metres and that it is exploring possibilities under Ministry of Coal guidelines.
Got a follow-up? Ask IRIS
What is the status of NLC India's green-hydrogen project?
NLC India is implementing a green-hydrogen project at Neyveli using 4 MW of solar input. A letter of award has been issued, the contract has been signed and an owner's engineering consultant has been appointed. The kick-off meeting and geotechnical investigations have also been completed, placing the project beyond the evaluation stage in the presentation.
The Neyveli project has an 18-month timeline and a planned plant life of 25 years. NLC India discloses the 4 MW solar input but not hydrogen production capacity, offtake arrangements, project cost or a commissioning month. The disclosed information therefore records implementation activity rather than operating-output or financial-contribution estimates.
NLC India's research programme also lists a 4 MW proton-exchange-membrane electrolyser-based green-hydrogen plant under implementation. Its 13 institutional projects include bio-hydrogen from biomass with Alagappa University and renewable hydrogen from biogas via parabolic solar heating with Annamalai University. These projects use biomass and biogas pathways, compared with the Neyveli project's solar-input configuration.
How is NLC India pursuing rare-earth extraction from fly ash?
NLC India has classified rare-earth extraction from fly ash as implementation underway through a pilot with the Bhabha Atomic Research Centre. The diversification presentation states that a letter of award has been issued, while the research section says NLC India signed a memorandum of understanding with the centre to pilot rare-earth-element extraction. Neither disclosure gives pilot throughput, recovery rates, commercial capacity or a results date.
The fly-ash pilot sits alongside four research projects with Annamalai University, including metal-supported solid oxide fuel cells from lignite fly ash, lignite humic acid for brackish-water aquaculture, renewable hydrogen from biogas and automated conveyor-belt monitoring. NLC India also says it is progressing alternate uses of lignite beyond conventional power generation through these projects.
NLC India's Centre for Applied Research and Development received National Accreditation Board for Testing and Calibration Laboratories accreditation under ISO/IEC 17025:2017 in December 2025. It received recognition as an in-house research and development unit from the Department of Scientific and Industrial Research in January 2026. The active research programme also includes a lab-scale carbon-capture system and biomass-pellet co-firing with coal and lignite in line with Ministry of Power directives.
Conclusion
NLC India's diversification programme combines projects at materially different stages. Four critical-mineral blocks have progressed to completed pre-exploration activity in Chhattisgarh, the 4 MW Neyveli hydrogen project is under implementation, and rare-earth extraction remains a pilot. Beach sand and coal gasification are earlier-stage proposals supported by capacities, feasibility work, site requirements and collaborations rather than commercial operating schedules.
The next disclosed milestones are commissioning of the Neyveli Neer project by November 2026, progress against the hydrogen project's 18-month timeline, and further report work for Barsingsar and Machhakata. NLC India has also identified Rs 200 crore as tentative investment for the beach-sand proposal, while the rare-earth pilot has yet to disclose capacity, recovery results or a commercialisation timetable.